Project Details

Description

Resurfacing works are required to maintain the safety and integrity of a section of the A90 carriageway (Southbound (SB)), south of Laurencekirk in Aberdeenshire, covering a total area of 1.2ha. The works are required as the carriageway is currently displaying various structural defects, such as fretting, rutting, cracking and patching.

Construction activities and the associated plant and machinery required are as follows:

  • Implementation of Traffic Management (TM) and marking out site (TM plant);
  • Removal of existing surfacing and milling to agreed depths (planer, wagon, lorries);
  • Resurfacing to the existing road levels using TS2010 aggregate, AC binder, AC base (paver, roller);
  • Reinstatement of road markings, linings, and studs (lorries/wagons and plant); and,
  • Removal of TM.

The proposed construction is programmed to be undertaken and completed within the 2025-2026 financial year during nighttime hours over a period of one week.

TM plans are yet to be confirmed but will likely consist of lane closures.

Location

The scheme extents are located along the A90 SB carriageway, south of Laurencekirk in Aberdeenshire at the following National Grid References (NGRs) (Figure 1):

  • Scheme Start - NO 72159 71077
  • Scheme End - NO 70788 70174