Southern Section (Stonehaven/Charleston to River Dee)

A90 Stonehaven Area

A90 Main Carriageway

Week commencing 21/04/2018: Weekend lane closures will be in place from 8pm Friday 20 April to 6am Monday 23 April. Overnight lane closures will be in place when required between 8pm and 6am from Monday 23 April to Friday 27 April.

Week commencing 28/04/2018:  Weekend lane closures will be in place from 8pm Friday 27 April 8pm to 6am Monday 30 April. Overnight lane closures will be in place when required between 8pm and 6am Monday 30 April to Friday 4 May.

A90 to B979 Northbound Diverge Slip Road

Week commencing 21/04/2018: Overnight road closures will be in place from Friday 20 April 8pm to 6am Saturday 21 April. A signed diversion route will be in place.

Week commencing 28/04/2018: No planned traffic management.

B979 to A90 Northbound Merge Slip Road

Week commencing 21/04/2018: Overnight road closures will be in place from Friday 20 April 8pm to 6am Saturday 21 April. A signed diversion route will be in place.

Week commencing 28/04/2018: No planned traffic management.

B979 to A90 Southbound Merge Slip Road

Week commencing 21/04/2018: Overnight road closures will be in place from Friday 20 April 8pm to 6am Saturday 21 April. A signed diversion route will be in place.

Week commencing 28/04/2018: Overnight road closures will be in place from Monday 30 April from 8pm until 6am for 4 nights. A signed diversion route will be in place.

B979 (South of junction with A90 northbound slip roads)

Week commencing 21/04/2018: 2 way temporary traffic signals will be in operation.

Week commencing 28/04/2018: 2 way temporary traffic signals will be in operation. Overnight road closures will be in place from Monday 30 April from 8pm until 6am for 4 nights. A signed diversion route will be in place.

B979 (West of junction with A90 northbound slip roads)

Week commencing 21/04/2018: Overnight road closures will be in place from Friday 20 April 8pm to 6am and Saturday 21 April 8pm to 6am. A signed diversion route will be in place.

Week commencing 28/04/2018: No planned traffic management.

U89K Aquhorthies-Ury Road

Week commencing 21/04/2018: No planned traffic management.

Week commencing 28/04/2018: No planned traffic management.

The access to and from the U89K at the B979 Netherley Road has been closed permanently.

U88K Fishermyre to Clayfolds Road

Week commencing 21/04/2018: 2 way temporary traffic signals will be in place from Friday 16 March for 6 weeks.

Week commencing 28/04/2018: 2 way temporary traffic signals will be in place from Friday 16 March for 6 weeks.

C12K Bridge of Muchalls to Netherley Road

Week commencing 21/04/2018: No planned traffic management.

Week commencing 28/04/2018: No planned traffic management.

C25K Muchalls to Burnhead Road

Week commencing 21/04/2018: No planned traffic management.

Week commencing 28/04/2018: No planned traffic management.

C24K Skateraw to Cookney Road

Week commencing 21/04/2018: No planned traffic management.

Week commencing 28/04/2018: No planned traffic management.

C13K Lairhillock to Portlethen Road

Week commencing 21/04/2018: No planned traffic management.

Week commencing 28/04/2018: No planned traffic management.

U59K Banchory-Devenick to Sunnyside Road

This road has been closed permanently.

C5K Lochton to Auchlunies to Nigg Road (near Greens of Crynoch)

Week commencing 21/04/2018: A road closure will be in place from 1am Monday 15 January for up to 16 weeks. A signed diversion route will be in place.

Week commencing 28/04/2018: A road closure will be in place from 1am Monday 15 January for up to 16 weeks. A signed diversion route will be in place.

A90 Main Carriageway (Portlethan to Redcraigs at South Bridge of Dee)

Week commencing 21/04/2018: Lane closures and Findon southbound diverge closure will be in place on the A90 from 8pm Friday 20 April to 6am Monday 23 April a signed diversion route will be in place. Lane closures will then be in place when required on the A90 between 8pm and 6am from Monday 23 April to Friday 27 April.

Week commencing 28/04/2018: Lane closures will be in place on the A90 from 8pm Friday 27 April to 6am Monday 30 April. Lane closures will then be in place when required on the A90 between 8pm and 6am from Monday 30 April to Friday 4 May.

A90 Charleston Area

A90 to A956 Northbound Diverge

Week commencing 21/04/2018: No planned traffic management.

Week commencing 28/04/2018: No planned traffic management.

A956 to A90 Northbound Merge

Week commencing 21/04/2018: No planned traffic management.

Week commencing 28/04/2018: No planned traffic management.

A90 to A956 Southbound Diverge

Week commencing 21/04/2018: No planned traffic management.

Week commencing 28/04/2018: No planned traffic management.

A956 to A90 Southbound Merge

Week commencing 14/04/2018: No planned traffic management.

Week commencing 21/04/2018: No planned traffic management.

A956 Main Carriageway (Wellington Road to Charleston Junction)

Week commencing 21/04/2018: Lane closures will be in place from Friday 13 April to Friday 20 April.

Week commencing 28/04/2018:  Lane closures will be in place from Friday 20 April to Friday 27 April.

C5K Lochton to Auchlunies to Nigg Road (near Charleston)

Week commencing 21/04/2018: No planned traffic management.

Week commencing 28/04/2018: No planned traffic management.

U58K Haremoss to Checkbar Road

Week commencing 21/04/2018: No planned traffic management.

Week commencing 28/04/2018: No planned traffic management.

The access to and from the C1C at the A90 has been closed permanently.

Side Roads between Charleston and River Dee

C30K Hillside to Batchart Road

Week commencing 21/04/2018: No planned traffic management.

Week commencing 28/04/2018: No planned traffic management.

C5K Lochton to Auchlunies to Nigg Road (near Cleanhill)

Week commencing 21/04/2018: 2 way traffic signals will be in place from Thursday 1 February for up to 14 weeks.

Week commencing 28/04/2018: 2 way traffic signals will be in place from Thursday 1 February for up to 14 weeks.

U63K Maryculter Road

Week commencing 21/04/2018: 2 way traffic signals will be in place from Thursday 1 February for up to 14 weeks.

Week commencing 28/04/2018: 2 way traffic signals will be in place from Thursday 1 February for up to 14 weeks.


Start date 21 Apr 2018 End date 8 May 2018 Area 1 Southern Section (Stonehaven/Charleston to River Dee) Projects