Project Details
Description
BEAR Scotland has been commissioned by Transport Scotland to carry out footway refurbishment works adjacent to the A82 northbound (NB) carriageway. Works will comprise the following activities:
- Resurfacing: The footway will be resurfaced across most of the scheme extents.
- Gullies: Existing gullies within the footway kerbs will be replaced or reset as required.
- Gabion baskets: A 25m long section of gabion baskets will be installed along the footway embankment, centred at National Grid Reference (NGR) NN 21726 81849, to provide additional support and underpin the footway.
- Kerbs: Existing kerbs will be replaced along most of the scheme extents.
- Vegetation clearance: There is potential for the removal of one tree at NGR NN 21740 81836 to facilitate installation of gabion baskets.
The works will take place over a length of 1,732m and an area of 0.125ha.
The existing footway condition has deteriorated across the scheme extent. Subsidence is occurring at the location where gabion baskets will be installed. The works are required to alleviate trip hazards caused by subsidence and deterioration issues and restore the footway to a safe condition for the public.
The works are currently programmed for delivery within the 2026/2027 financial year and are expected to commence in late November 2026 for a duration of approximately four weeks. The works will primarily be undertaken during daytime hours (09:00 – 16:00), with some requirement for night-time working (20:00 – 06:00) within the village of Spean Bridge. Changes in the programme may result in a change to the proposed working hours/commencement dates.
Traffic management (TM) will involve lane closures facilitated by 2-way and 3-way temporary traffic lights. Due to the extents of the scheme, TM will be set-up in stages and will move progressively along the A82 carriageway. The footway will be closed during the works with pedestrians marshalled thought the scheme extents. Local access will be accommodated within TM as much as is reasonably practicable.
Location
The scheme is located along the NB carriageway of the A82 trunk road between the village of Spean Bridge and monument of Commando Memorial, in the Highland Council administrative area (Figure 1) between the following NGRs:
- Start: NN 22202 81726; End: NN 20888 82288