Southern Section (Stonehaven/Charleston to River Dee)

A90 Stonehaven Area

A90 Stonehaven flyer

A90 Main Carriageway

Week commencing 16/09/2017: Overnight lane closures with 1+1 Contraflow will be in place when required from Friday 15 September to Friday 22 September between 8pm and 6am. There will be a road closure of the A90 Southbound from U90K to B979 Southbound merge on Friday 15 September 11.30pm to Saturday 16 September at 3am. There will be a signed diversion route in place.

Week commencing 23/09/2017: Overnight lane closures with 1+1 Contraflow will be in place when required from Friday 22 September to Friday 29 September between 8pm and 6am.

Contraflow will be in operation on the A90 from 6am on Wednesday 22 March, to safely facilitate AWPR works. The contraflow will consist of two lanes of traffic heading northbound and one lane southbound during the daytime and 1 lane of traffic heading northbound and 1 lane of traffic heading southbound overnight. This is expected to add between 10 and 20 minutes to journeys during morning and evening peak travelling periods for road users heading south.

A90 to B979 Northbound Diverge Slip Road

Week commencing 16/09/2017: A Contraflow will be in operation on A90 from 6am on Wednesday 22 March.

Week commencing 23/09/2017:.AContraflow will be in operation on A90 from 6am on Wednesday 22 March.

B979 to A90 Northbound Merge Slip Road

Week commencing 16/09/2017: A Contraflow will be in operation on A90 from 6am on Wednesday 22 March.

Week commencing 23/09/2017: A Contraflow will be in operation on A90 from 6am on Wednesday 22 March.

B979 to A90 Southbound Merge Slip Road

A new southbound merge slip road from the B979 at Stonehaven is in operation in a temporary configuration. This is expected to be in place until completion of the project.

Week commencing 16/09/2017: No planned traffic management.

Week commencing 23/09/2017: No planned traffic management.

B979 (South of junction with A90 northbound slip roads)

Week commencing 16/09/2017: 2 way temporary traffic signals will be in operation between 7am and 7pm from Friday 14 April 2017 for a period of approximately 8 months. The lights will be manually controlled at peak times between 7am and 9.30am and between 3.30pm and 6pm daily.

Week commencing 23/09/2017: 2 way temporary traffic signals will be in operation between 7am and 7pm from Friday 4 April 2017 for a period of approximately 4 months. The lights will be manually controlled at peak times between 7am and 9.30am and between 3.30pm and 6pm daily.

A 40mph temporary speed restriction is in place at Stonehaven for the safe use of multiple AWPR site accesses alongside existing road users. This is expected to be in place for the duration of the project’s construction works.

B979 (West of junction with A90 northbound slip roads)

Week commencing 16/09/2017: 2 way temporary traffic signals will be in operation between 7am and 7pm from Monday 14 April 2017 for a period of approximately 8 months. The lights will be manually controlled at peak times between 7am and 9.30am and between 3.30pm and 6pm daily.

Week commencing 23/09/2017: 2 way temporary traffic signals will be in operation between 7am and 7pm from Monday 14 April 2017 for a period of approximately 8 months. The lights will be manually controlled at peak times between 7am and 9.30am and between 3.30pm and 6pm daily.

A 40mph temporary speed restriction is in place at Stonehaven for the safe use of multiple AWPR site accesses alongside existing road users. This is expected to be in place for the duration of the project’s construction works.

U89K Aquhorthies-Ury Road

Week commencing 16/09/2017: No planned traffic management.

Week commencing 23/09/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

U88K Fishermyre to Clayfolds Road

Week commencing 16/09/2017: No planned traffic management.

Week commencing 23/09/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

C12K Bridge of Muchalls to Netherley Road

Week commencing 16/09/2017: No planned traffic management.

Week commencing 23/09/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

C25K Muchalls to Burnhead Road

Week commencing 16/09/2017: No planned traffic management.

Week commencing 23/09/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

C24K Skateraw to Cookney Road

Week commencing 16/09/2017: No planned traffic management.

Week commencing 23/09/2017: A road closure will be in place from Wednesday 27 September 1am for 5 days. A signed diversion route will also be in place.

C13K Lairhillock to Portlethen Road

Rothnick excavation flyer

Week commencing 16/09/2017: No planned traffic management.

Week commencing 23/09/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

U59K Banchory-Devenick to Sunnyside Road

Week commencing 16/09/2017: No planned traffic management.

Week commencing 23/09/2017: No planned traffic management.

The project results in the permanent closure of this road to vehicular traffic from Friday 7 April 2017. Vehicular traffic will be able to access Banchory-Devenick to Sunnyside Road by means of the C30K Hillside to Batchart Road. Local diversions will be in place.

C5K Lochton to Auchlunies to Nigg Road (near Greens of Crynoch)

Week commencing 16/09/2017: No planned traffic management.

Week commencing 23/09/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

A90 Charleston Area

A90 Main Carriageway

Week commencing 16/09/2017: Lane closures will be in place on the A90 from 8pm Friday 15 September to 6am Monday 18 September. Lane closures will then be in place when required on the A90 between 8pm and 6am from Monday 18 September to Friday 22 September.

Week commencing 23/09/2017: Lane closures will be in place on the A90 from 8pm Friday 22 September to 6am Monday 25 September. Lane closures will then be in place when required on the A90 between 8pm and 6am from Monday 25 September to Friday 29 September.

A 50mph speed restriction is in operation on the A90 northbound and southbound carriageways.

These works are part of the overall Charleston Junction works.

Findon Junction to A90 Northbound Merge

Week commencing 16/09/2017: Lane closures will be in place on the A90 from 8pm Friday 15 September to 6am Monday 18 September. Lane closures will then be in place when required on the A90 between 8pm and 6am from Monday 18 September to Friday 22 September.

Week commencing 23/09/2017: Lane closures will be in place on the A90 from 8pm Friday 22 September to 6am Monday 25 September. Lane closures will then be in place when required on the A90 between 8pm and 6am from Monday 25 September to Friday 29 September.

A 50mph speed restriction is in operation on the A90 northbound and southbound carriageways.

A90 to Findon Junction Southbound Diverge

Week commencing 16/09/2017: Lane closures will be in place on the A90 from 8pm Friday 15 September to 6am Monday 18 September. Lane closures will then be in place when required on the A90 between 8pm and 6am from Monday 18 September to Friday 22 September.

Week commencing 23/09/2017: Lane closures will be in place on the A90 from 8pm Friday 22 September to 6am Monday 25 September. Lane closures will then be in place when required on the A90 between 8pm and 6am from Monday 25 September to Friday 29 September.

A 50mph speed restriction is in operation on the A90 northbound and southbound carriageways.

A90 to A956 Northbound Diverge

Week commencing 16/09/2017: Lane closures will be in place on the A90 from 8pm Friday 15 September to 6am Monday 18 September. Lane closures will then be in place when required on the A90 between 8pm and 6am from Monday 18 September to Friday 22 September.

Week commencing 23/09/2017: Lane closures will be in place on the A90 from 8pm Friday 22 September to 6am Monday 25 September. Lane closures will then be in place when required on the A90 between 8pm and 6am from Monday 25 September to Friday 29 September.

A 50mph speed restriction is in operation on the A90 northbound and southbound carriageways.

A956 to A90 Northbound Merge

Week commencing 16/09/2017: Lane closures will be in place when required on the A956 from 8pm Friday 15 September to 6am Monday 18 September. Lane closures will then be in place when required on the A956 between 8pm and 6am from Monday 18 September to Friday 22 September.

Week commencing 23/09/2017: Lane closures will be in place when required on the A956 from 8pm Friday 22 September to 6am Monday 25 September. Lane closures will then be in place when required on the A956 between 8pm and 6am from Monday 25 September to Friday 29 September.

A 50mph speed restriction is in operation on the A90 northbound and southbound carriageways.

A90 to A956 Southbound Diverge

Week commencing 16/09/2017: Lane closures will be in place when required on the A90 from 8pm Friday 15 September to 6am Monday 18 September. Lane closures will then be in place when required on the A90 between 8pm and 6am from Monday 18 September to Friday 22 September.

Week commencing 23/09/2017: Lane closures will be in place on the A90 when required from 8pm Friday 22 September to 6am Monday 25 September. Lane closures will then be in place when required on the A90 between 8pm and 6am from Monday 25 September to Friday 29 September.

A956 to A90 Southbound Merge

Week commencing 16/09/2017: Lane closures will be in place when required on the A956 from 8pm Friday 15 September to 6am Monday 18 September. Lane closures will then be in place when required on the A956 between 8pm and 6am from Monday 18 September to Friday 22 September.

Week commencing 23/09/2017: Lane closures will be in place when required on the A956 from 8pm Friday 22 September to 6am Monday 25 September. Lane closures will then be in place when required on the A956 between 8pm and 6am from Monday 25 September to Friday 29 September.

A956 Main Carriageway

Week commencing 16/09/2017: Lane closures will be in place when required on the A956 from 8pm Friday 15 September to 6am Monday 18 September. Lane closures will then be in place when required on the A956 between 8pm and 6am from Monday 18 September to Friday 22 September.

Week commencing 23/09/2017: Lane closures will be in place when required on the A956 from 8pm Friday 22 September to 6am Monday 25 September. Lane closures will then be in place when required on the A956 between 8pm and 6am from Monday 25 September to Friday 29 September.

C5K Lochton to Auchlunies to Nigg Road (near Charleston)

Week commencing 16/09/2017: No planned traffic management.

Week commencing 23/09/2017: No planned traffic management.

A road closure between the A90 and the C5K will be in place from midnight on Tuesday 15 November 2016 for a period of 18 months. Local diversions will be in place whilst the road closure is in operation.

Plant crossings controlled by movement activated traffic signal system in operation.

U58K Haremoss to Checkbar Road

Week commencing 16/09/2017: No planned traffic management.

Week commencing 23/09/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

The project results in the closure of access between the A90 and the U58K from Saturday 02 July 2016, vehicular traffic will be able to access the A90 at Findon Junction by means of a new link road west of the main carriageway of the existing A90.

Side Roads between Charleston and River Dee

C34K Hilldowntree to Sunnyside to Causeyport Road

Week commencing 16/09/2017: No planned traffic management.

Week commencing 23/09/2017: No planned traffic management.

A permanent road closure will be in place on the C34K, from Monday 29 August 2016 to safely facilitate AWPR works, including the construction of a new bridge for farm traffic only. Local diversions will be in place and will be sign-posted.

Plant crossing controlled by movement activated traffic signal system in operation.

C30K Hillside to Batchart Road

Week commencing 16/09/2017: No planned traffic management.

Week commencing 23/09/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.

C5K Lochton to Auchlunies to Nigg Road (near Cleanhill)

Week commencing 16/09/2017: A road closure will be in place from Tuesday 15 August 10pm for 6 weeks. A local diversion route will be in place and sign posted.

Week commencing 23/09/2017: A road closure will be in place from Tuesday 15 August 10pm for 6 weeks. A local diversion route will be in place and sign posted.

Plant crossing controlled by movement activated traffic signal system in operation.

U63K Maryculter Road

Week commencing 16/09/2017: No planned traffic management.

Week commencing 23/09/2017: No planned traffic management.

Plant crossing controlled by movement activated traffic signal system in operation.


Start date 16 Sep 2017 End date 1 Oct 2017 Area 1 Southern Section (Stonehaven/Charleston to River Dee) Projects