Description of main enviromental impacts and proposed mitigation

Air quality

Impacts

  • On site construction activities carry the potential to produce airborne particulate matter, dust and generate emissions that may have a temporary impact on local air quality levels and act as a nuisance to nearby residents.
  • TM being implemented during the scheme may result in an increase in associated vehicle emissions through idling vehicles and increased congestion, particularly on routes impacted by diversions.
  • Renfrewshire Council’s declared AQMAs will be unimpacted by the works due to the scheme’s minor, temporary nature and the general distance of the sites from the area of works.

Mitigation

  • Best practice and measures as outlined in the ‘Guidance on the assessment of dust from demolition and construction (January 2024)’ published by the Institute of Air Quality Management (IAQM), which includes the following mitigation relevant to this scheme, will be followed:
  • The site layout will be planned (including plant, vehicles and Non-Road Mobile Machinery (NRMM)) so that machinery and dust causing activities are located away from receptors, as far as reasonably practicable;
  • Materials that have a potential to produce dust will be removed from site as soon as possible, unless being re-used on site (stockpiles will be covered or fenced to prevent wind whipping);
  • Cutting, grinding or sawing equipment will be fitted or used in conjunction with suitable dust suppression techniques such as water sprays or local extraction, e.g. suitable local exhaust ventilation systems;
  • Drop heights from conveyors and other loading or handling equipment will be minimised;
  • Vehicles carrying wastes and materials will be covered when entering and leaving the work area to prevent escape of materials during transport;
  • Equipment will be readily available on site to clean any dry spillages and spillages will be cleaned up as soon as reasonably practicable after the event using wet cleaning methods; and
  • When not in use, plant, vehicles and NRMMs will be switched off and there will be no idling vehicles.
  • Plant, vehicles and NRMM will be regularly maintained, paying attention to the integrity of exhaust systems to ensure such fuel operated equipment is not generating excessive fumes.
  • Green driving techniques will be adopted, and effective route preparation and planning will be undertaken prior to works.
  • Where possible, materials will be sourced locally.
  • Surfaces will be swept where loose material remains following planing.

No significant effects are predicted on air quality. Therefore, in accordance with DMRB Guidance document LA 105: Air Quality no further assessment is required.

Landscape and visual effects

Impacts

  • There will be no operational impacts on visual receptors as works entail the like-for-like resurfacing of the A737 carriageway within the scheme extents.
  • Residential receptors and core paths with sight of the works have the potential to be visually impacted by the scheme during construction due to the presence of TM, plant, vehicles, machinery and operatives.
  • The general setting of the area may be impacted during construction due to the presence of TM, plant, vehicles, machinery and operatives.

Mitigation

  • Works will be contained within the A737 carriageway extents.
  • Asset installation will be of a minimal visual impact (if any due to the like-for-like nature of the scheme) and will be in keeping with the current setting of the A737 carriageway within the scheme extents.
  • Temporary site lighting used throughout the scheme will be directional and pointed only at the area of works.

The effect on landscape and visual effects is deemed to be neutral. Therefore, in accordance with DMRB Guidance document LA 107: Landscape and Visual Effects, no further assessment is required.

Biodiversity

Impacts

  • During night-time programming, misdirected site lighting and additional noise could cause temporary disturbance to any surrounding nocturnal species.
  • There is potential for protected species to be active within the surrounding area and for the works to result in disturbance to these species.
  • Due to the scheme being contained within the pavement boundary, the INNS and Transport Scotland Target Species identified within 500m of the scheme extents will not be impacted by the works.
  • The scheme has potential connectivity to the Black Cart SPA and the Inner Clyde and Ramsar SPA (and associated SSSIs) and thus these sites may be impacted by the works through pollution events.

Mitigation

  • An HRA has been undertaken to assess the impacts of the scheme upon the aforementioned designated European sites. No direct impacts or significant effect pathways are anticipated for the qualifying interests of the European sites, with the sites located over 2km north of the scheme. There is physical connection of functional habitats suitable for some designated species (via the Candren Burn), however noise and visual disturbance and water and air pollution risks will be appropriately minimised by standard pollution and noise controls.
  • As part of the Network Management Contract, Amey, on behalf of Transport Scotland, has been asked to keep a record of various target species. Works will not cause the spread of these species, if a possibility arises wherein works are likely to result in the spread of these species through disturbance, the appropriate Amey landscaping team will be consulted.
  • In the event that protected species are sighted, works will temporarily be suspended and will be reported to the Amey ET&S team for any guidance, if required, and the control room will be contacted for environmental record.
  • All works and storage of plant, machinery, vehicles and equipment will be restricted to the boundaries of the carriageway.
  • All site lighting will be directed away from sensitive ecological receptors such as woodland and watercourses.
  • Noise mitigation measures, as outlined in the Noise and Vibration section, and pollution control mitigations, as outlined in the Road Drainage and the Water Environment section, will be adhered to during the works.

No significant effects are predicted on biodiversity. Therefore, in accordance with DMRB Guidance document LA 108: Biodiversity, no further assessment is required.

Material assets and waste

Impacts

  • The design life for the TS2010 surfacing proposed is estimated to be 20 years. This will reduce the requirement for maintenance to this section of road over this period.
  • The works will result in contribution to resource depletion through use of virgin materials.
  • GHG emissions will be generated by material production and transportation to and from site.
  • Transportation and recovery of materials/waste will require energy deriving from fossil fuels, a non-renewable source.

Mitigation

  • Materials will be derived from recycled, secondary or re-used origin as far as practicable within the design specifications to reduce natural resource depletion and associated emissions.
  • It is Amey policy to reuse or recycle as much waste material as possible. Where reuse is not feasible, waste material will be removed to a licenced waste facility.
  • Where possible, different waste streams will be separated at the source.
  • Waste will be stored in suitable containers and covered.
  • The waste hierarchy (Reduce, Reuse, Recycle and Dispose) will be employed throughout the construction works. Waste contractors on-site will adhere to the duty of care with regards to the disposal of removed materials.
  • Following on-site coring investigations and testing, no coal-tar was identified within the surfacing of the carriageway within the scheme extent. As such, road planings generated as a result of the works will be recovered in accordance with the criteria stipulated within SEPA document ‘Guidance on the Production of Fully Recoverable Asphalt Road Planings’ where possible.

With best practice mitigation measures in place, no significant effects are predicted in relation to Material Assets and Waste. Therefore, in accordance with DMRB Guidance document LA 110: Material Assets and Waste, no further assessment is required.

Noise and vibration

Impacts

  • TS2010 road surfacing is shown to have superior durability and noise reducing features compared to standard road surfacing mixes.
  • Noise and vibration heavy works will likely be required during night-time hours, which could cause disturbance for nearby sensitive receptors (such as residential and non-residential properties within 300m).
  • Noise impacts will result from vehicle traffic along the potential night-time diversion routes as a result of the TM being implemented, thus causing increased noise levels and disturbance to nearby receptors.

Mitigation

  • The noisiest works will be completed before 23:00 where feasible.
  • Plant/machinery will be fitted with silencers/mufflers.
  • No plant, vehicles or machinery will be left idling when not in use.
  • A soft start to the works will be undertaken, whereby plant/machinery will be turned on sequentially as opposed to simultaneously.
  • Amey’s environmental briefing on noise and vibration will be delivered to operatives prior to the start of construction.
  • Diversion routes will be discussed with the local authority to obtain a route(s) with minimal disruption.
  • Amey’s ET&S team has contacted Renfrewshire Council’s Environmental Health Team to notify of the works due to night-time programming.
  • Due to night-time programming, properties within 300m of the scheme extents will be notified in advance of the works. Pre-notification will include details of proposed timings and duration.

With best practice mitigation measures in place, and due to the works being of a minor and transient nature, no significant effects are predicted for noise and vibration. Therefore, in accordance with DMRB Guidance document LA 111: Noise and Vibration and no further assessment is required.

Population and human health

Impacts

  • Construction site lighting during night-time hours could cause disturbance for residential properties in close proximity, and for the nearby amenity users.
  • TM for the works will involve road closures and a potential night-time diversion route:
    • Nearby residents of surrounding settlements may experience travel disruption due to presence of TM, which may lead to increased journey lengths and times.
  • There will be no impact on land take from private land, community facilities or agricultural land as a result of the scheme as all works will be contained within the carriageway boundary.
  • On/off slips present at the northernmost and southernmost scheme extents are likely to be impacted by the works.
  • No impacts on Renfrewshire Council Core Paths within proximity to the scheme extents are anticipated due to their distance and separation from the area of works.

Mitigation

  • TM (including carriageway closures) will be advertised upon approach and in advance of the scheme. Potential closures and diversions routes will be discussed in advance with the relevant Renfrewshire Council department by Amey.
  • When in place, TM will be monitored to ensure it is effectively managing traffic flow.
  • Temporary site lighting used throughout the scheme will be directional and pointed only at the area of works.
  • Further site specific control measures regarding noise and vibration, landscape and visual effects and air quality can be found in the relevant sections (above).

No significant effects on population and human health are predicted. Therefore, in accordance with DMRB Guidance document LA 112: Population and Human Health, no further assessment is required.

Road drainage and the water environment

Impacts

  • If not adequately controlled, debris and runoff from the works could enter surrounding surface water environment. In the event of rain and/or a flooding incident, this debris may be mobilised and could enter the road drainage system, thus having a detrimental effect on the surrounding local water environment.
  • Potential for spills, leaks or seepage of fuels and oils associated with plant to escape and reach drainage systems and watercourses if not controlled, which may negatively affect the surrounding water environment.
  • Should flooding occur, this may delay the scheduled works.
  • The scheme has the potential to impact the Candren Burn and the Black Cart Water watercourses via pollution events.

Mitigation

  • All debris which has the potential to be suspended in surface water and wash into the local water environment will be cleaned from the site both during and following the works.
  • Debris and dust generated as a result of the works will be prevented from entering the drainage system. This will be via the use of drain covers or similar.
  • Appropriate measures will be implemented onsite to prevent any potential pollution to the natural water environment (e.g., debris, dust, and hazardous substances). This will include spill kits being present onsite at all times, and the use of funnels and drip trays when transferring fuel etc.
    • The Amey control room will be contacted if any pollution incidences occur (24 hours, 7 days a week).
  • Visual pollution inspections of the working area will be conducted frequently, especially during heavy rainfall and wind.
  • Weather reports will be monitored prior to and during all construction activities. In the event of adverse weather/flooding events, all activities will temporarily stop and only reconvene when deemed safe to do so.
  • All storage of materials/fuel and any refuelling activities will be more than 10m away from any drainage inlet at all times and placed on a hardstanding surface with an appropriate level of bunding.
  • Storage areas will be located away from areas that see high vehicular movement to prevent accidental damage.
  • All oils and fuels will be returned to storage area after use.
  • Amey’s environmental briefing on water pollution prevention will be delivered to operatives prior to the start of construction.
  • All site operatives will be made aware of the locations of the Candren Burn and Black Cart Water prior to works commencing.

Providing all works operate in accordance with current best practice, as demonstrated by SEPA’s Guidance for Pollution Prevention (GPPs), no significant effects are predicted on the water environment. Therefore, in accordance with DMRB Guidance document LA 113: Road drainage and the water environment no further assessment is required.

Climate

Impacts

GHG emissions will be emitted through the use of machinery, vehicles and materials used (containing recycled and virgin materials) and transporting to and from site.

Mitigation

  • Local suppliers will be used as far as reasonably practicable to reduce travel distance and GHG emitted as part of the works.
  • Vehicles/plant will not be left on when not in use to minimise and prevent unnecessary emissions.
  • Further actions and considerations for this scheme are detailed in the above Material assets and waste section.

With best practice mitigation measures in place, the significance of effect on climate is considered to be neutral. Therefore, in accordance with DMRB Guidance document LA 114: Climate, no further assessment is required.

Vulnerability of the project to risks

As the works will be limited to the like-for-like replacement of the carriageway structure, there will be no change in vulnerability of the road to risk, or in severity of major accidents/disasters that would impact on the environment.

It has been determined that the project is not expected to alter the vulnerability of the existing trunk road infrastructure to risk of major accidents or disasters.

Assessment cumulative effects

The Scottish Road Works Commissioner's Interactive Map has not highlighted any works during the proposed timescale and at the location of the works.

Renfrewshire Council’s Planning Portal has not highlighted any planning applications within the scheme extents at the time of the works in question.

Amey’s current programme of works has not highlighted any other works on the A737 carriageway that will be undertaken in conjunction with the scheme.

No other nearby schemes which may result in a combined effect on nearby receptors have been identified.

Any future schemes will be programmed to take into account already programmed works, and as such any effect (such as from TM arrangements and potential construction noise) will be limited.