Appendix 13 Water Quality Prediction

Appendix 13 Water Quality Prediction

This section is also available in pdf format (160k)

Proposed Scheme.

Water Quality Prediction

Proposed Road Configuration

29/11/2007

Leader Water

Headshaw Burn

E.Q.S. Level - copper

mg/l

3.0

3.0

Data from S.E.P.A.

E.Q.S. Level - zinc

mg/l

15.0

15.0

Data from S.E.P.A.

Area of road (A)

ha

2.08

0.91

13m wide road *

Runoff Coefficient (R)

 

0.5

0.5

Section A.3.ii, Annex 1, Part 10, DMRB Vol. 11.

Rainfall Depth (D)

mm/d

13

13

Figure A.1, Annex 1, Part 10, DMRB Vol. 11.

Q95

m3/s

0.087

0.043

Data from S.E.P.A.

CB - copper - upstream

kg/m3

0.0015

0.0015

Based on Leader Water Data of same river quality

CB - zinc - upstream

kg/m3

0.0075

0.0075

Based on Leader Water Data of same river quality

Runoff Volume (VH)

m3/day

135.2

59.2

Runoff Volume=(A x R x D/1000) x10000

Q95 (VR)

m3/day

7516.8

3749.8

95 percentile flow m3/day (Q95 x 3600seconds x 24hrs)

Dilution

 

55.6

63.4

(VR / VH) - Section A3 (iv), Annex 1, HA 216/06.

AADT

veh/day

11748

11748

From Stage 3 Traffic & Economic Assessment - Design Year (2025) Flows

Bulid up rate - Copper

kg/ha/yr

0.3

0.3

Table B.1, Annex 1, Part 10, DMRB Vol. 11.

Bulid up rate - Zinc

kg/ha/yr

1.0

1.0

Table B.1, Annex 1, Part 10, DMRB Vol. 11.

Mcu

kg/5day

0.0085

0.0037

Five day Pollutant build-up Copper

CR - soluable copper

kg/m3

0.0026

0.0025

CR = {(CB x VR)+(1000 x M)} / (VR x VH)

CR - soluable copper

mg/l

2.6

2.5

Down stream river concentration of copper in micrograms per litre µg/l

Mzn

kg/5day

0.028

0.012

Five day Pollutant build-up Zinc

Cr - zinc

kg/m3

0.0111

0.0107

CR = {(CB x VR)+(1000 x M)} / (VR x VH)

Cr - zinc

mg/l

11.1

10.7

Down stream river concentration of zinc in micrograms per litre µg/l

A68

*Area of road drained into Headshawn Burn = {(Ch1+45 to Ch2+50) x 11.75m wide road + (Ch2+50 to Ch7+35) x 13.5m wide road}/10,000m2
*Area of road drained into Leader Water = {(Ch7+35 to Ch18+30) x 13.5m wide road + (Ch18+30 to Ch21+55) x 12.75m}/10,000m2

New Side Road

*Area of road drained into Headshawn Burn = {(Ch700 to Ch1000) x 4m wide road}/10,000m2
*Area of road drained into Leader Water = {(Ch0 to Ch700) x 4m wide road}/10,000m2

Existing Scheme.

Water Quality Prediction

Existing Road Configuration

29/11/2007

Leader Water

Headshaw Burn

E.Q.S. Level - copper

mg/l

3.0

3.0

Data from S.E.P.A.

E.Q.S. Level - zinc

mg/l

15.0

15.0

Data from S.E.P.A.

Area of road * (A)

ha

1.06

0.54

13m wide road *

Runoff Coeficient (R)

 

0.5

0.5

Section A.3.ii, Annex 1, Part 10, DMRB Vol. 11.

Rainfall Depth (D)

mm

13

13

Figure A.1, Annex 1, Part 10, DMRB Vol. 11.

Q95

m3/s

0.087

0.043

Data from S.E.P.A.

CB - copper - upstream

kg/m3

0.0015

0.0015

Based on Leader Water Data of same river quality

CB - zinc - upstream

kg/m3

0.0075

0.0075

Based on Leader Water Data of same river quality

Runoff Volume

m3/day

68.9

35.1

Runoff Volume=(A x R x D/1000) x10000

Q95

m3/day

7516.8

3749.76

95 percentile flow m3/day (Q95 x 3600seconds x 24hrs)

Dilution

 

109

107

(VR / VH) - Section A3 (iv), Annex 1, HA 216/06.

AADT

veh/day

11748

11748

From Stage 3 Traffic & Economic Assessment - Design Year (2025) Flows

Build up rate - Copper

kg/ha/yr

0.3

0.3

Table B.1, Annex 1, Part 10, DMRB Vol. 11.

Build up rate - Zinc

kg/ha/yr

1.0

1.0

Table B.1, Annex 1, Part 10, DMRB Vol. 11.

Mcu

kg/5day

0.0044

0.0022

Five day Pollutant build-up Copper

CR - soluable copper

kg/m3

0.0021

0.0021

CR = {(CB x VR)+(1000 x M)} / (VR x VH)

CR - soluable copper

mg/l

2.1

2.1

Down stream river concentration of copper in micrograms per litre µg/l

Mzn

kg/5day

0.015

0.007

Five day Pollutant build-up Zinc

Cr - zinc

kg/m3

0.0093

0.0094

CR = {(CB x VR)+(1000 x M)} / (VR x VH)

Cr - zinc

mg/l

9.3

9.4

Down stream river concentration of zinc in micrograms per litre µg/l

*Area of road drained into Headshawn Burn = {(Ch1+45 to Ch5+50) x 10m wide road + (Ch5+50 to Ch7+35) x 7.3m}/10,000m2
*Area of road drained into Leader Water = {(Ch7+35 to Ch21+00) x 7.3m wide road + (Ch21+00 to Ch21+55) x 12m}/10,000m2