Description of main environmental impacts and proposed mitigation
Air quality
Construction activities associated with the proposed works have the potential to temporarily cause local air quality impacts. Activities undertaken on site may cause dust and particulate matter to be emitted to the atmosphere. However, taking into account the nature and scale of the works and the following mitigation measures, the risk of significant impacts to air are considered to be low.
- A water assisted dust sweeper will sweep the carriageway after dust-generating activities, and waste will be contained and removed from site as soon as is practicable.
- Materials that have a potential to produce dust will be removed from site as soon as possible, and vehicles that remove cold-milled material from site will have sheeted covers.
- Ancillary plant, vehicles and non-road mobile machinery (NRMM) will have been regularly maintained, paying attention to the integrity of exhaust systems.
- Ancillary plant, vehicles and NRMM will be switched off when stationary to prevent exhaust emissions (e.g., there will be no idling vehicles).
- Cutting, grinding, and sawing equipment (if required) will be fitted or used in conjunction with suitable dust suppression techniques e.g., local exhaust ventilation system that fits directly onto tools.
- Regular monitoring (e.g., by engineer or Clerk of Works) will take place when activities generating air pollution are occurring. In the unlikely event that unacceptable levels of air pollution are emanating from the site, the operation will, where practicable, be modified and re-checked to verify that the corrective action has been effective. Actions to be considered include: (a) minimizing cutting and grinding on-site, (b) reducing the operating hours, (c) changing the method of working, etc.
- All delivery vehicles carrying material with dust potential will be covered when travelling to or leaving site, preventing the spread of dust beyond the work area.
- Material stockpiles will be reduced as far as is reasonably practicable by using a ‘just in time’ delivery system. All material will also be stored on made ground.
- Any stockpiled material on site will be monitored daily to ensure no risk of dust emissions exists.
- Materials will be removed from site as soon as is practicable.
- Good housekeeping will be employed throughout the work.
With the above mitigation measures in place, it is anticipated that any air quality effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this Record of Determination (RoD).
Cultural heritage
Although three Listed Buildings lie within 20 metres of the works, one of which is located approximately 3–5 metres east of the A82 carriageway at the A82 South of Inverarnan scheme, all works will be confined to the existing road surface and its associated drainage infrastructure (e.g. gullies). No works are proposed on or immediately adjacent to the Listed Buildings, and no impacts are anticipated.
The works comprise a like-for-like renewal of the road surface and routine maintenance of the road drainage system. As such, they have been assessed as not having an adverse impact on the cultural heritage value of nearby heritage assets, provided the following mitigation measures are in place:
- All site personnel will be briefed on the importance of cultural heritage value within the area.
- If there are any unexpected archaeological finds, works will stop temporarily in the vicinity, the area will be cordoned off and a member of the BEAR Environment team will be contacted for advice.
- Laydown areas will be sensitively located (e.g., on areas of made ground) to avoid areas of cultural heritage interest where possible.
- There will be no storage of plant, materials or equipment against buildings, bridges, walls or fences.
With the above mitigation measures in place, it is anticipated that any cultural heritage effects associated with the proposed scheme are unlikely to be significant. This receptor is not considered further in this RoD.
Landscape and visual effects
The works lie within the boundary of the LLTNP. However, the works are like-for-like general maintenance of the trunk road surface and its drainage system and as such the works will not have an impact on landscape character associated with the LLTNP. Though, the National Park Authority will be notified of the works prior to construction commencing.
There will be a short-term impact on the landscape character and visual amenity of the site as a result of the presence of construction plant, vehicles, and TM. However, the works are of a short duration (up to nineteen nights), undertaken during the nightime hours (19:00 – 06:00) and restricted to the A82 carriageway boundary and generally screened from the wider landscape by woodland and roadside tree shelterbelts. Land use will not change as a result of the works, and the works will not result in any residual change to the visual amenity of the local landscape.
In addition, the following mitigation measures will be put in place during works:
- Throughout all stages of the works, the site will be kept clean and tidy, with materials, equipment, plant and wastes appropriately stored, reducing the landscape and visual effects as much as possible.
- LLTNP advice, if received, will be complied with.
- Works will avoid encroaching on land and areas where work is not required or not permitted. This includes general works, storage of equipment/containers and parking.
- Where applicable, upon completion of the works, any damage to the local landscape will be reinstated as much as is practicable.
- The site will be left clean and tidy following construction.
With the above mitigation measures in place, it is anticipated that any landscape and visual effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Biodiversity
The works lie within 2km of Glen Etive and Glen Fyne SPA and Loch Lomond Woods SAC and as such an HRA Proforma was undertaken to assess potential effects of the proposed resurfacing and drainage works on the SAC and SPA. The HRA Proforma concluded that the works would not result in LSE on the qualifying features of Glen Etive and Glen Fyne SPA and Loch Lomond Woods SAC due to the minor nature of the works and standard measures for pollution prevention.
Although a record of Japanese knotweed, INNS, was noted within A82 road verges within A82 South of Inverarnan scheme extents, the works will be restricted to the carriageway and its drainage system and as such it is unlikely that any invasive weeds will be encountered during the works. Furthermore, noted INNS of plants will be controlled/treated by cultural methods and/or chemical weed control as per the NW Annual Landscape Management Plan.
Activities undertaken on site could potentially have a temporary adverse impact on biodiversity in the area as a result of an increased vehicle presence and the potential for disturbance to protected species and pollution of habitats. However, works are restricted to the A82 carriageway and its drainage system and the number of construction vehicles and construction operatives required onsite is low given the scale and scope of works. In addition, any species in the area are likely to be accustomed to noise and visual disturbance pertaining to vehicle movements on the A82 and the scheme is of short duration (up to nineteen nights) and will be undertaken on a rolling programme. The potential for significant species disturbance within the area of likely construction disturbance is therefore considered to be low.
Although the majority of the scheme extents is flanked by areas of ancient woodland; no tree felling is planned for the works.
Pollution controls and good practice measures to reduce impacts of works on the local environment will be detailed in the SEMP and adhered to on site. Therefore, with the following mitigation measures in place, the risk of significant impacts on biodiversity are considered to be low:
- Works will be strictly limited to areas required for access and to carry out the works. Unnecessary encroachment onto terrestrial or aquatic areas will not be tolerated.
- All construction operatives will be briefed through toolbox talks prior to works commencing, which will be included in the SEMP. The toolbox talks will provide information on the legislation, general ecology, and best practice measures for relevant protected species.
- Site personnel will remain vigilant for the presence of any protected species throughout the works period. Should a protected species be noted during construction, works will temporarily halt until the species has sufficiently moved on. Any sightings of protected species will be reported to the BEAR Scotland Environmental Team. If required, NatureScot will be contacted for advice.
- Artificial lighting will be directed away from areas of woodland and waterbodies as far as is safe and reasonably practicable.
- Personnel will remain vigilant for the presence of INNS or injurious weeds in road verges throughout the works period. Should any INNS be identified in working areas, works will be restricted to a 7m buffer of any growth where reasonably practicable.
- A ‘soft start’ will be implemented on site each day. This will involve switching on vehicles and checking under/around vehicles and the immediate work area for mammals prior to works commencing to ensure none are present and that there is a gradual increase in noise.
- Any excavations, exposed pipes/drains, or areas where an animal could become trapped (e.g. storage containers) will be covered over when not in use, at the end of each shift, and following completion of the works to avoid animals falling in and becoming trapped.
- If fencing is utilised at any point during the works, a gap of 200mm from ground level will be provided, allowing free passage for mammals and preventing entrapment.
With the above mitigation measures in place, it is anticipated that any biodiversity effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Material assets and waste
There is potential for impacts as a result of resource depletion through use and transportation of new materials. However, materials will be sourced locally where possible and the following mitigation measures will be put in place:
- Materials will be sourced from recycled origins as far as reasonably practicable within design specifications.
- Care will be taken to order the correct quantity of required materials to prevent the disposal of unused materials.
- Where possible, minimal packaging will be requested on required deliveries to reduce unnecessary waste and production of packaging materials.
There is potential for impacts during works as a result of the improper storage or disposal of waste. The following mitigation measures will be put in place:
- The waste hierarchy (Reduce, Reuse, Recycle and Dispose) will be employed throughout the construction works.
- The subcontractor will adhere to waste management legislation and ensure they comply with their Duty of Care.
- Containment measures will be in place to prevent debris or pollutants from entering the surrounding environment.
- Planings will be re-used or recycled under a SEPA Paragraph 13(a) waste exemption and in line with BEAR Scotland’s procedure 126: The Production of Fully Recovered Asphalt Road Planings.
- All wastes and unused materials will be removed from site in a safe and legal manner by a licensed waste carrier upon completion of the works. The appointed waste carrier will have a valid SEPA waste carrier registration, a copy of which will be provided to and retained by BEAR Scotland as early as possible.
- All appropriate waste documentation will be present on site and will be available for inspection. A copy of the Duty of Care paperwork must be provided and filed appropriately in accordance with the Code of Practice (as made under Section 34 of Environmental Protection Act 1990 as amended).
- Re-use and recycling of waste will be encouraged and undertaken where possible, and the subcontractor will be required to fully outline their plans and provide documentary evidence for waste arising from the works (e.g., waste carrier’s licence, transfer notes, and waste exemption certificates).
- Staff will be informed that littering will not be tolerated. Staff will be encouraged to collect any litter seen on site.
- Where applicable, all temporary signage will be removed from site on completion of the works.
With the above mitigation measures in place, it is anticipated that any material assets and waste effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Noise and vibration
Construction activities associated with the proposed works have the potential to cause noise and vibration impacts through the use of equipment and construction vehicles for the proposed activities. The works will also be completed over up to nineteen nights on a rolling programme with the aim being to complete the noisiest works by 23:00 where possible. Due to the short duration and localised and transient nature of the works, the proposed scheme is anticipated to result in temporary minor noise impacts during the construction programme.
A number of properties located within 50m of the scheme have only limited screening provided from the A82 carriageway at the scheme extents. As such, there is potential for disturbance to residents, however with mitigation in place disturbance will be minimised and significant impact to these receptors is not predicted.
The road surface is in a poor condition with a series of defects. Replacing the life-expired surface course affords the benefits of a reduction in mid-to-high frequency traffic noise and a reduction in ground vibrations. As a result, upon completion of the work, noise associated with the movement of vehicles on the trunk road should decrease post construction.
The following mitigation measures will be put in place:
- The Best Practicable Means, as defined in Section 72 of the Control of Pollution Act 1974, will be employed at all times to reduce noise to a minimum.
- Affected residents, business premises and the Environmental Health Officer (EHO) for relevant administrative areas will be notified of works.
- All site staff will receive the ‘Being a Good Neighbour’ toolbox talk.
- The noisiest works (e.g. planing) will be programmed to be completed by 23:00 where possible.
- Drop heights from vehicles and NRMM will be kept to a minimum to minimise noise when unloading.
- All plant, machinery and vehicles will be switched off when not in use.
- On-site construction tasks will be programmed to be as efficient as possible, with a view to limiting noise disruption to local sensitive receptors.
- All site personnel will be fully briefed in advance of works regarding the need to minimise noise during works and of the site-specific sensitivities.
- All plant will be operated in such a way that minimises noise emissions and will have been maintained regularly to the appropriate standards.
- Where fitted, and where permitted under Health and Safety requirements, white noise reversing alarms will be utilised during construction.
- Where ancillary plant such as generators are required, they will be positioned so as to cause minimum noise disturbance. Where deemed necessary, acoustic screens will be utilised.
With the above mitigation measures in place, it is anticipated that any noise and vibration effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Population and human health
During construction, activities undertaken on site have the potential to have temporary adverse impacts on vehicle travellers. There is potential for impacts on human receptors due to A82 trunk road closures, however regular amnesties will be provided. No significant congestion issues are envisioned due to the proposed off-peak construction hours. Increased journey times may occur, but these are considered insignificant considering the relatively low traffic count during the night-time programming.
Pedestrian facilities are present within and in proximity to the scheme extents however the works are undertaken at nightime when footfall is to be at its lowest. Access for non-motorised users (NMUs) will be maintained throughout the works.
With the following mitigation measures in place, the risk of significant impacts on population and human health is considered to be low:
- Notification will be issued to local residents and local public transport operators prior to commencement of the works, advising of any proposed works and expected restrictions.
- Local access will be granted as required.
- Any changes of schedule (e.g. change from nighttime works to daytime works) will be communicated to travelling public throughout the programme.
- Appropriate provisions / measures will be implemented within the TM to allow the safe passage of NMUs of all abilities through the site (if required).
- Journey planning information will be available for drivers online at the trafficscotland.org website. Journey planning information will also be available for drivers online through BEAR’s social media platforms.
With the above mitigation measures in place, it is anticipated that any population and human health effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Road drainage and the water environment
There is potential for temporary impacts on the water environment due to operation of plant within and within proximity to watercourses and/or drainage systems, which may lead to potential changes in water quality from pollution events (either by accidental spillage of sediments, particulate matter, chemicals, fuels or by mobilisation of these in surface water caused by rain). No in-water works within natural watercourses will take place and there is no requirement for the abstraction or transfers of water from, or discharges to, a waterbody. As such, the potential for a direct pollution incident within a waterbody is unlikely. Experience gained from BEAR maintenance schemes elsewhere on the network has shown that where standard good working practice is adopted (e.g., adherence to SEPA good practice guidance, utilisation of drain covers or similar, etc.), water quality is protected.
The works may result in potential direct or indirect effects on surrounding waterbodies. The following mitigation measures will be put in place to reduce the risk of pollution incidents as a result of works:
- The scheme will not entail any in-stream works within natural waterbodies.
- Standard working practices to comply with The Water Environment (Controlled Activities) (Scotland) Regulations 2011 (as amended) for works in or near water are detailed in the SEMP and will be adhered to on site.
- No discharges into any watercourses or drainage systems are permitted. Appropriate containment measures will be in place to prevent any loss of construction materials into the water environment.
- Appropriate measures will be implemented during resurfacing operations to limit the potential for wastes (i.e. road planings) and materials (i.e. new asphalt) to enter any gullies present on site. On completion of resurfacing operations, any gullies present on site should be visually checked to ensure they have not become blocked as a result of the scheme.
- An incident response (contingency) plan will be put in place to reduce the risk from pollution incidents or accidental spillages. All necessary containment equipment, including suitable spill kits (for oil and chemicals) will be available on site, quickly accessible if needed, and staff trained in their use.
- All spills will be logged and reported. In the event of any spills into the water environment, all works will stop, and the incident will be reported to the project manager and the BEAR Scotland Environmental Team. SEPA will be informed of any such incident as soon as possible using the SEPA Pollution Hotline.
- All plant and equipment will be regularly inspected for any signs of damage and leaks. A checklist will be present to make sure that the checks have been carried out.
- Storage of hazardous material, oil and fuel containers will be distanced more than 10m away from any watercourses.
- If required, a designated refuelling area will be identified. Fuel bowsers will be stored on an impermeable area and will be fully bunded. This will be distanced more than 10m from any watercourses.
- During refuelling of smaller mobile plant, a funnel will be used, and drip trays will be in place. Care will be taken to reduce the chance of spillages. Spill kits will be quickly accessible to capture any spills should they occur. The ground / stone around the site of a spill will be removed, double bagged and taken off site as special contaminated waste.
- Generators and static plant may have the potential to leak fuel and / or other hydrocarbons and will have bunding with a capacity of 110%. If these are not bunded then drip trays must also be supplied beneath the equipment with a capacity of 110%.
With the above mitigation measures in place, it is anticipated that any road drainage and the water environment effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Climate
Construction activities associated with the proposed scheme works have the potential to cause local air quality impacts as a result of the emission of greenhouse gases through the use of vehicles and machinery, material use and production, and transportation of materials to and from site. The following mitigation measures will be put in place:
- BEAR Scotland will adhere to their Carbon Management Policy.
- Local contractors and suppliers will be used as far as practicable to reduce fuel use and greenhouse gas emitted as part of the works.
- Where possible, materials will be sourced locally to reduce greenhouse gas emissions associated with materials movement, and waste will be disposed at local landfill.
With the above mitigation measures in place, it is anticipated that any climate effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Vulnerability of the project to risks
Banks of Allt Arnan and Loch Lomond which lie in proximity to the scheme have been noted to have a high (10% chance) risk of fluvial flooding. Works will be programmed as far as is reasonably practicable to avoid periods of adverse weather or heavy rainfall.
Works are restricted to the made ground of the A82 carriageway and its drainage system; TM will be designed in line with existing guidance. TM will consist of nighttime road closures with amnesties. The road closures and times of amnesties will be publicised in advance. Local residents will be notified of working hours and provided with appropriate contact information. Pedestrians or other NMUs will be accommodated within the traffic management setup.
A Traffic Management Plan (TMP), which includes measures to avoid or reduce disruption to road traffic, will be produced in accordance with the Traffic Signs Manual (Department of Transport 2009). The TMP will ensure that there is no severance of community assets, access routes or residential development.
These measures, along with mitigation measures and standard working practices, will be detailed in the SEMP and adhered to on site. The vulnerability of the project to risks of major accidents and disasters is considered to be low.
Assessment cumulative effects
The proposed works are not anticipated to result in significant environmental effects. Due to the nature of the proposed works, no cumulative effects are anticipated with any other developments in the vicinity.
A search of the LLTNP Planning Portal (Loch Lomond and Trossachs National Park) identified three approved planning applications within 300m of the scheme, in the last 6 months. All of these applications are associated with Sloy Power Station and lies within 300m of A82 Viaduct scheme.
Although there is potential for cumulative effects to arise from overlapping construction periods with other developments, due to a number of factors - such as the timing and nature of the works and mitigation committed to for the proposed scheme (SEMP) - the assessment concluded that no significant cumulative effects are anticipated during the construction phase. No cumulative effects on people or property receptors are anticipated during operation given there will be no change to the existing road conditions.
A search of the Scottish Roads Works Commissioner website (Map Search) has identified BEAR Scotland 24 hour works on barrier within the scheme extents of A82 South of Inverarnan which are to overlap with the resurfacing works. Considering the locations overlap and both works are undertaken by BEAR Scotland, it is anticipated that the works will be undertaken under one set of TM, negating additional disturbance to travelling public.
BEAR Scotland programme all of their proposed works in line with appropriate guidance and contractual requirements. All schemes are programmed to take into account existing and future planned works, with a view of limiting any cumulative effects relating to TM. As a result of this exercise, where a potential for cumulative impacts is identified, BEAR will reprogramme schemes to avoid / limit any cumulative effects or will utilise existing TM to complete multiple schemes at once. This approach allows BEAR Scotland to effectively manage the potential cumulative effects as a result of TM, resulting in minimal disruption to users of the Scottish trunk road network.
Overall, it is unlikely that the proposed works will have a significant cumulative effect with any other future works in the area.