Assessments of the environmental effects
As detailed in the Description of Main Environmental Impacts and Proposed Mitigation section within this Record of Determination, there are no significant effects anticipated on any environmental receptors as a result of the proposed works.
A Statement of Appropriate Assessment has been conducted due to the scheme’s location within the Dornoch and Loch Fleet SPA and Ramsar site and connectivity to the Mound Alderwoods SAC. The assessment concluded that the works were directly connected to the management of the Mound Alderwoods SAC and that the works would not result in LSE on the Dornoch and Loch Fleet SPA and Ramsar site. Loch Fleet SSSI and Mound Alderwoods SSSI were included as part of the assessment.
Consultation with NatureScot was conducted in March 2026 and approved the refurbishment of the remaining four arches (3-6) during works in 2026, as long as two remain functional at all times throughout works. NatureScot also authorised some flexibility with the in-water working time restraints, and works may be extended into the first part of October; however, only if required to facilitate the completion of the works. In-water works should be completed by the end of September as much as possible.
A Marine Licence and Listed Building Consent are in place for refurbishment works and remain valid. SSSI consent will be sought from NatureScot prior to the commencement of works, for works within Loch Fleet SSSI.