Design development

Since the announcement of the preferred route for the Long-Term Solution (LTS) the project team have been undertaking further design development work as part of the DMRB Stage 3 Assessment, including:

  • Refinement of the A83 carriageway alignment
  • Design of the B828 Glen Mhor local road junction
  • Development of the debris flow shelter and protection wall design
  • Refinement of the geotechnical aspects of the design, including further geohazard and rock-fall modelling
  • Development of the proposals to minimise the impact on the environment, informed by various environmental surveys and field work
  • Development of the proposals to mitigate impacts on the water environment, including sustainable drainage proposals
  • Consideration of construction methodology to minimise disruption to road users during the construction phase
  • Consideration of the proposals for the Rest and Be Thankful Car Park and Viewpoint

Design Manual for Roads and Bridges (DMRB) Process

DMRB Stage 1 (Completed April 2021)

Strategic assessment and identification of a preferred route corridor.

DMRB Stage 2 (Completed June 2023)

Route option assessment and identification of a preferred route.

DMRB Stage 3 ( In progress)

Development and assessment of preferred option.

Statutory Process

Publication of draft Orders and Environmental Impact Assessment Report - not yet started.

Procurement

Not yet started.

Construction

Not yet started.

Typical Large Scale Infrastructure Project Timeline

  • DMRB Stage 1 - 1-2 years
  • DMRB Stage 2 - 1.5-2 years
  • DMRB Stage 3 - 1.5-2 years
  • Statutory Process - 1-2 years (Subject to need for Public Local Inquiry)
  • Procurement - 1 year (Subject to procurement route)
  • Construction - currently estimated 3-4 years