Traffic management

Weekly Traffic Management Update: 17/03/2017 16:30

This information is updated weekly for the following fortnight. The dates given are as accurate as possible but are subject to change at short notice.

Northern Section (River Don to Tipperty)

A947 Goval Area

B977 Echt to Balmedie Road (West of A947)

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

A947 Aberdeen to Old Meldrum to Turriff Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

B977 Echt to Balmedie Road (Between A947 and B997)

Week commencing 18/03/2017: 2 way temporary traffic signals will be in operation between 0930 and 1530 from Monday 20 March to Friday 24 March to safely facilitate AWPR works.

.

Week commencing 25/03/2017: No planned traffic management

A new roundabout will be in operation on the B977 at Goval from Friday 19 August 2016 until the end of the project, to safely facilitate AWPR works.

Plant crossing controlled by movement activated traffic signal system in operation.

A 30 mph temporary speed restriction is in place on the B977 Echt to Balmedie Road within the vicinity of the AWPR works site. This is to allow AWPR site traffic to safely use site access and plant crossing points alongside existing road users.

C25C Newmachar Church Link Road

Week commencing 18/03/2017: 2 way temporary traffic signals will be in operation between 0930 and 1530 from Monday 20 March to Friday 24 March to safely facilitate AWPR works.

 

Week commencing 25/03/2017: No planned traffic management

Traffic signal control will be in operation at Parkhill junction from Friday 19 August 2016 for a period of approximately 8 months.

Plant crossing controlled by movement activated traffic signal system in operation.

Side Roads between Goval and Blackdog

B977 Echt to Balmedie Road (North of B997)

Week commencing 18/03/2017: 2 way temporary traffic signals will be in operation between 0930 and 1530 from Monday 20 March to Friday 24 March to safely facilitate AWPR works.

.

Week commencing 25/03/2017: No planned traffic management

Plant crossing controlled by movement activated traffic signal system in operation.

A 30 mph temporary speed restriction is in place on the B977 Echt to Balmedie Road within the vicinity of the AWPR works site. This is to allow AWPR site traffic to safely use site access and plant crossing points alongside existing road users.

U19C Leuchlands to Cranbog to Sheilhill Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

A 40 mph temporary speed restriction is in place on the U19C. This is to allow AWPR site traffic to safely use a plant crossing point alongside existing road users on the U19C temporary diversion.

Plant crossing controlled by movement activated traffic signal system in operation.

B999 Aberdeen to Tarves Road

Week commencing 18/03/2017: No planned traffic management

Week commencing 25/03/2017: . A road closure will be in operation between 2100 Friday 31 March and 0600 Monday 3 April to safely facilitate AWPR works. Local diversions will be in operation whilst the road closure is in place.A 40 mph temporary speed restriction is in place on the B999 Aberdeen to Tarves Road within the vicinity of the AWPR works site. This is to allow AWPR site traffic to safely use site access and plant crossing points alongside existing road users.

A90 Blackdog Area

A90 Blackdog flyer

A90 Main Carriageway (Between Murcar Roundabout and Easter Hatton)

Week commencing 18/03/2017: No planned traffic management

Week commencing 25/03/2017: No planned traffic management.

A 50mph speed restriction with lane width restrictions is in operation on the A90 northbound and southbound carriageways.

Hareburn Terrace

Week commencing 18/03/2017: 2 way temporary traffic signals will be in operation between 0930 and 1530 from Monday 20 March to Friday 24 March to safely facilitate AWPR works.

.

Week commencing 25/03/2017: No planned traffic management.

C1C Belhelvie to Wateridgemuir 

Week commencing 18/03/2017:  No planned traffic management

Week commencing 25/03/2017:  No planned traffic management.

This junction will be closed from Monday 13 March 2017 until the opening of the new Blackdog roundabout to safely facilitate AWPR enabling works. Local diversions will be in place whilst the road closure is in operation.

A90 (between Easter Hatton and Millden)

Week commencing 18/03/2017: No planned traffic management

Week commencing 25/03/2017: No planned traffic management.

A 50mph speed restriction with lane width restrictions is in operation on the A90 northbound and southbound carriageways.

A90 Balmedie Area

A90 Balmedie flyer

A90 Main Carriageway (Millden to Keir Farm)

Week commencing 18/03/2017: No planned traffic management

Week commencing 25/03/2017: No planned traffic management.

A 50mph speed restriction with lane width restrictions is in operation on the A90 northbound and southbound carriageways.

Eigie Road, Balmedie

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

This junction will be closed permanently from Monday 18 July 2016 to the opening of the new Balmedie underpass to safely facilitate AWPR and utility works. Local diversions will be in place whilst the road closure is in operation.

A90 North of Balmedie

A90 (between Kier Farm and Old Road)

Week commencing 18/03/2017: No planned traffic management

Week commencing 25/03/2017: No planned traffic management.

Part time signals will be in operation at the junction of Old Road and the A90 from Tuesday 19 July until the opening of the new Balmedie underpass.

A 50mph speed restriction with lane width restrictions is in operation on the A90 northbound and southbound carriageways.

A90 (Near Foveran)

Week commencing 18/03/2017: 2 way temporary traffic signals will be in operation between 2000 and 0600 from Monday 20 March to Tuesday 21  March to safely facilitate utility works.

Week commencing 25/03/2017: No planned traffic management

A 50mph speed restriction is in operation on the A90 northbound and southbound carriageways.

A90 (Near B9000)

Week commencing 18/03/2017: No planned traffic management

Week commencing 25/03/2017: No planned traffic management.

A90 (Near Bridgend)

Week commencing 18/03/2017: 2 way temporary traffic signals will be in operation between 2000 and 0600 from Tuesday 22 March to Friday 24 March to safely facilitate AWPR works.

.

Week commencing 25/03/2017: No planned traffic management.

A 40mph speed restriction will be in operation on the A90 northbound and southbound carriageways from the evening of Friday 2 December for around four months.

Side Roads North of Balmedie Area 

Old Road, Balmedie

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

Part time signals will be in operation at the junction of Old Road and the A90 from Tuesday 19 July until the opening of the new Balmedie underpass.

The project results in the permanent closure of the junction between Old Road and the existing A90. Vehicular traffic will be able to access Old Road by means of a new link road to be constructed east of the main carriageway of the Aberdeen Western Peripheral Route at Balmedie underpass. The date for permanent closure of this road will be advised when confirmed.

B977 Belhelvie Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

The project results in the permanent closure of the junction between the B977 Belhelvie Road and the existing A90. Vehicular traffic will be able to access the B977 Belhelvie Road by means of a new link road to be constructed east of the main carriageway of the Aberdeen Western Peripheral Route at Balmedie underpass. The date for permanent closure of this road will be advised when confirmed.

Orrock Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signals in operation.

Westfield Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

This road will be closed permanently from Monday 18 April 2016 to the opening of the new Westfield Road to safely facilitate AWPR and utility works. Local diversions will be in place whilst the road closure is in operation

Kirkhill Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

A permanent road closure will be in place on Kirkhill Road from 15 August 2016. New Kirkhill link road open to traffic on Friday 19 August.

A975 Newburgh Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

Mill Road, Foveran

Week commencing 18/03/2017: No planned traffic management

Week commencing 25/03/2017: No planned traffic management.

This road will be closed permanently from Monday 11 July 2016 until the opening of the new Mill Road to safely facilitate AWPR and utility works. Local diversions will be in place while the new Mill Road is under construction

Pitmillan Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

B9000

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

Central Section (River Dee to River Don)

A93 Milltimber Area

A93 Milltimber flyer

B9077 South Deeside Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

A 30 mph temporary speed restriction will be in place on the B9077 at the above location once the plant crossing controlled by a movement activated traffic signal system, becomes operational. This will allow AWPR site traffic to safely use the plant crossing point alongside existing road users. The speed restriction is expected to be in place for the duration of the project’s construction works.

B979 south of A93

Week commencing 18/03/2017: 3 way temporary traffic signals will be in operation between 0930 and 1530 from Monday 20 March to Friday 24 March to safely facilitate AWPR works.

Week commencing 25/03/2017: 3 way temporary traffic signals will be in operation between 0930 and 1530 from Monday 27 March to Friday 31 March to safely facilitate AWPR works.

To facilitate AWPR enabling works, a temporary new road layout will be in operation from Monday 30 January 2017 for a period of up to 5 months.

Milltimber Brae

Week commencing 18/03/2017: No planned traffic management

Week commencing 25/03/2017: No planned traffic management

A road closure will be in place on the U133C Milltimber Brae from 0600 Friday 08 April 2016 for a period of approximately 12 months, to safely facilitate utility works. Local diversions will be in place whilst the road closure is in operation.

A93 North Deeside Road

Week commencing 18/03/2017: 3 way temporary traffic signals will be in operation between 0930 and 1530 from Monday 20 March to Friday 24 March to safely facilitate AWPR works.

Week commencing 25/03/2017: 3 way temporary traffic signals will be in operation between 0930 and 1530 from Monday 27 March to Friday 31 March to safely facilitate AWPR works.

A road closure will be in operation between 2000 Friday 31 March and 0600 Monday 3 April to safely facilitate AWPR works. Local diversions will be in operation whilst the road closure is in place.

To facilitate AWPR enabling works, a temporary new road layout will be in operation from Monday 30 January 2017 for a period of up to 5 months.

Culter House Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

The project results in the permanent closure of this road to vehicular traffic. Vehicular traffic will be able to access Culter House Road by means of a new link road to be constructed as part of Milltimber Junction north of the A93. The date for permanent closure of this road will be advised when confirmed.

Side Roads between Milltimber and South Kingswells  

Contlaw Road

Week commencing 18/03/2017: 3 way temporary traffic signals will be in operation from 0930 to 1530 from Monday 20 March to Friday 24 March to safely facilitate AWPR works.

Week commencing 25/03/2017: No planned traffic management.

To facilitate AWPR enabling works, a new road layout will be in operation from Monday 04 April 2016.

Plant crossing controlled by movement activated traffic signal system in operation.

C127C Wester Ord to Blacktop Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

A new road layout will be operational from Monday 13 June 2016.

Plant crossing controlled by movement activated traffic signal system in operation.

A944 South Kingswells Area

A944 Main Carriageway

Week commencing 18/03/2017: Contraflow will be in operation on the A944 between 2000 Friday 17 March and 0600 Monday 20 March, to safely facilitate AWPR works.

Lane closures will be in operation on the A944, between 2000 and 0600 from Monday 20 March to Friday 24 March, to safely facilitate AWPR works.

The Footway/Cycleway adjacent to the eastbound Carriageway will be closed from 2000 Friday 17 March, to safely facilitate AWPR works. Local diversions for Non-Motorised Users will be in place whilst the Footway /Cycleway closure is in operation. 

Week commencing 25/03/2017: Lane closures will be in operation on the A944, between 2000 and 0600 from Monday 20 March to Friday 24 March, to safely facilitate AWPR works.

.

C93C Clinterty to Kingsford Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

A new road layout will be in operation from Thursday 27 October 2016.

Side Roads between South Kingswells and Craibstone

U90C Tulloch Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

To facilitate AWPR enabling works, a new road layout will be in operation from 0600 on Monday 11 April 2016.

Plant crossing controlled by movement activated traffic signal system in operation.

C89C Chapel of Stoneywood to Fairley Road

Week commencing 18/03/2017: No planned traffic management

Week commencing 25/03/2017: No planned traffic management

This road is permanently closed immediately North of the junction with the U90C Tulloch Road.

A 40 mph temporary speed restriction is in place on the C89C within the vicinity of the AWPR site offices at Craibstone. This is to allow AWPR site traffic to safely use site access and plant crossing points alongside existing road users. The temporary speed restriction is expected to be in place for the duration of the project’s construction works.

A96 Craibstone Area

A96 Main Carriageway

Week commencing 18/03/2017: No planned traffic management

Week commencing 25/03/2017: Lane closures will be in operation from 0600hrs to 2000hrs on Saturday 25 and Sunday 26 March to safely facilitate AWPR works.

The central reservation of the A96 at the junction with Forritt Brae will be closed, barring right turns, from Thursday 12 January 2017 until the completion of the project.

Dyce Drive

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

Side Roads between Craibstone and River Don

U53C Chapel of Stoneywood to Newton to Kirkhill Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

A permanent road closure will be in place on the U53C from Monday 08 August 2016. Local diversions will be in place until the new airport link road is in operation.

C55C Pitmedden Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

Southern Section (Stonehaven/Charleston to River Dee)

A90 Stonehaven Area

A90 Stonehaven flyer

A90 Main Carriageway

Week commencing 18/03/2017: Lane closures will be in place on the A90, between 2000 and 0600, from Saturday 18 March to Friday 24 March, to safely facilitate AWPR works.

Week commencing 25/03/2017: Lane closures will be in place on the A90, between 2000 and 0600, from Saturday 25 March to Friday 31 March, to safely facilitate AWPR works.

Contraflow will be in operation on the A90 from 0600 on Tuesday 21 March, to safely facilitate AWPR works. The contraflow will consist of two lanes of traffic heading northbound and one lane southbound during the daytime and 1 lane of traffic heading northbound and 1 lane of traffic heading southbound overnight. This is expected to add between 10 and 20 minutes to journeys during morning and evening peak travelling periods for road users heading south.

A90 to B979 Northbound Diverge Slip Road

Week commencing 18/03/2017: Lane closures will be in place on the A90, between 2000 and 0600, from Saturday 18 March to Friday 24 March, to safely facilitate AWPR works.

Week commencing 25/03/2017: Lane closures will be in place on the A90, between 2000 and 0600, from Saturday 25 March to Friday 31 March, to safely facilitate AWPR works.

Contraflow will be in operation on the A90 from 0600 on Tuesday 21 March, to safely facilitate AWPR works.

B979 to A90 Northbound Merge Slip Road

Week commencing 18/03/2017: Lane closures will be in place on the A90, between 2000 and 0600, from Saturday 18 March to Friday 24 March, to safely facilitate AWPR works.

Week commencing 25/03/2017: Lane closures will be in place on the A90, between 2000 and 0600, from Saturday 25 March to Friday 31 March, to safely facilitate AWPR works.

Contraflow will be in operation on the A90 from 0600 on Tuesday 21 March, to safely facilitate AWPR works.

B979 (South of junction with A90 northbound slip roads)

Week commencing 18/03/2017: 2 way temporary traffic signals will be in operation between 0700 and 1900 from Monday 09 January 2017 for a period of approximately 3 months. The lights will be manually controlled at peak times between 0700 and 0930 and between 1530 and 1800 daily to safely facilitate AWPR enabling works.

Week commencing 25/03/2017: 2 way temporary traffic signals will be in operation between 0700 and 1900 from Monday 09 January 2017 for a period of approximately 3 months. The lights will be manually controlled at peak times between 0700 and 0930 and between 1530 and 1800 daily to safely facilitate AWPR enabling works.

A 40mph temporary speed restriction is in place at Stonehaven to facilitate the safe use of multiple AWPR site accesses alongside existing road users. This is expected to be in place for the duration of the project’s construction works.

B979 (West of junction with A90 northbound slip roads)

Week commencing 18/03/2017: 2 way temporary traffic signals will be in operation between 0700 and 1900 from Monday 09 January 2017 for a period of approximately 3 months. The lights will be manually controlled at peak times between 0700 and 0930 and between 1530 and 1800 daily to safely facilitate AWPR enabling works.

Week commencing 25/03/2017: 2 way temporary traffic signals will be in operation between 0700 and 1900 from Monday 09 January 2017 for a period of approximately 3 months. The lights will be manually controlled at peak times between 0700 and 0930 and between 1530 and 1800 daily to safely facilitate AWPR enabling works.

A 40mph temporary speed restriction is in place at Stonehaven to facilitate the safe use of multiple AWPR site accesses alongside existing road users. This is expected to be in place for the duration of the project’s construction works.

U89K Aquhorthies-Ury Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

The project results in the permanent closure of this road to vehicular traffic, with an underpass providing continuity of passage for non-motorised users. Vehicular traffic will be able to access the U88K by means of a new link road to be constructed east of the main carriageway of the Aberdeen Western Peripheral Route. The date for permanent closure of this road will be advised when confirmed.

U88K Fishermyre to Clayfolds Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

C12K Bridge of Muchalls to Netherley Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

C25K Muchalls to Burnhead Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

C24K Skateraw to Cookney Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

C13K Lairhillock to Portlethen Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

C5K Lochton to Auchlunies to Nigg Road (near Greens of Crynoch)

Week commencing 18/03/2017: A road closure will be in place from 1600 Friday 24 March for 4 Days to safely facilitate AWPR works. Local diversions will be in place whilst the road closure is in operation.

Week commencing 25/03/2017:

A road closure will be in place from 1600 Friday 24 March for 4 Days to safely facilitate AWPR works. Local diversions will be in place whilst the road closure is in operation.

Plant crossing controlled by movement activated traffic signal system in operation.

A90 Charleston Area

A90 Main Carriageway

Week commencing 18/03/2017:  Lane closures will be in place on the A90 between 2000 and 0600, from Friday 17 March to Friday 24 March, to safely facilitate AWPR enabling works.Week commencing 25/03/2017:  

Weekend contraflow will be in place on the A90 between Saturday 25 March and Sunday 26 March, to safely facilitate AWPR enabling works.

Road closures will be in place on the A90 between 2000 and 0600 on Saturday 25 March and Sunday 26 March to safely facilitate AWPR enabling works. Local diversions will be in place whilst the road closure is in operation.

Lane closures will be in place on the A90 between 2000 and 0600, from Monday 27 March to Friday 31 March, to safely facilitate AWPR enabling works.

A 50mph speed restriction is in operation on the A90 northbound and southbound carriageways.

These works are part of the overall Charleston Junction works.

Findon Junction to A90 Northbound Merge

Week commencing 18/03/2017:  Lane closures will be in place on the A90 between 2000 and 0600, from Friday 17 March to Friday 24 March, to safely facilitate AWPR enabling works Week commencing 25/03/2017:  

Weekend contraflow will be in place on the A90 between Saturday 25 March and Sunday 26 March, to safely facilitate AWPR enabling works.

A road closure will be in place on the A90 between 2000 and 0600 on Saturday 25 March, to safely facilitate AWPR enabling works. Local diversions will be in place whilst the road closure is in operation.

Lane closures will be in place on the A90 between 2000 and 0600, from Monday 27 March to Friday 31 March, to safely facilitate AWPR enabling works.

A 50mph speed restriction is in operation on the A90 northbound and southbound carriageways.

A90 to Findon Junction Southbound Diverge

Week commencing 18/03/2017: Lane closures will be in place on the A90 between 2000 and 0600, from Friday 17 March to Friday 24 March, to safely facilitate AWPR enabling works Week commencing 25/03/2017:  Weekend contraflow will be in place on the A90 between Saturday 25 March and Sunday 26 March, to safely facilitate AWPR enabling works.

A road closure will be in place on the A90 between 2000 and 0600 on Saturday 25 March, to safely facilitate AWPR enabling works. Local diversions will be in place whilst the road closure is in operation.

Lane closures will be in place on the A90 between 2000 and 0600, from Monday 27 March to Friday 31 March, to safely facilitate AWPR enabling works.

A 50mph speed restriction is in operation on the A90 northbound and southbound carriageways.

A90 to A956 Northbound Diverge

Week commencing 18/03/2017:  Lane closures will be in place on the A90 between 2000 and 0600, from Friday 17 March to Friday 24 March, to safely facilitate AWPR enabling works.

Week commencing 25/03/2017:  Weekend contraflow will be in place on the A90 between Saturday 25 March and Sunday 26 March, to safely facilitate AWPR enabling works.

A road closure will be in place on the A90 between 2000 and 0600 on Saturday 25 March, to safely facilitate AWPR enabling works. Local diversions will be in place whilst the road closure is in operation.

Lane closures will be in place on the A90 between 2000 and 0600, from Monday 27 March to Friday 31 March, to safely facilitate AWPR enabling works.

To facilitate AWPR enabling works, the northbound diverge will be closed as of Tuesday 15 November 2016. A diversion via a temporary northbound diverge will be in operation.

A 50mph speed restriction is in operation on the A90 northbound and southbound carriageways.

A956 to A90 Northbound Merge

Week commencing 18/03/2017:  Lane closures will be in place on the A90 between 2000 and 0600, from Friday 17 March to Friday 24 March, to safely facilitate AWPR enabling works Week commencing 25/03/2017:  Weekend contraflow will be in place on the A90 between Saturday 25 March and Sunday 26 March, to safely facilitate AWPR enabling works.

A road closure will be in place on the A90 between 2000 and 0600 on Saturday 25 March, to safely facilitate AWPR enabling works. Local diversions will be in place whilst the road closure is in operation.

Lane closures will be in place on the A90 between 2000 and 0600, from Monday 27 March to Friday 31 March, to safely facilitate AWPR enabling works.

To facilitate AWPR enabling works, the northbound merge will be closed as of Tuesday 15 November 2016. A diversion via a temporary northbound merge will be in operation.

A 50mph speed restriction is in operation on the A90 northbound and southbound carriageways.

A90 to A956 Southbound Diverge

Week commencing 18/03/2017:  Lane closures will be in place on the A90 between 2000 and 0600, from Friday 17 March to Friday 24 March, to safely facilitate AWPR enabling works.

Week commencing 25/03/2017:  Weekend contraflow will be in place on the A90 between Saturday 25 March and Sunday 26 March, to safely facilitate AWPR enabling works.

A road closure will be in place on the A90 between 2000 and 0600 on Saturday 25 March, to safely facilitate AWPR enabling works. Local diversions will be in place whilst the road closure is in operation.

Lane closures will be in place on the A90 between 2000 and 0600, from Monday 27 March to Friday 31 March, to safely facilitate AWPR enabling works.

A 50mph speed restriction is in operation on the A90 northbound and southbound carriageways.

A956 to A90 Southbound Merge

Week commencing 18/03/2017:  Lane closures will be in place on the A90 between 2000 and 0600, from Friday 17 March to Friday 24 March, to safely facilitate AWPR enabling works.

Week commencing 25/03/2017:  Weekend contraflow will be in place on the A90 between Saturday 25 March and Sunday 26 March, to safely facilitate AWPR enabling works.

A road closure will be in place on the A90 between 2000 and 0600 on Saturday 25 March, to safely facilitate AWPR enabling works. Local diversions will be in place whilst the road closure is in operation.

Lane closures will be in place on the A90 between 2000 and 0600, from Monday 27 March to Friday 31 March, to safely facilitate AWPR enabling works.

A 50mph speed restriction is in operation on the A90 northbound and southbound carriageways.

A956 Main Carriageway

Week commencing 18/02/2017: Lane closures will be in place between 2000 and 0600, from Friday 17 March to Friday 24 March, to safely facilitate AWPR enabling works Week commencing 18/03/2017: Lane closures will be in place between 2000 and 0600, from Friday 24 March to Friday 31 March, to safely facilitate AWPR enabling works. .A 50mph speed restriction is in operation on the A90 northbound and southbound carriageways.

C5K Lochton to Auchlunies to Nigg Road (near Charleston)

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

A road closure between the A90 and the C5K will be in place from 0000 Tuesday 15 November 2016 for a period of 18 months, to safely facilitate AWPR works. Local diversions will be in place whilst the road closure is in operation.

Plant crossings controlled by movement activated traffic signal system in operation.

U58K Haremoss to Checkbar Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

The project results in the closure of access between the A90 and the U58K from Saturday 02 July 2016, vehicular traffic will be able to access the A90 at Findon Junction by means of a new link road west of the main carriageway of the existing A90.

Side Roads between Charleston and River Dee

C34K Hilldowntree to Sunnyside to Causeyport Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

A permanent road closure will be in place on the C34K, from Monday 29 August 2016 to safely facilitate AWPR works, including the construction of a new bridge for farm traffic only. Local diversions will be in place and will be sign-posted.

Plant crossing controlled by movement activated traffic signal system in operation.

C30K Hillside to Batchart Road

Week commencing 18/03/2017: A road closure will be in place from 0600 Saturday 03 March for 4 weeks to safely facilitate AWPR works. Local diversions will be in place whilst the road closure is in operation.

Week commencing 25/03/2017: A road closure will be in place from 0600 Saturday 03 March for 4 weeks to safely facilitate AWPR works. Local diversions will be in place whilst the road closure is in operation.

Plant crossing controlled by movement activated traffic signal system in operation.

C5K Lochton to Auchlunies to Nigg Road (near Cleanhill)

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

U63K Maryculter Road

Week commencing 18/03/2017: No planned traffic management.

Week commencing 25/03/2017: No planned traffic management.

AWPR/B-T Construction Works

All traffic management is planned and coordinated through a Traffic Management Review Panel, chaired by the contractor and attended by Transport Scotland representatives, Traffic Scotland, both local Councils, and Police Scotland.

In addition, Transport Scotland, Aberdeen City Council and Aberdeenshire Council have been working closely with Aberdeen Roads Limited (ARL) to ensure the safety of road users and the workforce during traffic management, whilst keeping disruption to a minimum.

As the project develops, updates on major temporary traffic management, which will allow the project to be constructed, will be provided.

Access to local businesses across the north east will be maintained at all times.

For enquiries relating to traffic management, please contact Aberdeen Roads Limited on 0800 058 8350 or at enquiries@aberdeenroads.com

Major Works at Charleston Junction - Significant changes to road layout

These works will include the construction of a new bridge to carry road users over the existing A90 and existing Charleston Junction slip roads, the realignment of the A956 and widening the A90 to three lanes in each direction.

Due to the proximity of these works to live traffic on the A90, major traffic management is required to enhance the safety of construction workers and road users. These measures will include closing the access from Lochton to Auchlunies to Nigg Road (C5K Banchory – Devenick Road) to the A90; opening a new signed diversion for road users;  and the implementation of a 50mph speed restriction on the A90 at Charleston.

Access closure / Diversion

From early November, access to the A90 from Lochton to Auchlunies to Nigg Road (C5K Banchory – Devenick Road) will be permanently closed in line with the previously published project details. Signed diversions will be in place to help road users join and leave the A90.

Maps showing the diversion routes

Speed restriction / Designated lanes

From early November, a 50mph speed restriction will be in place on the A90 at Charleston 24 hours a day, seven days a week. Road users will be advised via signage to ‘Get In Lane, Stay In Lane’. Road users heading northbound  can remain on the A90 by using the outside lane while road users on the inside lane can choose to stay on the A90 or to join the A956 (Wellington Road). Work is also ongoing with a view to installing average speed cameras on the A90 through this section to enhance safety for construction workers and road users. Further details on this will be available shortly.

Upcoming beam deliveries

The AWPR/B-T project will have 75 principal structures, including two river crossings and one railway bridge, as well as over 70 culverts.

Beams are required for the construction of the structures and are delivered in various lengths to assist the works underway, ranging between 8m and 45m. All beams deliveries are carefully planned by the contractor, local authorities, Police Scotland and Transport Scotland. For safety reasons, and to minimise disruption to road users, beams are transported during daylight hours out with peak travelling times.

The dates provided in the ‘Upcoming beam deliveries’ section are for guidance only and are subject to change as construction progresses

A956 Charleston Junction Overbridge

On Sunday 26 March, between 9.30am and 3.30pm, two 47m long beams are expected to be delivered to the south section, which will help to form the Charleston Junction Overbridge.

Pitmedden Road Underbridge

On Monday 27 March, two 19m long edge beams are expected to be delivered to the centre section between 9.30am and 3.30pm, which will form part of the Pitmedden Road Underbridge. This will be followed by the delivery of nine 19m long beams on Thursday 30 March and Friday 31 March, between 8pm and 6am. The delivery of these beams have been timed to minimise inconvenience to road users.

Additional safety measures for the A90

Average speed cameras are now operational between Blackdog and Balmedie and at Charleston. It is expected that these will enhance safety of construction workers and road users, as well as improve safety, traffic flow and journey time reliability. 

Aberdeen Roads Limited has been working closely with Transport Scotland, Aberdeenshire Council, Police Scotland and the North Safety Camera Unit over the use of average speed cameras.