Maps

Intelligent Transport System Map

There are three main elements to the Forth Replacement Crossing project.

View Fife ITS map A detail

View Principal Contract map B detail

View M9 Junction 1A map C detail

 A. Fife ITS Contract

What: Installation of Intelligent Transport System gantries on M90 between the Admiralty and Halbeath Junctions in Fife and provision for southbound hard shoulder running for buses

Who:John Graham (Dromore) Ltd

When: Construction began in autumn 2011 and was completed in December 2012.

 

Map of Fife ITS contract

 

 B. FRC Principal Contract

What: Construction of new cable-stayed Queensferry Crossing across the Forth and connecting roads

Who: Forth Crossing Bridge Constructors consortium, comprising Hochtief, Dragados, American Bridge International and Morrisons

When: Construction began in autumn 2011 and is scheduled for completion in May 2017

 

Forth Replacement Crossing Principal Contract map

 

C. M9 Junction 1a Contract

What: Upgrade and improvements to M9 Junction 1a at Kirkliston including new west facing slip roads to the M9

Who: Sisk Roadbridge Civil Engineering Ltd

When: Construction began in autumn 2011 and was completed ahead of schedule in February 2013.

Map of M9 Junction 1a

Employers Delivery Team

What: The Employers Delivery Team (EDT) operates on site across all three contracts to monitor progress, quality and adherence to the Forth Crossing Act.

Who: Transport Scotland and its consultants, Jacobs Arup

When: The EDT is already co-located on site and will remain in place until the successful completion of the project