Assessment of cumulative effects

A search of the Highland Council Planning Portal did not identify any approved planning applications within 300m of the scheme extents over the last two years. Therefore, due to the nature of the proposed works, no cumulative effects are anticipated with any other developments in the vicinity.

A search of the Scottish Roads Works Commissioner website (Map Search) identified no roadworks commencing within the same time frame as the proposed works, within 300m of the scheme. Additionally, no other large-scale tree felling or vegetation clearance schemes are planned on the A86 in the current financial year.

Trees to be removed are located along the A86 road corridor and within falling distance of the A86. The majority are of a small size, unstable, diseased, or otherwise defective. Trees to be removed across the scheme consist of trees that are not suited for tree growth, such as where they block visibility splays, encroach on signage, overhang the carriageway, etc. Furthermore, they will be removed from areas where it has been assessed that their growth will be detrimental to existing woodland assets. Tree removal will be limited to the minimum number required to ensure the safety of road users and will be focused on the trunk road corridor, which is likely to provide sub-optimal habitat for adjacent trees due to the proximity of the trunk road and exposure to salt and other runoff from the road. The total quantity of trees to be removed from the A86 trunk road has been assessed as negligible in the context of both the local and wider landscape, with woodland remaining a dominant feature along the trunk road corridor for much of the extent between Laggan and Moy. In addition, the cumulative number of trees/vegetation to be removed will be considered and recorded for future compensatory planting in appropriate locations. Suitable locations for replanting are highly limited within the trunk road boundary in proximity to these schemes; therefore, BEAR Scotland will seek to identify alternative suitable locations for compensatory planting, in discussion and consultation with Transport Scotland. The above scheme is due to begin in on 02/11/2026 for a duration of 10 weeks. BEAR Scotland programme all of its proposed works in line with appropriate guidance and contractual requirements. All schemes are programmed to take into account existing and future planned works, with a view of limiting any cumulative effects relating to traffic management. As a result of this exercise, where a potential for cumulative impacts is identified, BEAR will reprogramme schemes to avoid / limit any cumulative effects or will utilise existing traffic management to complete multiple schemes at once. This approach allows BEAR Scotland to effectively manage the potential cumulative effects as a result of traffic management, resulting in minimal disruption to users of the Scottish trunk road network.

Overall, it is unlikely that the proposed works will have a significant cumulative effect with any other future works in the area.