Statement of case in support of a Determination that a statutory EIA is not required
This is a relevant project in terms of section 55A(16) of the Roads (Scotland) Act 1984 as it is a project for the improvement of a road and the completed works (together with any area occupied by apparatus, equipment, machinery, materials, plant, spoil heaps, or other such facilities or stores required during the period of construction) is situated within Cairngorms National Park and Drumochter Hills Site of Special Scientific Interest which are sensitive areas within the meaning of regulation 2(1) of the Environmental Impact Assessment (Scotland) Regulations 1999.
The project has been subject to screening using the Annex III criteria to determine whether a formal Environmental Impact Assessment is required under the Roads (Scotland) Act 1984 (as amended by The Roads (Scotland) Act 1984 (Environmental Impact Assessment) Regulations 2017). Screening using Annex III criteria, reference to consultations undertaken and review of available information has not identified the need for a statutory EIA.
The project will not have significant effects on the environment by virtue of factors such as:
Characteristics of the scheme
- All conditions of the SSSI consent will be adhered to on site and no works will take place until the SSSI consent is in place.
- Works are restricted to like-for-like replacement of worn layby road surface and worn street furniture, and routine ditch clearance; with all works restricted to the A9 trunk road boundary.
- Construction activities are restricted to a length of 300m and 0.249ha.
- Works will be temporary, localised and completed during nighttime hours with the aim being to complete the noisiest works by 23.00.
- Works are not expected to result in significant disturbance to nearby receptors or protected species that may be present in the wider area.
- A pre-construction nesting bird check will be conducted if works are delayed into nesting bird season.
- Measures to mitigate the spread of invasive weeds located within the works area will be detailed in the SEMP.
- The risk of major accidents or disasters is considered to be low.
- Ecological surveys did not identify any protected mammal shelters or resting places within 200m of the proposed works.
- Any potential impacts of the works are expected to be temporary, non-significant, and limited to the construction phase.
- By removing the carriageway defects this will provide this A9 layby with another life cycle, and significantly improve the ride quality which will result in safer conditions for road users.
- No impacts on the environment are expected during the operational phase as a result of the works. The works are expected to result in positive impacts on road users during the operational phase.
- Measures will be in place to ensure appropriate removal and disposal of waste.
- Vegetation clearance will be limited to the minimum amount necessary to facilitate the works.
Location of the scheme
- The scheme is located within the existing A9 trunk road boundary and, as such, no land take is required.
- The scheme lies wholly within CNP and the CNP Authority will be consulted prior to works commencing. Any mitigation measures outlined by CNP Authority will be detailed in the SEMP and adhered to on site.
- The scheme is located wholly within the Drumochter Hills SSSI and SSSI consent has been obtained from NatureScot.
- The scheme has ecological connectivity with multiple European sites and all mitigation measures detailed in the Appropriate Assessment will be detailed in the SEMP and adhered to on site.
- There are no features of cultural heritage importance within 300m of the scheme.
- There is no requirement for a site compound, with materials and plant stored within TM.
- Local access will be granted as much as reasonably practicable.
Characteristics of potential impacts of the scheme
- Any potential impacts of the works are expected to be temporary, short-term, non-significant and limited to the construction phase.
- Measures will be in place to ensure appropriate removal and disposal of waste.
- Measures to mitigate the introduction and/or spread of INNS and injurious weeds will be detailed in the SEMP.
- Any mitigation measures advised by the CNP Authority and NatureScot will be adhered to on site.
- No impacts on the environment are expected during the operational phase as a result of the works. The works are expected to result in positive impacts on road users, ecological and human receptors during the operational phase.
- Residual visual impacts will be localised to the existing A9 layby and are not considered to be significant.
- As the works are restricted to like-for-like replacement routine maintenance of the trunk road assets, there is no change to the vulnerability of the road or the risk or severity of major accidents/ disasters.
- Works are programmed to be of short duration and undertaken during night-time working hours.
- The SEMP will include plans to address environmental incidents.
- No in-combination effects have been identified.