Ferrytoll Junction

Ferrytoll Roundabout

The roundabout for the junction is now circulating on the line for the final arrangement. Temporary footpaths are on the north side of the junction where the permanent paths and cycleway will operate.

Ferrytoll Park & Ride

Bus stances serving Ferrytoll Park & Ride are now in their new positions at the newly constructed bus turning circle. Users of the Park & Ride should be aware that works will continue in the area while the previous temporary measures are removed and other ancillary works completed.

B981

Temporary traffic light controls will operate on the B981 below Ferrytoll Viaduct during overhead works and while concrete finishing is applied to the adjacent slopes under the viaduct.


Start date 14 Jun 2017 Area 1 Ferrytoll Junction Projects