Assessment cumulative effects
The proposed works are not anticipated to result in significant environmental effects. Due to the nature of the proposed works, no cumulative effects are anticipated with any other developments in the vicinity.
A search of the Highland Council Planning Portal identified no approved planning applications within 300m of the scheme, in the last 6 months.
A search of the Scottish Roads Works Commissioner website (Map Search) has identified that no other roadworks are noted as being planned on this area of the A82 and A828 trunk roads at the same time as this scheme. Due to the timing and nature of the proposed works, no cumulative effects are anticipated with any other developments in the vicinity.
BEAR Scotland programme all of their proposed works in line with appropriate guidance and contractual requirements. All schemes are programmed to take into account existing and future planned works, with a view of limiting any cumulative effects relating to TM. This approach allows BEAR Scotland to effectively manage the potential cumulative effects as a result of TM, resulting in minimal disruption to users of the Scottish trunk road network.
Overall, it is unlikely that the proposed works will have a significant cumulative effect with any other future works in the area.