Borders Railway reinstatement and reduction questions: EIR release
You asked for
Borders Railway – Original Construction
A. Project Approval of Reinstatement. Please indicate:
- The date upon which the reinstatement was approved
- The body which approved the reinstatement
- The cost upon which approval was granted, and the basis of its preparation and by whom, including reference (i.e. date of calculation or index basis)
- The length of new dual track to be laid from the Millerhill junction
B. Reduction in Scope. Please indicate: - The date upon which the scope reduction was approved
- The body which approved the scope reduction
- The revised cost upon which this decision was made, and that basis of its preparation and by whom including reference (i.e. date of calculation of index basis)
- The revised specifications – i.e. length reduced to single track and other infrastructure amendments.