Progress report - Autumn 2024 - A9 Short term measures - A9 Safety Group

In December 2022 the Scottish Government announced a £5M package of additional engineering measures to be applied to the A9 from Perth to Inverness between 2023 and 2025 and which are intended to address the perceived contributory factors to collisions in 2022.

These measures include:

  • New centre and edge lines marked using high specification “Weatherline Plus” material that has enhanced reflectivity and acoustic properties (i.e. textured lines, which aim to act as a noise warning for drifting vehicles). Changes to existing markings to provide double white lines (prohibiting overtaking) will be progressed around junctions where feasible and supported by Police Scotland.
  • Illuminated road studs to provide greater clarity of junction layout at night, along with new/refreshed red infill surface in hatched areas (where required) to give greater emphasis, at junctions not currently treated.
  • Upgrade to the transition from dual to single carriageway with enhanced signs indicating the end of dual carriageway, red infill in hatched areas to give greater emphasis and illuminated road studs at the transition between the two types of carriageway, along with use of “Weatherline Plus” at carriageway centre and edge lines.
  • Road signs and road markings reaffirming ‘drive on the left’ at one mile intervals, translating to ‘one minutes’ travel time at 60mph.
  • Deployment of variable message signs (VMS) displaying road safety messages at eight strategic locations during holiday season.
Before and after improvements to approach to single carriageway
Before and after improvements to approach to single carriageway
Before and after improvements to approach to dual carriageway
Before and after improvements to approach to dual carriageway
Before and after improvements to junction markings
Before and after improvements to junction markings
Single carriageway with red delineation between each side of the road
Single carriageway lane delineation
Solar studs lighting up the approach and exit at the junction on the left
Solar studs at junction
Red tarmac between sides of the road at the transition from single to dual carriageway
Red surface infill at dual/single carriageway transition

Short term measure update

Details of the progress made so far on each element is shown below with completion dates for each section. The overall programme of works is scheduled to be completed in March 2025.

Single carriageway marking enhancements (8 sections)

Complete

  • Bankfoot to Dalguise (May 2023)
  • Dalguise to Ballinluig (October 2023)
  • Pitlochry S to Faskally (December 2023)
  • Killiecrankie to Drumochter (June 2024)
  • Dalraddy to Slochd (October 2022)
  • Drumochter (N) to Crubenmore (July 2024)

In progress

  • Kincraig to Aviemore
  • Crubenmore (DC) to Kincraig

Junction enhancements (15 junctions)

Complete

  • A924 Pitlochry N (February 2024)
  • B8029 S Blair Atholl (February 2024)
  • B8029 House of Bruar (February 2024) 
  • B847 Calvine (May 2024)
  • A889 Dalwhinnie (May 2024)
  • B9150 Ralia (February 2024) 
  • Clunie/Cluniemore (December 2023)
  • Foss Road (April 2024)
  • Crubenmore (August 2024)
  • Glentruim (August 2024)
  • Trinafour (June 2024)

Programmed

  • A86 Kingussie S & N
  • B9152 Aviemore S (Lynwilg)
  • A95 Aviemore N (Granish)
  • A938 Carrbridge

Dual to Single marking enhancements (12 interfaces)

Complete

  • Bankfoot-Dunkeld (May 2023)
  • Killiecrankie S (January 2024)
  • Killiecrankie N (January 2024)
  • Drumochter N (May 2024)
  • Crubenmore S (August 2024)
  • Crubenmore N (Glen Truim) (August 2024)

In progress

  • Kincraig
  • Slochd

Programmed

  • Ballinluig S
  • Pitlochry S
  • Drumochter S
  • Dalraddy

Dual to Single carriageway interface traffic signs (12 interfaces)

Complete

  • Bankfoot-Dunkeld (May 2023)

In progress

  • Drumochter S
  • Drumochter N

Programmed

  • Ballinluig S
  • Pitlochry S
  • Killiecrankie S
  • Killiecrankie N
  • Crubenmore S
  • Crubenmore N (Glen Truim)
  • Kincraig
  • Dalraddy
  • Slochd

Two-way offset arrow markings (7 sections)

Complete

  • Bankfoot to Dalguise (May 2023)
  • Dalguise to Ballinluig (October 2023)
  • Pitlochry S to Faskally (December 2023)
  • Killiecrankie to Drumochter (June 2024)
  • Drumochter (N) to Crubenmore (July 2024)

In progress

  • Crubenmore DC to Kincraig

Programmed

  • Dalraddy to Slochd

Two-way warning signs (7 sections)

Complete

  • Bankfoot to Dalguise (May 2023)
  • Dalguise to Ballinluig (September 2024)
  • Crubenmore DC to Kincraig (August 2024)

In progress

  • Pitlochry S to Faskally
  • Killiecrankie to Drumochter

Programmed

  • Drumochter (N) to Crubenmore
  • Dalraddy to Slochd


Published date 9 Oct 2024 Topic