Description of main environmental impacts and proposed mitigation
Air quality
Impacts
- On site construction activities carry the potential to produce airborne particulate matter, dust and generate emissions that may have a temporary impact on local air quality levels and act as a nuisance to nearby residents.
- TM being implemented during the scheme may result in an increase in associated vehicle emissions through idling vehicles and increased congestion, particularly on diversion routes.
- The impacts identified will be temporary for the duration of the works only and therefore no permanent change is predicted on air quality.
- Post construction there will be no change to the traffic volume, speed or road alignment as works are like-for-like.
Mitigation
- Best practice and measures as outlined in the ‘Guidance on the assessment of dust from demolition and construction (January 2024)’ published by the Institute of Air Quality Management (IAQM), which includes the following mitigation relevant to this scheme will be followed:
- The site layout will be planned (including plant, vehicles and Non-Road Mobile Machinery (NRMM)) so that machinery and dust causing activities are located away from receptors, as far as reasonably practicable;
- Materials that have a potential to produce dust will be removed from site as soon as possible, unless being re-used on site (stockpiles will be covered or fenced to prevent wind whipping);
- Cutting, grinding or sawing equipment will be fitted or used in conjunction with suitable dust suppression techniques such as water sprays or local extraction, e.g. suitable local exhaust ventilation systems;
- Drop heights from conveyors and other loading or handling equipment will be minimised;
- Vehicles carrying wastes and materials will be covered when entering and leaving the work area to prevent escape of materials during transport;
- Equipment will be readily available on site to clean any dry spillages and spillages will be cleaned up as soon as reasonably practicable after the event using wet cleaning methods; and
- When not in use, plant, vehicles and NRMMs will be switched off and there will be no idling vehicles.
- Plant, vehicles and NRMM will be regularly maintained, paying attention to the integrity of exhaust systems to ensure such fuel operated equipment is not generating excessive fumes.
- Green driving techniques will be adopted, and effective route preparation and planning will be undertaken prior to works.
- Where possible, materials will be sourced locally.
- Surfaces will be swept where loose material remains following planing.
No significant effects are predicted on air quality. Therefore, in accordance with DMRB Guidance document LA 105: Air Quality no further assessment is required.
Cultural Heritage
Impacts
- All works will be located within the existing carriageway boundary and are unlikely to impact any areas of land that have not previously been subjected to engineering activity.
Mitigation
- Should the nature of the works change, the Amey ET&S team will be contacted prior to works commencing.
- Should works encounter any materials of archaeological interest (i.e. discoloured soils or material finds such as ceramics or bone) works will cease and the Amey E&S Team will be contacted.
- All plant, machinery and materials will be stored within the carriageway boundary at all times.
- Consultation with Perth and Kinross Council has been undertaken due to the works taking place within a Battlefield. At the time of writing, no response has been received by Perth and Kinross Council.
No significant effects are predicted on Cultural Heritage. Therefore, in accordance with DMRB Guidance document LA 106: Cultural Heritage Assessment, no further assessment is required.
Landscape and visual effects
Impacts
- There will be no operational impacts on visual receptors as works entail the like-for-like resurfacing of the A9 carriageway within the scheme extents.
- Visual receptors identified have the potential to be visually impacted by the scheme during construction due to the presence of TM, plant, vehicles, machinery and operatives.
- The general setting of the area may be impacted during construction due to the presence of TM, plant, vehicles, machinery and operatives.
Mitigation
- Asset installation will be of a minimal visual impact (if any due to the like-for-like nature of the scheme) and will be in keeping with the current setting of the A9 carriageway within the scheme extents.
- Visual screening will be used where possible to minimise visual impacts on surrounding receptors.
- Where possible, vehicles, plant and machinery will be stored out of sight from nearby visual receptors. All site areas will be well-kept and tidy.
- Temporary site lighting will be directional and pointed at the works area only.
The residual effect on landscape and visual effects is deemed to be not significant. Therefore, in accordance with DMRB Guidance document LA 107: Landscape and Visual Effects no further assessment is required.
Biodiversity
Impacts
- During night-time programming, misdirected site lighting and additional noise could cause temporary disturbance to any surrounding nocturnal species.
- Due to the scheme being contained within the pavement boundary, the ancient woodlands identified within 500m of the scheme extents and the Transport Scotland Target Species identified within the carriageway verge will not be impacted by the works.
- A Habitats Regulations Appraisal (HRA) was undertaken and has concluded that there will be no Likely Significant Effects (LSE) on the South Tayside Goose Roosts Special Protection Area (SPA) due to the following:
- There is no requirement for land take within the SPA as a result of the scheme. All works will be confined to the existing carriageway.
- There is no potential for disturbance to designated features given the site is separated from the works by farmland, roads and infrastructure and does not interact with surface water ways that create hydrological connectivity. Any disturbances created through the proposed works will be minor and temporary in nature in comparison to the daily use of the A9.
- The proposed works will not lead to increased habitat or species fragmentation as they are to be undertaken within the carriageway and not within the designated site or its adjacent habitats. Works will be undertaken within habitats adjacent to the highway but still within the highway boundary.
- The proposed works will not lead to any loss of habitat / species.
Mitigation
- Operatives will remain vigilant for the presence of protected species within or near the works. If a protected species is seen in or near the scheme, all works will be stopped until the animal passes by. The protected species will not be approached, and the area will be temporarily isolated until the animal has moved on. Any sightings will be reported to the E&S Team.
- Directional lighting will be used for all construction activities where works are required at night to minimise the impact of temporary lighting on foraging and commuting nocturnal species. This will include avoiding light spill onto watercourses and adjacent woodland parcels.
- Impacts from noise will be kept to a minimum through the use of appropriate mufflers and silencers fitted to machinery. All exhaust silencers will be checked at regular intervals to ensure efficiency.
- No vehicles, machinery or materials will be parked/stored on any soft verges.
- Additional mitigation measures in Noise and Vibration and Road drainage and the water environment will be implemented.
It has been determined that the proposed scheme will not have direct or indirect significant effects to local Biodiversity.
Geology and soils
Impacts
- All works are contained to the engineered layers of the existing carriageway and immediate verges, resulting in limited potential for soil disturbance.
- There will be no impacts upon the surrounding agricultural land.
- There is a potential for pollution of soils from accidental spills or leaks of fuels and oils from construction plant and machinery.
Mitigation
The following mitigation measures will be in place during the works:
- Vehicles and materials will not be stored or parked on grass verges where possible. Where damage occurs, reinstatement will be undertaken.
- Pollution prevention measures outlined in the Road Drainage and the Water Environment section will be followed during construction.
- In the event of a major spill, SEPA will be contacted.
- Excavation of soils will be kept to a minimum and only where necessary, with any excavated soils being re-used on site as far as reasonably practicable (e.g., to backfill removed trial holes etc.).
- Excavated soils will not be stored on site, and will be appropriately contained/covered, and protected from the elements.
- Spill kits will be present on site and all operatives will be fully trained in their use. Any fuels or chemicals required for use will be stored securely with drip trays used appropriately and stored under any chemical or fuel containers.
- After the works have been completed, excavations will be backfilled with soils/materials and reinstated to the original ground level (where relevant/required). The area will be left level and free from debris.
- Dust suppression systems, such as dampening down or use of collection vacuums, will be used when cutting concrete.
With mitigation measures in place, no significant effects are anticipated on geology and soils. Therefore, in line with DMRB Guidance document LA 109: Geology and Soils no further assessment is required.
Material assets and waste
Impacts
- Transportation and recovery of materials/waste will require energy deriving from fossil fuel, a non-renewable source.
- The design life for the TS2010 surfacing proposed is estimated to be 20 years. This will reduce the requirement for maintenance to this section of road over the period.
- There is potential for the works to contribute to resource depletion through use of transportation of primary materials such as aggregates.
- There will be an increase in waste sent to landfill sites if waste materials are not recycled or reused.
Mitigation
- The Contractor will comply with all ‘Duty of Care’ requirements, ensuring that any surplus materials or wastes are stored, transported, treated, used, and disposed of safely without endangering human health or harming the environment. All waste transfer notes and/or waste exemption certificates will also be completed and retained.
- Materials will be derived from recycled, secondary or re-used origin as far as practicable within the design specifications to reduce natural resource depletion and associated emissions.
- All waste will be managed in accordance with the Environmental Authorisations (Scotland) Regulations 2025, under the relevant SEPA waste authorisation for recovery, reuse or disposal. For example, road planings will be prioritised for recovery or reuse, through recycling into new asphalt, in line with the waste hierarchy.
- Waste will be transferred to SEPA-authorised facilities by carriers with valid waste carrier registration. A waste transfer note (WTN) will be completed for removal of waste from site and retained for two years, in line with statutory Duty of Care requirements.
- Use of TS2010 will reduce the usage of imported aggregates and increase the use of a wider range of sustainable aggregate sources thus reducing GHG emissions.
- All special waste will be transport by suitable licenced contractor and be accompanied by correctly completed special waste consignment note (SWCN) providing information about the waste, the producer and the person the waste is being handed to; the SWCN will be kept for three years, the Site Responsible Manager is responsible for ensuring these are retained onsite.
With best practice mitigation measures in place, the residual significance of effect on material assets and waste is considered to be not significant. Therefore, in accordance with DMRB Guidance document LA 110: Material Assets and Waste, no further assessment is required.
Noise and vibration
Impacts
- Noise heavy works will likely be required (temporarily) during night-time hours, which could cause disturbance for nearby sensitive receptors (such as residential properties within 300m).
- TS2010 road surfacing offers enhanced durability and noise reducing properties compared to standard surfacing materials. As a result, both road users and nearby receptors are expected to benefit from the improved surface quality over the long term.
- Post-construction, the works are not expected to alter existing baseline noise levels for any sensitive receptors.
Mitigation
Mitigation measures follow Best Practicable Means as outlined in British Standard (BS) 5228:2009+A1:2014. The standard provides specific detail on suitable measures for noise control in respect to construction operations, for example:
- On-site construction tasks will be programmed to be as efficient as possible, with a view to limiting noise disruption to local sensitive receptors. The noisiest works will be undertaken before 23:00 where possible.
- Effects from noise will be kept to a minimum through the use of appropriate mufflers and silencers fitted to machinery. All exhaust silencers will be checked at regular intervals to ensure efficiency.
- A ‘soft start’ to works will be in place, whereby plant/machinery/vehicles are started sequentially as opposed to simultaneously.
- The site supervisor will monitor the effects of noise and vibration levels during the works and make necessary working arrangements.
The following further mitigation measures related to noise and vibration will be in place:
- Amey’s environmental briefing on noise and vibration will be delivered to operatives prior to the start of construction.
- Amey’s ET&S team has contacted Perth and Kinross Council’s Environmental Health Team to notify of the works and discuss any noise related concerns.
- Residential properties within 300m will be notified in advance of the works via letter drop, providing details of timings, nature, and duration of the works.
With best practice mitigation measures in place, and due to the works being of a minor, temporary, transient nature, no significant effects are predicted for noise and vibration. Therefore, in accordance with DMRB Guidance document LA 111: Noise and Vibration and no further assessment is required.
Population and human health
Impacts
- Construction site lighting during night-time hours could cause disturbance for residential properties in close proximity, and for the nearby amenity users.
- TM has potential to cause temporary levels of disruption to road users (i.e. congestion and increased travel times).
- There will be no permanent or temporary impacts on land take from private land, community facilities or agricultural land as a result of the scheme as all works will be contained within the carriageway boundary.
- Potential for restricted access to farmland adjacent to the works, laybys and residential properties.
Mitigation
- TM will be advertised upon approach and in advance of the scheme. When in place, TM will be monitored to ensure it is effectively managing traffic flow.
- Temporary site lighting used throughout the scheme will be directional and pointed only at the area of works.
- Site specific control measures regarding noise and vibration, landscape and visual effects and air quality can be found in the relevant sections (above).
- Due to night-time programming, properties within 300m of the scheme extents will be notified in advance of the works. Pre-notification will include details of proposed timings, duration of the works.
- Single access points to properties and private land will be maintained at all times throughout the scheme.
With best practice mitigation measures in place, no significant effects on population and human health are predicted. Therefore, in accordance with DMRB Guidance document LA 112: Population and Human Health, no further assessment is required.
Road drainage and the water environment
Impacts
- Potential for spills, leaks or seepage of fuels and oils associated with plant to escape and reach drainage systems if not controlled, which may impact the water environment.
- If not appropriately controlled, debris and runoff from the works has the potential to enter nearby drains and watercourses and could detrimentally impact water quality.
- In the event of a flooding incident, debris may be mobilised and could enter the road drainage having a detrimental effect on the surrounding local water environment.
- The Strathmore and Fife NVZ will not be impacted by the proposed scheme due to the nature of the works (e.g. minor, transient etc.) combined with the relevant pollution control measures detailed below.
- The resurfacing works will not increase flood risk as they are limited to the existing impermeable carriageway surface, with no alteration to drainage infrastructure or surface water runoff patterns. No other post construction impacts are anticipated.
Mitigation
- Best practice, as detailed by SEPA’s Guidance for Pollution Prevention (GPP5 and PPG6), will always be followed onsite. This will ensure that any potential debris/spills are not allowed to enter road drainage unchecked.
- Appropriate measures will be implemented onsite to prevent any potential pollution to the natural water environment (e.g. debris, dust and hazardous substances). This will include, but will not be limited to, spill kits being present onsite at all times, and the use of funnels and drip trays when transferring fuel, and utilisation of drain covers/shielding boards.
- Any pollution incidences will be reported to the Amey control room.
- Operatives will conduct regular checks of the work site, especially in periods of heavy wind and rainfall.
- All debris which has the potential to be suspended in surface water and wash into the local water environment will be cleaned from the site following the works.
- Bunds will be provided around drums up to 205 litres with a buffer of 25% of their capacity, and around bulk storage to a capacity of 110% of the stored fuel/oil.
- All plant and fuel storage at the site compound will be located on hardstanding and sited more than 10m from any watercourse.
- All plant and fuel storage areas will be located away from areas that see high vehicular movement to prevent accidental damage.
- All oils and fuels will be returned to storage area after use.
- No refuelling will take place within 10m of any watercourse, including field drains and road drainage.
- Weather reports will be monitored prior to and during all construction activities. In the event of adverse weather/flooding events, all activities will temporarily stop, and only reconvene when deemed safe to do so, and when run-off/drainage can be adequately controlled to prevent pollution.
Providing all works operate in accordance with current best practice, as demonstrated by SEPA’s Guidance for Pollution Prevention (GPPs), no significant effects are predicted on the water environment. Therefore, in accordance with DMRB Guidance document LA 113: Road drainage and the water environment no further assessment is required.
Climate
Impacts
- GHG emissions will be emitted through the use of machinery, vehicles and materials used (containing recycled and virgin materials) and transporting to and from site.
Mitigation
- Local suppliers will be used as far as reasonably practicable to reduce travel time and GHG emitted as part of the works.
- Vehicles/plant will not be left on when not in use to minimise and prevent unnecessary emissions.
- The use of Super-Low Carbon materials are being considered for this scheme, which is an asphalt solution that integrates biogenic materials into the bitumen to retain carbon.
- Further actions and considerations for this scheme are detailed in the above Material assets and waste section.
With best practice mitigation measures in place, the residual significance of effect on climate is considered to be not significant. Therefore, in accordance with DMRB Guidance document LA 114: Climate, no further assessment is required.
Vulnerability of the project to risks
As the works will be limited to the like-for-like resurfacing of the carriageway, there will be no change in vulnerability of the road to risk, or in severity of major accidents/disasters that would impact on the environment.
It has been determined that the proposed scheme will not alter the vulnerability of the existing trunk road infrastructure to risk of major accidents or disasters.
Assessment cumulative effects
The Scottish Road Works Commissioner's Interactive Map does not highlight any other works in the area at the time of construction.
Perth and Kinross Council’s Planning Portal does not highlight any proposed developments or planning applications on the A9 carriageway within 2km of the scheme.
Amey’s current programme of works has not highlighted any other works on the A9 that will be undertaken in conjunction with the scheme.
No other nearby schemes which may result in a combined effect on nearby receptors have been identified.
Any future schemes will be programmed to take into account already programmed works, and as such any effect (such as from TM arrangements and potential construction noise) will be limited.