Preparing for the main works

August 2014 – December 2014

A pre-start works agreement enabled the preferred bidder to undertake further design work and to begin works including environmental surveys and ground investigations ahead of the main works contract.

October 2012 – August 2014

Several major advance works were undertaken in this period, including archaeological surveys, ground investigations and hydrological and hydrogeological monitoring.

A range of environmental mitigation measures were also completed. This involved the creation of new habitats for a wide range of protected species, including water voles, badgers, bats, red squirrels and otters.

2006 – September 2012

In addition to the statutory process and design development work, one of the largest environmental and ecological surveys in Scottish development history was undertaken.


Published date 20 Dec 2014 Projects