Queensferry Crossing in full swing

Significant operations are underway over the entire footprint of the project at the same time resulting in a new peak in employment of over 1,200 people across the site.

Work on the project has kept up pace despite the wet and windy weather experienced for much of 2015. Recent milestones include:

  • The south approach viaduct has been fully launched to its final position
  • The first cables have been installed on the North Tower
  • All three of Queensferry Crossing’s towers are over 160 metres high – at least 10 metres above the height of the Forth Road Bridge
  • The new B800 bridge over the A90 was opened in July
  • Assembly of north approach viaduct is nearly complete ready for launch this autumn.

Mr Brown said:

“It’s great credit to the hard work and dedication of the men and women working on the Queensferry Crossing to see the progress they have made since my last visit. This is despite the challenging conditions they often face, particularly in the middle of the Forth estuary, even during the summer.

“Work is underway on every front across this vast project and workforce numbers are at a peak. Direct employment on this large scale infrastructure project is bringing significant benefits to the to the Scottish economy with over 1,200 people employed on site and 75 per cent having a home address in Scotland.

“Significant opportunities continue to be created for Scottish businesses through the wider supply chain. To date Scottish firms have been awarded subcontracts and supply orders from the project with a total value £246 million out of a total of £549 million.

“Everywhere you look on the project, north, south and of course out in the Forth itself, there are major operations underway or already complete. Recently the bridge’s south approach viaduct was fully launched, with assembly of the north viaduct nearly complete, and launch out over the piers expected in the autumn.

“Work on the connecting roads to both the north and south of the Crossing has made significant progress this year. Meanwhile Queensferry Crossing’s three main towers are approaching their final height and are now higher than the top of the Forth Road Bridge with another 36 metres to go on the Centre and South Towers and only 28 metres to go on the North Tower.

“The project team have done a great job in mitigating the effects of the recent poor weather and it is pleasing to report that the project remains on schedule to be complete by the end of 2016.”

Notes to editors

Background

  • A high quality video showing the final push of the south approach viaduct is available for broadcast from the Queensferry Crossing youtube channel:

https://youtu.be/pNTc66WOQgI

  • The Forth Replacement Crossing (FRC) is being delivered under budget. Down from a fixed cost budget range of £1.45 to £1.60 billion in June 2011 to a new budget range of £1.35 - £1.4 billion as announced in October 2014
  • A total of £195 million worth of savings have been released on the FRC project since construction started in June 2011. This reduction is a result of continued delivery of key construction milestones, successful management of the project and prevailing market conditions
  • The FRC is the first contract to demand that subcontracts tendered by the commercial contractors are advertised on Public Contracts Scotland procurement portal in order to give Scottish businesses the opportunity to express an interest in the work and demonstrate their capabilities.
  • All job opportunities are advertised in local job centres
  • As of June 2015, 29,236 out of 32,178 supply orders have been awarded to Scottish companies with a total value of around £115 million
  • From June 2015, Scottish firms have been awarded subcontracts or supply orders on the FRC project with a total value of around £131 million
  • For recent images and information on the project please visit: www.queensferrycrossing.co.uk

Contact:

Mark Dunlop : 01383 421397 : 07920 595 449


Published 13 Aug 2015 Tags