Statement of case in support of a Determination that a statutory EIA is not required
This is a relevant project in terms of section 55A(16) of the Roads (Scotland) Act 1984 as it is a project for the improvement of a road and the completed works (together with any area occupied by apparatus, equipment, machinery, materials, plant, spoil heaps, or other such facilities or stores required during the period of construction) exceed 1 hectare in area.
The project has been subject to screening using the Annex III criteria to determine whether a formal Environmental Impact Assessment is required under the Roads (Scotland) Act 1984 (as amended by The Roads (Scotland) Act 1984 (Environmental Impact Assessment) Regulations 2017). Screening using Annex III criteria, reference to consultations undertaken and review of available information has not identified the need for a statutory EIA.
The project will not have significant effects on the environment by virtue of factors such as:
Characteristics of the scheme:
- Works are restricted to like-for-like replacement of worn road surface, with all works restricted to made ground on the A835 carriageway surface.
- Construction activities are restricted to an area of 1.32ha along a 1,690m stretch of the A835.
- The works will be temporary, transient, localised, and completed during night-time hours on a rolling programme.
- Works are not expected to result in significant disturbance to protected species that may be present in the wider area.
- The risk of major accidents or disasters is considered to be low.
- Removing the carriageway defects will provide this part of the A835 carriageway with another life cycle, and significantly improve the ride quality, which will result in safer conditions for road users.
Location of the scheme:
- The scheme will be located within the existing A835 road boundary and as such, no land take will be required.
- The scheme is not located within a NP/NSAs or any other sensitive sites (such as any sites designated for biodiversity conservation). Works entail like-for-like resurfacing and no change to the visual landscape is expected.
Characteristics of potential impacts of the scheme:
- Any potential impacts of the works are expected to be temporary, short-term, non-significant, and limited to the construction phase.
- Measures will be in place to ensure appropriate removal and disposal of waste.
- No impacts on the environment are expected during the operational phase as a result of works. The works are expected to result in positive impacts on road users, ecological and human receptors during the operational phase.
- As the works will be limited to the like-for-like replacement there is no change to the vulnerability of the road to the risk or severity of major accidents/disasters that would impact on the environment.
- Mitigation measures detailed above (and in the SEMP) will be put in place with the objective to prevent and, if required, subsequently control any potential impacts on sensitive receptors.