APPENDIX 3. POTENTIAL EFFECTS OF PROPOSALS ON EROSION
APPENDIX 3. POTENTIAL EFFECTS OF PROPOSALS ON EROSION
Current Service |
Proposed (preferred option) |
Theme |
Erosion Potential Areas 1,2 |
Ferry Information and Assumptions |
Likely Impacts |
Firth of Clyde |
|||||
Arran Two routes:
|
|
|
|
Ardrossan-Brodick
|
Increase in vessel traffic at the Ardrossan and Brodick Ports could increase the risk of erosion in the vicinity of these ports, particularly during approaches and vessel turning. |
|
|
|
|
No effects identified |
|
Bute Two routes:
|
|
|
|
Colintraive-Rhubodach
|
Colintraive-Rhubodach Increasing vessel movements could increase the risk of erosion in the vicinity of the ports on the Kyles of Bute. However, the effect of increasing the operating day from 14 to 18 hours is unlikely to result in an increase in vessel numbers large enough to result in significant effects. |
Cumbrae-Largs. Two vessel service, extended (14 hour) operating day, early morning-middle evening |
Extension of operating day into late evening: increased services |
Additional vessel movements on existing route |
Cumbrae and Largs - beaches with high erosion potential located adjacent to both ports. |
|
Increased vessel movements could increase erosion potential of beaches adjacent to both ports. However, the effect of increasing the operating day from middle to late evening is unlikely to result in an increase in vessel numbers large enough to result in significant effects. |
Cowal Peninsula/Dunoon Gourock to Dunoon: shuttle-basis seven days per week, early morning to very late evening. Hunter's Quay (Dunoon) to mcinroy's Point (Gourock): commercial service |
Retain status quo |
No change |
No impacts |
No impacts |
No impacts |
Inner Hebrides |
|||||
Coll and Tiree Oban - Coll and Tiree
|
|
|
|
Oban - Coll and Tiree
|
Oban - Coll and Tiree Increasing the number of vessel movements in winter could increase the risk of localised erosion at locations along the Sound of Mull. However, large ropax ferries also travel to the outer Hebrides on other routes via the sound , and it is unlikely that increasing the winter sailings by 2 days a week for this route will greatly increase erosion. Localised erosion may occur in the vicinity of the Oban, Coll and Tiree ports due to additional vessels turning at these ports. It is uncertain whether this would be significant. |
Mull Four services:
|
|
|
|
Craignure - Oban
Fishnish to Lochaline.
Tobermory to Kilchoan
|
Craignure - Oban: Increasing vessel numbers to a two vessel service could increase erosion potential at Oban and Craignure ports during vessel turning at both ends of the route. Significance of effect is uncertain. Fishnish to Lochaline: Removing service will eliminate erosion risk along this route from this service. Tobermory to Kilchoan: Significant impacts are considered unlikely as the change is not expected to result in a significant increase in vessel movements. |
Iona Summer and winter services |
|
|
Fionnphort-Iona
|
Fionnphort-Iona
|
Increase in vessel movements could increase risk of erosion immediately adjacent to the existing Fionnphort Ferry Terminal. However, the effect of increasing the operating day by 90 minutes is unlikely to result in an increase in vessel numbers large enough to result in significant effects. Secondary impacts from construction works, dredging and changes to the wave patterns generated by this new berthing facility may result in localised erosion or accretion at Fionnphort. This would need to be explored at project level. |
Ardnamurchan / Morvern Four ferry routes:
|
|
No change |
No impacts |
No impacts |
No impacts |
Lismore Two routes:
|
|
|
|
Oban-Achriacroish
Port Appin-Ramsey Point
|
Oban-Achriacroish: Removing service will eliminate erosion risk along this route from this service. Port Appin-Ramsey Point: Increase in services could increase potential for erosion in susceptible areas at Port Appin and Ramsey Point. Particular concern is during vessel turning (if a single ramp vehicle vessel is introduced rather than a double ramp vessel) and vessels approaching and leaving both ports. Significance is uncertain. |
Kerrera, Luing and Easdale Island
|
Retain status quo |
No change |
No impacts |
No impacts |
No impacts |
Northern Isles |
|||||
Services to Aberdeen Lerwick-Aberdeen every day with overnight journey to Aberdeen. Stops at Kirkwall on three days. Two-vessel service |
Retain status quo |
No change |
No impacts |
No impacts |
No impacts |
Pentland Firth Three routes:
|
Retain status quo |
No change |
No impacts |
No impacts |
No impacts |
Orkney and Shetland Isles Operated by local authorities |
Retain status-quo (SG to work with Local Authorities to review suitability of services) |
No change |
No impacts |
No impacts |
No impacts |
Skye, Raasay, the Small Isles and Knoydart |
|||||
Skye Mallaig to Armadale:
|
|
Subsidy change only |
No impacts |
No impacts |
No impacts |
Raasay Sconser to Raasay, every day, early morning to early evening |
Retain status quo but explore further as part of next CHFS contract |
No change |
No impacts |
No impacts |
No impacts |
The Small Isles (Muck, Eigg, Rum and Canna) are currently served by one vessel operating from Mallaig (for them all). Depending on the actual island there are between four and five sailing days in summer and three to four in winter. The number of sailings per day ranges from one to two sailings. The current time-table allows visitors to make a meaningful return trip in the course of a day, but does not allow residents to travel to the mainland and back on the same day. |
Shorter-term options:
Longer-term option:
|
Increase in number of vessel movements |
|
Mallaig to Small Isles
|
Increased ferry traffic at Mallaig port could increase localised erosion from the service, particularly due to vessel turning and particularly at the sheltered beach area identified immediately east of the port. Significance is uncertain. Increasing services in the short and long term could increase localised erosion potential at ports and surrounding areas on Eigg, Rum, Muck and Canna. Significance is uncertain. |
Knoydart Mallaig-Inverie-Tarbet: Summer: five days per week Winter: three days per week |
Community asked for views on whether additional sailing days in both the summer and winter seasons required. |
Increase in number of vessel movements |
Erosion-susceptible shorelines including beaches, soft strands and soft-rock cliffs along the north and east banks of Loch Nevis, and in the vicinity of the Tarbet and Inverie ports. |
Wide but reasonably sheltered loch (>1km), but narrowing near Tarbet). No vessel details available, but likely a small or medium vessel. 10-14 knots speed likely. Vessel turning likely to be required. |
Increased services could increase erosion risk on identified susceptible shorelines, particularly in the vicinity of the Tarbet and Inverie ports during vessel turning. Significance is uncertain. |
Southern Hebrides |
|||||
Islay and Jura Kennacraig-Port Askaig/ Port Ellen: Seven days/week, 3-4 services/day. Port Askaig-Feolin (Jura): small shuttle service. |
|
|
|
Islay-mainland and Jura-mainland
Port Askaig
Port Ellen
|
Islay-mainland and Jura-mainland: No impacts as no changes proposed. Port Askaig: Additional ferry vessels from traversing the narrow (~0.6km) Sound of Islay and docking in Port Askaig. May increase risk of erosion at beach areas identified on west coast of Jura (with high erosion potential), particularly with additional vessel turning at Port Askaig located in the narrow strait. Significance is uncertain. Port Ellen: No significant changes are expected as few erosion susceptible areas have been identified on this route. |
Colonsay Oban-Colonsay:
|
|
Increase in number of vessel movements |
Cliffs and beaches identified respectively near Oban and Colonsay ports as being susceptible to erosion. |
Oban-Colonsay
|
Increasing services could increase localised erosion potential at Oban and Colonsay ports, particularly during vessel turning and port approaches at both ends of the route. However, given the small increase in service numbers, significant erosion impacts are considered unlikely. These potential impacts at Oban may be offset with the closure of other services from Oban (ie. Oban to Achriacroish, movement of services out of Mallaig instead of Oban). |
Gigha Gigha-Tayinloan: seven days per week; early morning to early evening; frequent basis. |
|
|
|
Gigha-Tayinloan
|
Increased vessels could increase erosion risk to the significant beach areas at both Tayinloan and Gigha ports during approaches to and leaving the ports. Significance is uncertain. |
Kintyre Tarbert-Portavadie |
|
|
|
Campbeltown-Arran-Ardrossan/ Troon
|
An increase in vessel traffic at the Campbeltown, Brodick and Troon Ports could increase the risk of erosion in the vicinity of these ports, particularly during vessel turning. However, given the projected increase, significance is uncertain. Ferries between Campbeltown and Troon may need to keep a sufficient distance from the coast north and south of Troon to reduce erosion risk in this identified actively eroding area. This needs to be investigated further at project level. |
Western Isles |
|||||
Lewis and Harris:
Uists and Benbecula:
Barra:
Sound of Harris (inter-island service Berneray - Leverburgh) Southern "set" South Uist
Sound of Barra (inter-island service Aird Mhor, Barra - Eriskay) Five services to mainland, two inter-island services |
|
No change |
No impacts |
No impacts |
No impacts |