Vulnerability of the project to risks

Part of the A82 carriageway within the scheme is recorded as having high risk (10% chance each year) of surface water flooding. Works will be programmed to avoid periods of adverse weather or heavy rainfall as far as is reasonably practicable.

Works are restricted to the made ground of the A82 trunk road boundary and TM will be designed in line with existing guidance. TM will consist full road closures with regular amnesties. Where required, alternative NMU provisions/routes will be included in the traffic management setup, to minimise impact of the works on NMUs.

A Traffic Management Plan (TMP), which includes measures to avoid or reduce disruption to road traffic, will be produced in accordance with the Traffic Signs Manual (Department of Transport, 2009). The TMP will ensure that there is no severance of community assets, access routes or residential development.

These measures, along with mitigation measures and standard working practices, will be detailed in the SEMP and adhered to on site. The vulnerability of the project to risks of major accidents and disasters is considered to be low.