Vulnerability of the project to risks

Areas of the A82 carriageway within the scheme extent are recorded as having medium to high risk (10% chance each year) of surface water and small watercourse flooding. Works will be programmed as far as is reasonably practicable to avoid periods of adverse weather or heavy rainfall. There will be no increase to the likelihood of flooding on the A82 within the scheme extents upon completion of the works.

TM will consist of lane closures on the A82 with closures of the A82 NB footway. NMUs will be marshalled through the scheme via TM.

A Traffic Management Plan (TMP), which includes measures to avoid or reduce disruption to road traffic, will be produced in accordance with the Traffic Signs Manual (Department of Transport 2009). The TMP will ensure that there is no severance of community assets, access routes, or residential development.

The works are expected to provide a beneficial outcome for users of the A82 NB footway by underpinning and stabilising the footway and improving its condition.

These measures, along with mitigation measures and standard working practices, will be detailed in the SEMP and adhered to on site. The vulnerability of the project to risks of major accidents and disasters is considered to be low.