Statement of case in support of a Determination that a statutory EIA is not required
This is a relevant project in terms of section 55A(16)] of the Roads (Scotland) Act 1984 as it is a project for the improvement of a road and the completed works (together with any area occupied by apparatus, equipment, machinery, materials, plant, spoil heaps, or other such facilities or stores required during the period of construction) exceed 1 hectare in area.
The project has been subject to screening using the Annex III criteria to determine whether a formal Environmental Impact Assessment is required under the Roads (Scotland) Act 1984 (as amended by The Roads (Scotland) Act 1984 (Environmental Impact Assessment) Regulations 2017). Screening using Annex III criteria, reference to consultations undertaken and review of available information has not identified the need for a statutory EIA.
The project will not have significant effects on the environment by virtue of factors such as:
Characteristics of the scheme
The works are limited in scope, short-term and confined to the existing carriageway. No significant disturbance to protected species or sensitive habitats is anticipated and the risk of major accidents or disasters is low. Any environmental effects are expected to be temporary and restricted to the construction phase, with no adverse operational impacts. The scheme is expected to deliver minor positive operational effects for road users and nearby receptors through the improved road surface. No in-combination or cumulative effects are identified.
Location of the scheme
The scheme is not situated in whole, or in part in a sensitive area, nor is it located within 2km or with hydrological connectivity to a European site. The works are not located within an area designated for its specific landscape character or quality.
All activities will be contained to the existing A90 carriageway surface. As a result, no land take or vegetation removal is required, and the scheme will not alter existing land uses or affect surrounding habitats.
Characteristics of potential impacts of the scheme
Appropriate measures will be implemented to ensure appropriate removal and disposal of waste, alongside containment measures to prevent debris and pollutants from entering the surrounding environment. Measures to minimise the potential disturbance to protected species will also be in place.
Overall, any environmental effects arising from the works are expected to be temporary, minor and confined to the construction phase with no significant or long-term impacts. No in combination effects with other projects or works have been identified.