Description of main environmental impacts and proposed mitigation
Air quality
Construction activities associated with the proposed works have the potential to temporarily cause local air quality impacts. The main sources are likely to be dust generated by cold milling in preparation of carriageway resurfacing, as well as exhaust emissions from ancillary plant and vehicles. As a result, there is potential for dust, particulate matter, and exhaust emissions to be emitted to the atmosphere. However, taking into account the nature and scale of the works and the following mitigation measures, the risk of significant impacts to air are considered to be low.
- A water-assisted dust sweeper will sweep the carriageway after dust-generating activities, and waste will be contained and removed from site as soon as is practicable.
- Materials that have a potential to produce dust will be removed from site as soon as possible, and vehicles that remove cold-milled material from site will have sheeted covers.
- Ancillary plant, vehicles and non-road mobile machinery (NRMM) will have been regularly maintained, paying attention to the integrity of exhaust systems.
- Ancillary plant, vehicles and NRMM will be switched off when stationary to prevent exhaust emissions (e.g., there will be no idling vehicles).
- Cutting, grinding, and sawing equipment (if required) will be fitted or used in conjunction with suitable dust suppression techniques e.g., local exhaust ventilation system that fits directly onto tools.
- Regular monitoring (e.g., by engineer or Clerk of Works) will take place when activities generating air pollution are occurring. In the unlikely event that unacceptable levels of air pollution are emanating from the site, the operation will, where practicable, be modified and re-checked to verify that the corrective action has been effective. Actions to be considered include: (a) minimizing cutting and grinding on-site, (b) reducing the operating hours, (c) changing the method of working, etc.
- All delivery vehicles carrying material with dust potential will be covered when travelling to or leaving site, preventing the spread of dust beyond the work area.
- Material stockpiles will be reduced as far as is reasonably practicable by using a ‘just in time’ delivery system. All material will also be stored on made ground.
- Any stockpiled material on site will be monitored daily to ensure no risks of dust emissions exists.
- Materials will be removed from site as soon as is practicable.
- Good housekeeping will be employed throughout the work.
With the above mitigation measures in place, it is anticipated that any air quality effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this Record of Determination (RoD).
Cultural Heritage
Although there are records of cultural heritage interest within the scheme and within 300m of the scheme extents, any excavation works associated with the scheme are restricted to the already engineered carriageway boundary, and as such the potential for changes to known or exposure of unknown cultural heritage features is considered to be low; construction of the A9 road corridor is likely to have removed any archaeological remains that may have been present.
As standard, the following good practice measures will be in place to reduce the risk of impacts to undiscovered features of cultural heritage interest:
- There will be no storage of vehicles, plant, or materials against any buildings, walls or fences.
- Should any unexpected archaeological evidence be discovered, works will stop temporarily in the vicinity and the BEAR Scotland Environment Team contacted for advice. Historic Environment Scotland will be contacted for advice as required.
- People, plant, and materials will, as much as is reasonably practicable, only be present on areas of made / engineered ground. Where access out with these areas is required for the safe and effective completion of the scheme, it will be reduced as much as is reasonably practicable and ideally be limited to access on foot.
With the above mitigation measures in place, it is anticipated that any cultural heritage effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Landscape and visual effects
There will be a short-term impact on the landscape character and visual amenity of the site as a result of the presence of construction plant, vehicles, and TM. The schemes fall within the Cairngorms National Park and the Killiecrankie Duals to Single scheme is additionally located within the Loch Tummel NSA.
However, people, ancillary plant, vehicles, NRMM and materials are restricted to areas of made/engineered ground on the A9, and construction works are programmed to be undertaken at night on a rolling programme. As such, the visual impact of the works will be reduced. Upon completion of the works, no residual impacts are anticipated e.g., when complete the visual appearance will remain largely unaffected, with a renewed road surface being the only discernible change. The Cairngorms National Park Authority will be notified of the proposed works and advised of any road closures/diversion routes in advance of the works.
In addition, the following mitigation measures will be put in place during works:
- Throughout all stages of the works, the site will be kept clean and tidy, with materials, equipment, plant and wastes appropriately stored, reducing the landscape and visual effects as much as possible.
- Works will avoid encroaching on land and areas where work is not required or not permitted. This includes general works, storage of equipment/containers and parking.
- Where applicable, upon completion of the works, any damage to the local landscape will be reinstated as much as is practicable.
- The site will be left clean and tidy following construction.
With the above mitigation measures in place, it is anticipated that any landscape and visual effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Biodiversity
Activities undertaken on site could potentially have a temporary adverse impact on biodiversity in the area as a result of an increased vehicle presence and the potential for disturbance to protected species and pollution of habitats.
The River Tay SAC, Aldclune and Invervack Meadows SSSI and Pass of Killiecrankie SSSI lie within 300m of the schemes, with the Tulach Hill and Glen Fender Meadows SAC/SSSI and Cairngorms Massif within 1km.
BEAR Scotland has produced a Habitats Regulations Appraisal (HRA) Proforma which concluded that none of the proposed works will result in Likely Significant Effects (LSE) on the qualifying features of these sites.
All relevant good practice measures will be detailed in the SEMP and adhered to during works. As such, no significant impacts on the designated European sites are anticipated based on the following factors:
- All works are minor, transient, highly localised, and restricted to the A9 carriageway surface with only resurfacing being undertaken. There will be no in-stream or verge works; therefore, no direct impacts to any of the above European sites are anticipated.
- There is no requirement for land take (or resources) or site clearance from within the sites and no works are required within any part of the site boundaries.
- Standard good practice measures to prevent pollution and reduce noise and lighting associated with works will be in place.
- The works will not result in significantly higher levels of noise or lighting than existing levels of traffic on the A9.
- Works will not promote the known negative pressure on the various designated species.
- No significant dust, particulate matter, and exhaust emissions sources will be introduced by the works, and standard pollution prevention measures will be in place during works.
Several records of native injurious plants are recorded in proximity to the schemes. However, the works are confined to the trunk road boundary, there is no requirement to import or excavate the topsoil. As such, there is limited potential to spread or introduce INNS, invasive native perennials, or injurious flowering plant species.
Pollution controls and good practice measures to reduce impacts of works on the local environment will be detailed in the Site Environmental Management Plan (SEMP) and adhered to on site. Any protected species in the area are likely to be accustomed to road noise on the A9 and the schemes are of short duration (5 nights for each scheme) and will be undertaken on a rolling programme. Therefore, with the following mitigation measures in place, the risk of significant impacts on biodiversity are considered to be low:
- Works will be strictly limited to areas required for access and to carry out the works. Unnecessary encroachment onto terrestrial or aquatic areas will not be tolerated.
- All construction operatives will be briefed through toolbox talks prior to works commencing, which will be included in the SEMP. The toolbox talks will provide information on the legislation, general ecology, and best practice measures for relevant protected species.
- Site personnel will remain vigilant for the presence of any protected species throughout the works period. Should a protected species be noted during construction, works will temporarily halt until the species has sufficiently moved on. Any sightings of protected species will be reported to the BEAR Scotland Environmental Team.
- Artificial lighting will be directed away from areas of woodland and waterbodies as far as is safe and reasonably practicable.
- Personnel will remain vigilant for the presence of INNS or injurious weeds in road verges throughout the works period. Should any INNS be identified in working areas, works will be restricted to a 7m buffer of any growth where reasonably practicable.
- A ‘soft start’ will be implemented on site each day. This will involve switching on vehicles and checking under/around vehicles and the immediate work area for mammals prior to works commencing to ensure none are present and that there is a gradual increase in noise.
- Any excavations, exposed pipes/drains, or areas where an animal could become trapped (e.g. storage containers) will be covered over when not in use, at the end of each shift, and following completion of the works to avoid animals falling in and becoming trapped.
- If fencing is utilised at any point during the works, a gap of 200mm from ground level will be provided, allowing free passage for mammals and preventing entrapment.
With the above mitigation measures in place, it is anticipated that any biodiversity effects associated with the proposed works are unlikely to be significant.
Material assets and waste
There is potential for impacts as a result of resource depletion through use and transportation of new materials. However, materials will be sourced locally where possible and the following mitigation measures will be put in place:
- Materials will be sourced from recycled origins as far as reasonably practicable within design specifications.
- Care will be taken to order the correct quantity of required materials to prevent the disposal of unused materials.
- Where possible, minimal packaging will be requested on required deliveries to reduce unnecessary waste and production of packaging materials.
There is potential for impacts during works as a result of the improper storage or disposal of waste. The following mitigation measures will be put in place:
- The waste hierarchy (Reduce, Reuse, Recycle and Dispose) will be employed throughout the construction works.
- The subcontractor will adhere to waste management legislation and ensure they comply with their Duty of Care.
- Containment measures will be in place to prevent debris or pollutants from entering the surrounding environment.
- Road planings will be re-used or recycled under a SEPA Paragraph 13(a) waste exemption and in line with BEAR Scotland’s Procedure 126: The Production of Fully Recovered Asphalt Road Planings.
- All wastes and unused materials will be removed from site in a safe and legal manner by a licensed waste carrier upon completion of the works. The appointed waste carrier will have a valid SEPA waste carrier registration, a copy of which will be provided to and retained by BEAR Scotland as early as possible.
- All appropriate waste documentation will be present on site and be available for inspection. A copy of the Duty of Care paperwork will be provided and filed appropriately in accordance with the Code of Practice (as made under Section 34 of Environmental Protection Act 1990 as amended).
- Re-use and recycling of waste will be encouraged, and the subcontractor will be required to fully outline their plans and provide documentary evidence for waste arising from the works (e.g., waste carrier’s licence, transfer notes, and waste exemption certificates).
- Staff will be informed that littering will not be tolerated. Staff will be encouraged to collect any litter seen on site.
- Where applicable, all temporary signage will be removed from site on completion of the works.
- If the works encounter coal tar, then this will be appropriately processed in line with Transport Scotland’s Guidance Note on Dealing with Coal Tar Bound Arisings. This will include:
- Coal tar contaminated road planings will be classified as a Special Waste.
- All waste will be appropriately segregated, with coal tar contaminated planings being kept separate from uncontaminated planings.
- Waste will be transported in a safe and secure manner to prevent the release of contaminated material en-route.
With the above mitigation measures in place, it is anticipated that any material assets and waste effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Noise and vibration
Construction activities associated with the proposed schemes have the potential to cause noise and vibration impacts through the use of equipment and construction vehicles for the proposed activities. However, the works are not located within a CNMA or CQA and scattered residential properties are generally well screened from the road by woodland. Works will also be completed over 5 nights (per scheme) on a rolling programme, with the aim being to complete the noisiest works by 23:00. Works with the potential to induce worst-case scenario noise and vibration will also be intermittent, temporary, transient and short-lived.
The road surface is in a poor condition, with a series of defects. Replacing the life-expired surface course with TS2010 road surfacing affords the benefits of a reduction in mid-to-high frequency traffic noise and a reduction in ground vibrations. As a result, upon completion of the work, noise associated with the movement of vehicles on the trunk road should decrease post construction.
The following mitigation measures will be put in place:
- Where possible, the noisiest work operations (e.g., cold milling, using breakers (jackhammers), chipping hammers, use of rollers, etc.) will be completed before 23:00.
- The Environmental Health Officers (EHO) from Perth and Kinross Council will be notified of works.
- Local residents which are affected by the works will be notified in advance of the works, likely by a letter drop, which will contain details of the proposed timings and duration of the works, in addition to contact details for the Site Supervisor.
- The Best Practicable Means, as defined in Section 72 of the Control of Pollution Act 1974, will be employed at all times to reduce noise to a minimum. On-site construction tasks will be programmed to be as efficient as possible, with a view to limiting noise disruption to local sensitive receptors.
- All site personnel will be fully briefed in advance of works regarding the need to minimise noise during works and of the site-specific sensitivities.
- Drop heights from vehicles and NRMM will be kept to a minimum to minimise noise when unloading.
- All plant, machinery and vehicles will be switched off when not in use.
- All plant will be operated in such a way that minimises noise emissions and will have been maintained regularly to the appropriate standards.
- Where fitted, and where permitted under Health and Safety requirements, white noise reversing alarms will be utilised during construction.
- Where ancillary plant such as generators are required, they will be positioned so as to cause minimum noise disturbance. Where deemed necessary, acoustic screens will be utilised.
With the above mitigation measures in place, it is anticipated that any noise and vibration effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Population and human health
During construction, activities undertaken on site have the potential to have temporary adverse impacts on local residents, vehicle travellers, and NMUs. No significant congestion issues are noted during the proposed construction hours; however increased journey times may occur, but these are considered insignificant considering the relatively low traffic counts and works being undertaken out of the traffic peak hours. In the event of local access restrictions to residential properties, access will be granted as requested.
Six residential properties are found within 300m of scheme extents. While most are well screened, the nearest residential property lies 20m away from the River Garry to Shierglas scheme with little screening from the carriageway. As works are due to take place at night times, there is potential for disturbance from noise, vibration and construction lighting.
With the following mitigation measures in place, the risk of significant impacts on population and human health is considered to be low:
- The works schedule and any changes to this will be communicated to local residents prior to and throughout the programme.
- Construction lighting will consider the need to avoid illuminating surrounding environment to avoid a nuisance at night, and non-essential lighting will be switched off at night.
- Appropriate provisions / measures will be implemented within the traffic management to allow the safe passage of NMUs of all abilities through the site.
- Journey planning information will be available for drivers online at the trafficscotland.org website. Journey planning information will also be available for drivers online through BEAR’s social media platforms.
With the above mitigation measures in place, it is anticipated that any population and human health effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Road drainage and the water environment
There is potential for temporary impacts on the water environment due to operation of plant within proximity to watercourses and/or drainage systems, which may lead to potential changes in water quality from pollution events (either by accidental spillage of sediments, particulate matter, chemicals, fuels or by mobilisation of these in surface water caused by rain). No in-water works will take place and there is no requirement for the abstraction or transfers of water from, or discharges to, a waterbody. As such, the potential for a direct pollution incident within a waterbody is unlikely. Experience gained from BEAR maintenance schemes elsewhere on the network has shown that where standard good working practice is adopted (e.g., adherence to SEPA good practice guidance, utilisation of drain covers or similar, etc.), water quality is protected.
The following mitigation measures will be put in place to reduce the risk of pollution incidents as a result of works:
- The schemes will not entail any in-stream works.
- Standard working practices to comply with The Water Environment (Controlled Activities) (Scotland) Regulations 2011 (as amended) for works in or near water will be detailed in the SEMP and adhered to on site.
- No discharges into any watercourses or drainage systems will be permitted. Appropriate containment measures will be in place to prevent any loss of construction materials into the water environment.
- An incident response (contingency) plan will be put in place to reduce the risk from pollution incidents or accidental spillages. All necessary containment equipment, including suitable spill kits (for oil and chemicals) will be available on site, quickly accessible if needed, and staff trained in their use.
- All spills will be logged and reported. In the event of any spills into the water environment, all works will stop and the incident will be reported to the project manager and the BEAR Scotland Environmental Team. SEPA will be informed of any such incident as soon as possible using the SEPA Pollution Hotline.
- All plant and equipment will be regularly inspected for any signs of damage and leaks. A checklist will be present to make sure that the checks have been carried out.
- Storage of hazardous material, oil and fuel containers will be distanced more than 10m away from any watercourses.
- If required, a designated refuelling area will be identified. Fuel bowsers will be stored on an impermeable area and be fully bunded. This will be distanced more than 10m from any watercourses.
- During refuelling of smaller mobile plant, a funnel will be used, and drip trays will be in place. Care will be taken to reduce the chance of spillages. Spill kits will be quickly accessible to capture any spills should they occur. The ground / stone around the site of a spill shall be removed, double bagged and taken off site as special contaminated waste.
- Generators and static plant may have the potential to leak fuel and / or other hydrocarbons and will have bunding with a capacity of 110%. If these are not bunded then drip trays will also be supplied beneath the equipment with a capacity of 110%.
With the above mitigation measures in place, it is anticipated that any road drainage and the water environment effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Climate
Construction activities associated with the proposed scheme works have the potential to cause local air quality impacts as a result of the emission of greenhouse gases through the use of vehicles and machinery, material use and production, and transportation of materials to and from site. The following mitigation measures will be put in place:
- BEAR Scotland will adhere to their Carbon Management Policy.
- Local contractors and suppliers will be used as far as practicable to reduce fuel use and greenhouse gases emitted as part of the works.
With the above mitigation measures in place, it is anticipated that any climate effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Vulnerability of the project to risks
There will be no change to the likelihood of flooding on the A9 within the scheme extents upon completion of the works.
Works are restricted to areas of made ground on the A9 carriageway surface, with access to the schemes gained via the A9. TM will employ lane closures facilitated by a convoy system. Local residents will be notified of working hours and provided with appropriate contact information.
A Traffic Management Plan (TMP), which includes measures to avoid or reduce disruption to road traffic, will be produced in accordance with the Traffic Signs Manual (Department of Transport 2009). The TMP will ensure that there is no severance of community assets, access routes or residential development.
These measures, along with mitigation measures and standard working practices, will be detailed in the SEMP and adhered to on site. The vulnerability of the project to risks of major accidents and disasters is considered to be low.
Assessment of cumulative effects
During construction, activities associated with the works may create several types of minor temporary disturbances such as changes to noise and vibration and air quality. However, these impacts will be temporary in nature and are not anticipated to result in a significant cumulative effect.
A search of the Perth & Kinross Council Planning Portal (Map Search) identified no approved planning applications within 300m of the scheme within the last year.
A search of the Scottish Roads Works Commissioner website (Map Search) has identified no other roadworks noted as being planned on the trunk road at the same time as these schemes. Due to the nature of the proposed works, no cumulative effects are anticipated with any other developments in the vicinity.
BEAR Scotland programme all of their proposed works in line with appropriate guidance and contractual requirements. All schemes are programmed to take into account existing and future planned works, with a view of limiting any cumulative effects relating to TM. As a result of this exercise, where a potential for cumulative impacts is identified, BEAR will reprogramme schemes to avoid / limit any cumulative effects or will utilise existing TM to complete multiple schemes at once. This approach allows BEAR Scotland to effectively manage the potential cumulative effects as a result of TM, resulting in minimal disruption to users of the Scottish trunk road network.
Overall, it is unlikely that the proposed works will have significant cumulative effects with any other future works in the area.