Project Details
Description
BEAR Scotland has been commissioned by Transport Scotland to undertake resurfacing works on a stretch of the A830 trunk road, approximately 5km west from the village of Glenfinnan. The scheme covers an approximate area of 0.201ha and is 300m in length. Carriageway resurfacing will involve the milling out and replacement of bituminous material and the replacement of road markings. Grip cutting and clearing of ditches is also included in the scheme. The package of works will include:
- Set up traffic management (TM) and mark out site.
- Mill out old surface course.
- Lay new surface course.
- Roll surface and allow it to go off.
- Install road markings and studs.
- Grip cutting and ditch clearing.
- Remove TM and open road.
The works are currently programmed to be completed within the 2026/2027 financial year, scheduled to take place from 16/11/2026, over a duration of 10 days, utilising a daytime working pattern (07:00 – 19:00). Changes in the programme may result in a change to the proposed working hours/commencement dates. The works are necessary to rectify surface deterioration.
Traffic Management (TM) will include two-way temporary traffic lights with 10mph convoy (07:00 – 19:00). The TM strategy will be in line with recommendations and guidance in The Traffic Signs Manual Chapter 8 (Traffic signs manual chapter 8). Site access and plant storage will be located within the TM. If the programme changes, this may result in amendment to the exact TM requirements.
Location
The scheme is located on a stretch of the A830 trunk road approximately 5km west from the village of Glenfinnan within Highland Council (Figure 1). The scheme has the following National Grid Reference (NGR):
- Scheme start point NGR: NM 84194 81646
- Scheme end point NGR: NM 83966 81799