Description of main environmental impacts and proposed mitigation
Air quality
Construction activities associated with the proposed works have the potential to temporarily cause local air quality impacts. The main sources are likely to be dust and particulate matter generated by resurfacing operations, excavations and vegetation clearance, as well as exhaust emissions from ancillary plant and vehicles. As a result, there is potential for dust, particulate matter, and exhaust emissions to be emitted to the atmosphere. However, taking into account the nature and scale of the works and the following mitigation measures, the risk of significant impacts to air are considered to be low.
- A water-assisted dust sweeper will sweep the carriageway after dust-generating activities and waste will be contained and removed from site as soon as is practicable.
- Materials that have the potential to produce dust will be removed from site as soon as possible, and vehicles that remove cold-milled material from site will have sheeted covers.
- Ancillary plant, vehicles and machinery will have been regularly maintained, paying attention to the integrity of exhaust systems.
- Ancillary plant, vehicles and machinery will be switched off when stationary to prevent exhaust emissions (e.g., there will be no idling vehicles).
- Cutting, grinding and sawing equipment (if required) will be fitted or used in conjunction with suitable dust suppression techniques e.g., local exhaust ventilation system that fits directly onto tools.
- Regular monitoring (e.g., by engineer or Clerk of Works) will take place when activities generating air pollution are occurring. In the unlikely event that unacceptable levels of air pollution are emanating from the site, the operation will, where practicable, be modified and re-checked to verify that the corrective action has been effective. Actions to be considered include: (a) minimizing cutting and grinding on-site, (b) reducing the operating hours, (c) changing the method of working, etc.
- All delivery vehicles carrying material with dust potential will be covered when travelling to or leaving site, preventing the spread of dust beyond the work area.
- Material stockpiles will be reduced as far as is reasonably practicable by using a ‘just in time’ delivery system. All material will also be stored on made ground.
- Any stockpiled material on site will be monitored daily to ensure no risks of dust emissions exists.
- Materials will be removed from site as soon as is practicable.
- Good housekeeping will be employed throughout the work.
With the above mitigation measures in place, it is anticipated that any air quality effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Landscape and visual effects
There will be a temporary, short-term impact on the landscape character and visual amenity of the site as a result of the presence of construction plant, vehicles and TM. However, people, ancillary plant, vehicles, machinery and materials will be restricted to areas of made/engineered ground on the A9, and construction works are programmed to be of a short duration (five nights).
Minor permanent change will occur to the local landscape due to resurfacing, vegetation clearance and the replacement of bollards, signs and fence posts. However, all change is within the A9 trunk road boundary and replacement of bollards, signs and fence posts will all be like-for-like. Additionally, vegetation clearance will be minor in nature and restricted to three sectioned off areas on the grass verge separating the layby from the main carriageway.
The visual impact of the works will be minimal and, on completion of the works, a renewed layby surface, cleared ditches, replaced signs, bollards and fence posts and minor vegetation clearance will be the only discernible change. The CNP Authority will be notified of the proposed works and, if required, additional mitigation measures will be included in the SEMP and adhered to on site.
In addition, the following mitigation measures will be put in place during works:
- Vegetation clearance will be limited to only the amount necessary to complete the works.
- All replacement of signs, bollards and fence posts will be like-for-like and in keeping with the character of the existing street furniture.
- Throughout all stages of the works, the site will be kept clean and tidy, with materials, equipment, plant and wastes appropriately stored, reducing the landscape and visual effects as much as possible.
- Works will avoid encroaching on land and areas where work is not required or not permitted. This includes general works, storage of equipment/containers and parking.
- Where applicable, upon completion of the works, any damage to the local landscape will be reinstated as much as is practicable.
- The site will be left clean and tidy following construction.
With the above mitigation measures in place, it is anticipated that any landscape and visual effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Biodiversity
The scheme is located wholly within the Drumochter Hills SSSI. The proposed works fall under several ‘operations requiring consent’ and, as such, SSSI consent has been obtained from NatureScot. All conditions of the SSSI consent will be detailed in the SEMP and adhered to on site. The scheme is also located in close proximity to the Drumochter Hills SAC, Drumochter Hills SPA and River Spey SAC. Due to the proximity to the designated sites, an HRA was produced following consultation with NatureScot via SSSI consent. The HRA concluded that there would be no Likely Significant Effects (LSE) on the qualifying features of the Drumochter Hills SAC on account of the following:
- No works are required within the boundary of the SAC.
- Vegetation clearance is restricted to three fenced areas within the layby boundary and no qualifying habitat associated with the SAC is present in these areas.
- There is limited hydrological connectivity between the SAC and the proposed works.
- The qualifying habitats are immobile and standard working practices to prevent pollution will be in place.
- NatureScot also advised there would be no LSE on the qualifying features of the SAC due to the restriction of the works to the trunk road boundary.
The HRA also concluded that there would be no LSE on the qualifying features of the Drumochter Hills SPA on account of the following:
- No works will take place within the boundary of the SPA.
- Vegetation clearance associated with the works is restricted to three fenced areas which does not hold supporting habitat for the qualifying bird species
- Standard working practices to prevent pollution will be in place.
- There is no suitable nesting habitat for the qualifying bird species within the works area, and suitable nesting habitat is located 50m from the scheme with intervening landscape features
- Works are highly localised and of short duration, with ample alternative foraging habitat available to qualifying bird species away from the works area
- Qualifying bird species are likely habituated to existing levels of noise and light disturbance associated with the A9 trunk road
- NatureScot also advised that the works would not result in LSE on the qualifying features of the SPA due to the restriction of the works to the A9 trunk road and the timing of works outside breeding bird season (March to August inclusive).
LSE on the qualifying features of the River Spey SAC could not be ruled out due to the known presence of the features in proximity to the works and the risk of pollution impacts and disturbance. However, following Appropriate Assessment, no adverse effects on site integrity (AESI) on the qualifying features of the River Spey SAC with the below mitigation measures in place, along with standard good practice measures to prevent pollution and noise and visual disturbance. NatureScot also advised of this assessment.
Ecological surveys conducted did not identify any protected mammal shelters, resting places or field signs within proximity to the scheme.
The surrounding habitat is suitable for nesting birds, including ground nesting birds; however, the proposed works will be conducted outwith nesting bird season (March to August inclusive). If the proposed works are delayed into nesting bird season, a pre-construction nesting bird check will be conducted.
Ecological surveys also identified the native invasive weed, rosebay willowherb, throughout the scheme extent, including within areas required for vegetation clearance. Mitigation measures to avoid the spread of injurious weeds will be detailed in the SEMP and are summarised below.
In general, activities undertaken on site could potentially have a temporary adverse impact on biodiversity in the area as a result of increased vehicle presence and the increase in noise and artificial lighting during the night. However, works are restricted to the A9 trunk road boundary, the number of construction vehicles and operatives required on site is low and works are of a short duration (five nights). In addition, any species in the area are likely to be accustomed to noise and visual disturbance pertaining to vehicle movements on the A9. Therefore, the potential for significant species disturbance within the area is considered low.
Pollution controls and good practice measures to reduce impacts of works on the local environment will be detailed in the SEMP and adhered to on site.
The following mitigation measures to avoid AESI on features associated with the River Spey SAC will be in place throughout works:
- Artificial lighting required for works will be directed on the immediate works area and away from watercourses as far as is safe and reasonably practicable.
- Plant, machinery and equipment will be fitted with effective silencers where available. Where fitted and where permitted under Health and Safety requirements, white noise reversing alarms will be utilised during construction.
- Where possible, inherently quiet plan will be selected for construction works. Where appropriate, pumps and generators will be sound-reduced models with fitted, lined and sealed acoustic covers.
- All plant will be operated in such a way that minimises noise emissions and be switched off when not in use.
The following mitigation measures to avoid AESI on mammals associated with the River Spey SAC will be in place throughout works:
- Toolbox Talk will be included in the SEMP and provided to all site staff prior to works commencing.
- Artificial lighting used during night works will be used for as short a duration as possible and directed on the immediate area of works. Artificial lighting will avoid being directed onto nearby watercourses or habitats as far as is safe and reasonably practicable.
- The working area and any machinery stored on site will be checked at the start of each shift. A soft start will be implemented to ensure a gradual increase in noise and activity.
- Any excavations, entrances to pipes/drains, or areas where an animal could be trapped (e.g. storage containers) will be covered over when not in use, at the end of each shift, and following completion of the works.
- If excavations (e.g., trenches) cannot be covered, escape ramps will be installed.
- If fencing is used at any point during works, a gap of 200mm from ground level will be provided, allowing free passage and preventing entrapment.
- If animals are observed in the area of works prior to works starting, no works will commence until they have moved at least 50m away.
- If animals are observed during works, all works will cease until they have moved at least 50m away.
- Works will be restricted to the A9 trunk road boundary at Layby 82 only, including the storage of plant, machinery and equipment.
- Plant, machinery and equipment fitted with effective silencers where available will be utilised for the works. Where fitted, and where permitted under Health and Safety requirements, white noise reversing alarms will be utilised during construction.
- Where possible, inherently quiet plant will be selected for construction works. Where appropriate, pumps and generators will be sound-reduced models with fitted, lined, and sealed acoustic covers.
- All plant will be operated in such a way that minimises noise emissions and be switched off when not in use.
- All ancillary plant such as generators will be positioned so as to cause minimum noise disturbance. Where deemed necessary, acoustic screens will be utilised.
The following general mitigation measures will be in place to minimise impacts on other biodiversity features in the area:
- All conditions of the SSSI consent issued by NatureScot will be detailed in the SEMP and adhered to on site.
- No in-water works in a natural watercourse or discharge into the water environment will be permitted.
- Works will be strictly limited to areas required for access and to carry out the works. Unnecessary encroachment onto terrestrial or aquatic areas will not be tolerated.
- All construction operatives will be briefed through toolbox talks prior to works commencing, which will be included in the SEMP. The toolbox talks will provide information on the legislation, general ecology, and best practice measures for relevant protected species.
- Artificial lighting used during nighttime works will be used for as short a duration as possible and directed on the immediate area of works. Artificial lighting will avoid being directed onto nearby woodland habitat and watercourses as far as is safe and reasonably practicable.
- Site personnel will remain vigilant for the presence of any protected species throughout the works period. Should a protected species be noted during construction, works will temporarily halt until the species has sufficiently moved on. Any sightings of protected species will be reported to the BEAR Scotland Environmental Team. If required, NatureScot will be contacted for advice.
- Measures to mitigate the spread of invasive weeds within the works area will be detailed in the SEMP and adhered to on site.
- The Working with INNS and Injurious Plants toolbox talk will be issued to operatives prior to the commencement of works.
- Access and works within 7m of INNS or injurious weed growths will be avoided where possible. Where this is not possible, access and works will be kept to the minimum required to facilitate the works.
- Strict hygiene measures will be adhered to at all times to limit the spread of INNS and/or injurious weeds.
- Storage of plant, materials and equipment will be restricted to the made ground of the A9 carriageway, away from areas of rosebay willowherb.
- Any rosebay willowherb which is required to be cleared as part of the works will be left on site, more than 10m from any watercourses or drainage ditches.
- A ‘soft start’ will be implemented on site each day. This will involve switching on vehicles and checking under/around vehicles and the immediate work area for mammals prior to works commencing to ensure none are present and that there is a gradual increase in noise.
- Any excavations, exposed pipes/drains, or areas where an animal could become trapped (e.g. storage containers) will be covered over when not in use, at the end of each shift, and following completion of the works to avoid animals falling in and becoming trapped.
- If fencing is utilised at any point during the works, a gap of 200mm from ground level will be provided, allowing free passage for mammals and preventing entrapment.
- If an active bird nest is found in vicinity of the works, all works within 30m of the nest will stop until the BEAR Scotland Environment Team can provide advice.
- If works are delayed into nesting bird season (March to August inclusive), a pre-works nesting bird check will be conducted prior to works commencing and prior to any vegetation clearance.
- If nesting birds are found during pre-works checks or during works, consultation with NatureScot will be carried out and a licence will be sought if advised by NatureScot. If required, all conditions of any licences will be adhered to.
With the above mitigation measures in place, it is anticipated that any biodiversity effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Geology and soils
The scheme is located wholly within the Drumochter Hills SSSI which is designated for Fluvial Geomorphology of Scotland, in addition to biodiversity features detailed above. SSSI consent has been sought from NatureScot and all conditions of the SSSI consent will be detailed in the SEMP and adhered to on site.
Excavation is required as part of the resurfacing works, ditch clearing and for the replacement of damaged fence posts, signs and bollards. However, this is restricted to the A9 trunk road boundary, and all verge excavations will be conducted by machinery from the hard standing of the layby or by operatives utilising hand tools. Therefore, some localised soil exposure/disturbance may occur during excavations and during ditch clear out; however, this will be minor in nature and will involve excavation in areas for replacement of street furniture only. It is not anticipated that this will result in any change to local soil make-up and standard working practices will limit any potential pollution of soils. To mitigate any adverse impacts on geology and soils, the following measures will be in place:
- Excavation will be restricted to the trunk road boundary and to the minimum amount necessary to complete the works.
- Verge excavations will be conducted utilising machinery from the hard standing of the layby only (i.e. no heavy machinery will be used on the verges).
- If excavated soils are to be re-used on site, then it will be wetted (if necessary) during periods of dry weather to prevent drying out.
- Upon completion of the works, any damage to the local landscape will be reinstated as much as is practicable.
- Mitigation measures to prevent contamination of soils through loss of containment will be strictly adhered to.
- The parking of machinery / vehicles and storage of equipment on verges will be minimised as far as is reasonably practicable.
- All relevant soil management toolbox talks will be included in the SEMP and sediment control measures will be in place where required.
- Additional pollution prevent measures as outlined in the ‘Road drainage and the water environment’ section will be adhered to during construction.
With the above mitigation measures in place, it is anticipated that any geology and soil effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Material assets and waste
There is potential for impacts during works as a result of resource depletion through use and transportation of new materials. However, materials will be sourced locally where possible and the following mitigation measures will be put in place:
- Materials will be sourced from recycled origins as far as reasonably practicable within design specifications.
- Care will be taken to order the correct quantity of required materials to prevent disposal of unused materials.
- Where possible, minimal packaging will be requested on required deliveries to reduce unnecessary waste and production of packaging materials.
There is potential for impacts during works are a result of the improper storage or disposal of waste. The following mitigation measures will be put in place:
- The waste hierarchy (Reduce, Reuse, Recycle and Dispose) will be employed throughout the construction works.
- All waste stored on site will be adequately protected against the elements.
- The subcontractor will adhere to waste management legislation and ensure they comply with their Duty of Care.
- Containment measures will be in place to prevent debris or pollutants from entering the surrounding environment.
- All road planings will be treated in line with Low Risk Waste Activity (LRWA) 3 and be recycled in line with SEPA’s WAS-G-DEF-05 Guidance for End-of-Waste for Recycled Aggregates.
- It is anticipated that soil waste from excavations will be redistributed on site. Cleared vegetation, old fence posts, old signs and old bollards will be removed from site and disposed of appropriately.
- Management of waste from ditching works is covered by LRWA 9: ‘Depositing non-hazardous waste dredging materials from inland waters, or sustainable urban drainage systems, on land near to where the dredging takes place’. The following LRWA9 conditions will be adhered to for any ditching works, where waste is not being removed from site:
- Waste will be produced by a dredging activity that is authorised by General Binding Rule (GBR), Registration or Permit.
- Waste will be deposited at the same site where it was produced.
- Waste will not be left on the banks such that its placement heightens the banks of any river, burn, ditch or loch.
- Large items, litter, or fly-tipped waste will be removed from the dredged materials and transported to a suitably authorised site by a registered transporter of waste.
- All wastes and unused materials will be removed from site in a safe and legal manner by a licensed waste carrier upon completion of the works. The appointed waste carrier will have a valid SEPA waste carrier registration, a copy of which will be provided to and retained by BEAR Scotland as early as possible.
- All appropriate waste documentation will be present on site and be available for inspection. A copy of the Duty of Care paperwork will be provided and filed appropriately in accordance with the Code of Practice (as made under Section 34 of Environmental Protection Act 1990 as amended).
- Re-use and recycling of waste will be encouraged, and the subcontractor will be required to fully outline their plans and provide documentary evidence for waste arising from the works (e.g., waste carrier’s licence, transfer notes, and waste exemption certificates).
- Staff will be informed that littering will not be tolerated. Staff will be encouraged to collect any litter seen on site.
- Where applicable, all temporary signage will be removed from site on completion of the works.
With the above mitigation measures in place, it is anticipated that any material assets and waste effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Noise and vibration
Construction activities associated with the proposed scheme have the potential to cause adverse noise and vibration impacts through the use of equipment and construction vehicles for the proposed activities. However, the works are not located within a CNMA, and there are no residential or commercial properties within proximity to the scheme, with the closest property at a distance of 1km. The works will employ a night-time pattern with the noisiest works (e.g. planing) completed by 23:00 where practicable. Therefore, works with the potential to induce worst-case scenario noise and vibration will be intermittent, temporary and short-lived.
The road surface of the layby is in poor condition with a series of defects. Replacing the life-expired surface course affords benefits of a reduction in mid-to-high frequency traffic noise and a reduction in ground vibrations. As a result, upon completion of the work, noise associated with the movement of vehicles within the layby should decrease post construction.
The following mitigation measures will be put in place:
- The Best Practicable Means, as defined in Section 72 of the Control of Pollution Act 1974, will be employed at all times to reduce noise to a minimum. On-site construction tasks will be programmed to be as efficient as possible, with a view to limiting noise disruption to local sensitive receptors.
- The Environmental Health Officer (EHO) for the Highland Council will be notified of works.
- The noisiest works (e.g. planing) will be programmed to be completed by 23.00 where possible.
- Where possible, inherently quiet plant will be selected for construction works.
- All site personnel will be fully briefed in advance of works regarding the need to minimise noise during works and of the site-specific sensitivities.
- Drop heights from vehicles and machinery will be kept to a minimum to minimise noise when unloading.
- All plant, machinery and vehicles will be switched off when not in use.
- All plant will be operated in such a way that minimises noise emissions and will have been maintained regularly to the appropriate standards.
- Where fitted, and where permitted under Health and Safety requirements, white noise reversing alarms will be utilised during construction.
- Where ancillary plant such as generators are required, they will be positioned so as to cause minimum noise disturbance. Where deemed necessary, acoustic screens will be utilised.
With the above mitigation measures in place, it is anticipated that any noise and vibration effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Population and human health
During construction, activities undertaken on site have the potential to have temporary adverse impacts on vehicle travellers and non-motorised users (NMUs) as a result of construction presence and associated noise and delays due to TM measures and the closure of the layby.
However, no residential or commercial properties are located within 300m of the scheme. In addition, no significant congestion issues are noted during the proposed construction hours; however, increased journey times may occur due to TM measures. However, these are considered insignificant considering the timing of works during off-peak tourist season, the restriction of the main works to the layby and the night-time working hours. Road users will be informed of the works through media release which will provide details of construction dates and times.
The walking route and core path located adjacent to the A9 NB carriageway will not be directly impacted by the works and will remain open throughout.
With the following mitigation measures in place, the risk of significant impacts on population and human health is considered to be low:
- Notification will be issued to local residents and local public transport operators prior to the commencement of works, advising of any proposed works and expected restrictions.
- Local access will be granted where required.
- Construction lighting will consider the need to avoid illuminating the surrounding environment to avoid a nuisance at night; and non-essential lighting will be switched off when not required.
- Appropriate provisions / measures will be implemented within the works area to allow the safe passage of NMUs of all abilities through the site (if required).
- Journey planning information will be available for drivers online at the trafficscotland.org website. Journey planning information will also be available for drivers online through BEAR’s social media platforms.
- Layby closures will be signposted in advance.
Taking into account the nature and scale of the works and the good site practice measures to be adopted during the works (outlined in the SEMP), it is anticipated that any population and human health effects associated with the works are unlikely to be significant. This receptor is not considered further in this RoD.
Road drainage and the water environment
During the works, there is potential for temporary impacts on the water environment due to the operation of plant within proximity to watercourses and/or drainage systems. Potential changes in water quality from pollution events (either by accidental sediments, particulate matter, chemicals, fuels or by mobilisation of these in surface water caused by rain/flooding) during works have the potential to have a direct or indirect effect on the surrounding water bodies.
No in-water works within natural watercourses are required and there is no abstraction or transfers of water from, or discharges to, a water body. As such, the potential for a direct pollution incident within a water body is unlikely. Experience gained from BEAR maintenance schemes elsewhere on the network has shown that, where good working practice is adopted (e.g. adherence to SEPA good practice guidance, appropriate containment measures, etc.), water quality is protected.
The following mitigation measures will be put in place to reduce the risk of pollution incidents as a result of the works:
- No in-water works in a natural watercourse or discharges into any watercourses or drainage systems are permitted.
- Standard working practices to comply with the Environmental Authorisations (Scotland) Regulations (EASR) 2018 for works in or near water will be detailed in the SEMP and adhered to on site.
- Appropriate containment measures will be in place to prevent any loss of construction materials into the water environment.
- Appropriate measures will be implemented during resurfacing operations to limit the potential for wastes (i.e. road planings) and materials (i.e. new asphalt) to enter any gullies present on site. On completion of resurfacing operations, any gullies present on site will be visually checked to ensure that they have not become blocked as a result of the works.
- A toolbox talk on silt and sediment containment will be included in the SEMP and delivered to all site staff as part of the site induction.
- Concrete batching, where required, will be undertaken on an impermeable surface and 10m away from watercourses/ drainage systems.
- Any concrete wash-out will be contained and removed off-site for appropriate treatment/ disposal. Disposal of wash water into waterbodies or road drainage will not be permitted.
- An incident response (contingency) plan will be put in place to reduce the risk from pollution incidents or accidental spillages. All necessary containment equipment, including suitable spill kits (for oil and chemicals) will be available on site, quickly accessible if needed, and staff trained in their use.
- All spills will be logged and reported. In the event of any spills into the water environment, all works will stop and the incident will be reported to the project manager and the BEAR Scotland Environmental Team. SEPA will be informed of any such incident as soon as possible using the SEPA Pollution Hotline.
- All plant and equipment will be regularly inspected for any signs of damage and leaks. A checklist will be present to make sure that the checks have been carried out.
- Storage of hazardous material, oil and fuel containers will be distanced more than 10m away from any watercourses.
- If required, a designated refuelling area will be identified. Fuel bowsers will be stored on an impermeable area and be fully bunded. This will be distanced more than 10m from any watercourses.
- During refuelling of smaller mobile plant, a funnel will be used, and drip trays will be in place. Care will be taken to reduce the chance of spillages. Spill kits will be quickly accessible to capture any spills should they occur. The ground / stone around the site of a spill will be removed, double bagged and taken off site as special waste.
- Generators and static plant may have the potential to leak fuel and / or other hydrocarbons and will have bunding with a capacity of 110%. If these are not bunded then drip trays will also be supplied beneath the equipment with a capacity of 110%.
- All storage of hazardous materials utilised on site is required to undergo assessment under the Control of Substances Hazardous to Health (COSHH) Regulations 2002. These assessment(s) will contain a section on environment which highlights any precautions and mitigation requirements.
- Felled vegetation material will be disposed of appropriately in line with the NW NMC (Schedule 5, Appendix 0/1, 3010SR Maintenance of Established Trees and Shrubs).
- Any vegetation cuttings will not be disposed of in any watercourses or road drainage systems. Cuttings will be removed from site and disposed of appropriately. Any cuttings left on site will be left at least 10m away from any watercourses or drainage systems.
With the above mitigation measures in place, it is anticipated that any road drainage and the water environment effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.
Climate
Construction activities associated with the proposed scheme works have the potential to cause local air quality impacts as a result of the emission of greenhouse gases through the use of vehicles and machinery, material use and production, and transportation of materials to and from site. However, considering the nature, short-term duration, size and scale of the works, and the mitigation measures detailed below, the risk of significant impacts to climate are considered to be low:
- BEAR Scotland will adhere to its Carbon Management Policy.
- If appropriate, warm mix asphalt will be used.
- Local contractors and suppliers will be used as far as practicable to reduce fuel use and greenhouse gas emitted as part of the works.
- Where possible, materials will be sourced locally to reduce greenhouse gas emissions associated with materials movement, and waste will be removed to local waste management facilities.
With the above mitigation measures in place, it is anticipated that any climate effects associated with the proposed works are unlikely to be significant. This receptor is not considered further in this RoD.