Slide 1 - Meeting details

A83 Taskforce

Part 2: Wider A83

Slide 2 - Works Undertaken Since Previous Meeting

A83 Taskforce

Works Undertaken Since Previous Meeting

  • Total A83 investment between October and January = £3.8M
  • The programme for the next quarter is currently being finalised

Surfacing Improvements

  • A83 Stronachullin
  • A83 North of Tayinloan
  • A83 North of Stonefield
  • A83 Low Ballevain
  • A83 Drum
  • A83 Glaschoine
  • A83 Ardgenavan
  • A83 Kennacraig Ferry

Bridges/Structures/Seawalls

  • A83 Douglas Water expansion joint replacement

Slide 3 - Works Undertaken Since Previous Meeting

Slide 3 - Works Undertaken Since Previous Meeting

Works Undertaken Since Previous Meeting

Road Signs and Road Markings

  • A83 Route Priority road markings and stud refresh
  • A83 Minard to Lochgilphead bend treatments

Drainage/Landscaping/Slope Improvements/Barriers

  • A83 Easn Dubh Embankment
  • A83 Thornwood Cottage, Furnace Drainage Improvements
  • A83 Tarbert to Campbeltown Ditching Various
  • A83 Tree Maintenance
  • A83 Clachan Safety Barriers

Slide 4 - A83 Lochgilhead to Tarbert Landscape Maintenance

Slide 4 - A83 Lochgilhead to Tarbert Landscape Maintenance, as described in the following text

A83 Taskforce

A83 Lochgilhead to Tarbert Landscape Maintenance

Slide contains a photograph of landscape maintenance along a road with the landscape having been cut back from the edge of the road.

Slide 5 - A83 Ardgenavan Road Resurfacing

A83 Ardgenavan Road Resurfacing, as described in the following text

A83 Taskforce

A83 Ardgenavan Road Resurfacing

Slide contains two photographs of the resurfaced road along the A83 near Ardgenavan. The first photograph shows workers laying the new road with plant. The second photograph shows the new resurfaced road.

Slide 6 - A83 Glaschoine Road Resurfacing

Slide 6 - A83 Glaschoine Road Resurfacing, as described in the following text

A83 Taskforce

A83 Glaschoine Road Resurfacing

Slide contains a photograph of a new resurfaced road along the A83 near Glaschoine.

Slide 7 - Works Planned in Next Quarter (Programmes under development)

Slide 7 - Works Planned in Next Quarter (Programmes under development), as described in the following text

A83 Taskforce

Works Planned in Next Quarter (Programmes under development)

Surfacing Improvements

  • A83 North of Bellochantuy
  • A83 Leamnamiuc
  • A83 Arrochar to River Loin
  • A83 Tangy

Road Signs and Road Markings

  • A83 Route Priority road markings and stud refresh

Bridge Works

  • A83 Tangy corrugated pipe lining
  • A83 Tigh Cladich South wall repairs

Slide 8 - Works Planned in Next Quarter

Slide 8 - Works Planned in Next Quarter, as described in the following text

A83 Taskforce

Works Planned in Next Quarter

Drainage/Landscaping/Slope Improvements

  • A83 Tree Maintenance
  • A83 North Lodge Drainage
  • A83 Tarbert to Campbeltown Ditching

Road Safety/Active Travel

  • A83 Campbeltown Pedestrian crossings
  • A83 Approach to Kilmory Roundabout
  • A83 Minard to Lochgilphead bend treatments (continues)

Slide 9 - Thank You & Any Questions

Slide 9 - Thank You & Any Questions, as described in the following text

A83 Taskforce

Thank You & Any Questions