Project Details

Description

Resurfacing works are required to maintain the safety and integrity of a section of the A77 carriageway located south of Ayr as the existing carriageway is displaying surface and structural defects such as fretting, crazing, longitudinal and alligator cracking.

In addition to structural inlays, minor verge works will be carried out, comprising filter stone replacement, vehicle restraint system (VRS) upgrades and footway and layby upgrades. 

Resurfacing treatment will include inlays to remove deterioration and reinstate binder layers, with deeper partial reconstructions applied in localised patches where more extensive deterioration is present. The scheme will replace the existing pavement with new Hot Mix Asphalt (HMA) surface course and AC binder layers to ensure consistency, durability and long-term performance. Road studs and lining will be refreshed as part of the scheme.

The following plant and machinery will be required:

  • Planer;
  • Paver;
  • Miller;
  • Wagon;
  • Roller;
  • Excavator; and
  • Traffic Management (TM) plant.

The scheme is 1.71 kilometres (km) long, with a total area of approximately 1.4 hectares (ha).

The proposed works are programmed for completion within the 2026-2027 financial year, with construction currently proposed for November 2026. TM will consist of a full road closure, supported by an overnight convoy system. During the closure, northbound traffic will be diverted via the B7023 at Maybole and the A719 towards Ayr, rejoining the A77 at Ayr. Southbound moving traffic will follow the same diversion route in reverse.

The works will be carried out overnight for approximately two-weeks.

Location

This section of the A77 dual carriageway, located north of Minishant, South Ayrshire at the following National Grid References (NGRs) (Figure 1):

  • Scheme start: NS 33072 14344

Scheme end: NS 33797 15798