Project Details
Description
The works are required to maintain the safety and integrity of a stretch of the A92 carriageway within Glenrothes, Fife. The carriageway is presenting signs of continual deterioration.
Construction activities will entail the resurfacing of the A92 carriageway between the Tullis roundabout and Tofthill with the activities as follows:
- Installation of Traffic Management (TM);
- Milling of carriageway to agreed depths;
- Resurfacing of the carriageway to existing road levels using TS2010 surface source, AC20 binder and AC32 bituminous base;
- Reinstatement of road markings, linings and studs; and
- Removal of TM.
The following (but not limited to) plant/machinery/vehicles may be used throughout the scheme:
- Planer;
- Wagon(s);
- Bitumen tank;
- Extrusion liner;
- Paint tanker;
- Paver; and
- Roller(s).
The works are scheduled to be completed within the 2025/2026 financial year (ending on 1st April 2026) for a duration of seven to 10 nights, with works being undertaken during night-time hours.
TM for the scheme will consist of carriageway closures on the A92 carriageway. A diversion route will be in place, with the A911 and B969 local carriageways being utilised. Only local access to the area of works will be permitted with all other traffic diverted.