A898 Erskine Bridge vehicle barrier replacement
The barriers needed to be replaced as the existing vehicle barrier arrangement did not provide the level of protection required to the bridge towers and cable anchorages against heavy goods vehicle (HGV) impact.
Why was the work needed?
The existing nearside barriers were non-standard with an unknown level of containment consisting of tubular post and double rail.
The replacement barriers reduce the risk of structural damage to the bridge towers, cable anchorages and nearside deck cantilever sections.
What was involved?
Specialist Contractors:
- removed the existing vehicle barriers on the central reserve and the nearside lane
- installed new H4a High and N2 containment vehicle barriers
At the same time, we took the opportunity to:
- undertake carriageway surfacing repairs
- repaint the white lining
How much did it cost?
Final cost will be determined at the end of the 52 week maintenance period.
What stage is it currently at?
The vehicle barrier replacement works were completed in September 2014.
How will it affect me?
The works represent a significant investment by Transport Scotland and will provide the level of protection required to the bridge towers and cable anchorages against heavy goods vehicle (HGV) impact.
The works were essential to bring the vehicle barriers at Erskine Bridge up to current standards and to ensure the long term safe operation of the bridge.
Construction phase
The following report describes the processes to remove the original barrier and install the new high containment barrier at one post location on the northbound nearside barrier. Each of these processes had to take place approximately 320 times on this side Similar steps were taken in the southbound nearside barrier and the two central reserve barriers. Throughout the project over 1200 new posts were replaced and over 15600m of rails installed.
Construction process report (PDF, 13MB)
What was done to reduce the environmental impact?
The environmental impact of the works was low as the works involved replacing an existing vehicle barrier on the bridge deck. However, control measures were put in place to protect the local environment.
Contract Documentation
Documents relating to the Erskine Bridge Contract as released under Freedom of Information (Scotland) Act 2002.
The attached contract documents relate to the A898 Vehicle Barrier Replacement contract carried out by Highway Barrier Solutions between July 2013 and May 2014. Some additional work was carried out at the north approaches following the Commonwealth Games during August and September 2014:
- Erskine VBR Instructions to Tenderers_Tender Issue
- Erskine VBR List of Quantities Tender Issue
- Erskine VBR - VOL 1 Form of Tender_Tender Issue
- Erskine VBR - VOL 1 Form of Tender_Tender Issue_RevA
- Erskine VBR - VOL 2 Conditions of Contract_Tender Issue
- Erskine VBR - VOL 3 Preconstruction Information Pack_complete
- Erskine VBR - VOL 4 Spec_Tender Issue
- Erskine VBR VOL 5 Drawings Tender Issue _A3 Format
- Erskine VBR – pre-tender Meeting minutes Tender Bulletin No. 1
- Erskine VBR Tender Queries 1-13 - Tender Bulletin No. 2
- Erskine VBR – Tender amendments - Tender Bulletin No. 3
- Erskine VBR – Tender Queries 15-19 Tender Bulletin No. 4
- Erskine VBR – Tender Queries 20-23 Tender Bulletin No. 5
- Erskine VBR HBS_Tender Bulletin No. 6
- Erskine VBR Tender Bulletin 6 RevA_HBS
- Erskine VBR – Tender amendments - Tender Bulletin No. 8
- Erskine VBR Tender Bulletin 10
- Erskine VBR Tender Bulletin 11
- Erskine VBR – Tender Query - TQ - Com 02 - Phasing for Approval
- Erskine VBR – Tender Query - TQ 024 - Anti-skid Surfacing
- Erskine VBR Tender Submission Package A1 Complete
- Erskine VBR Tender Submission Package A2 Complete redact
- Erskine VBR Tender Submission Package B Complete
- Erskine VBR Package C Complete redact