Appendix D - Central Tower Stability D.1 Comparison between single main span and double main span bridge D.2 Static Behaviour D.3 Dynamic Behaviour D.4 Potential Means to Stabilise the Central Tower

Appendix D - Central Tower Stability

This section is also available in pdf format (520k)

D.1 Comparison between single main span and double main span bridge

One of the major structural issues for the double main span bridge proposed for the Forth Replacement Crossing is related to the stability of the central tower. The bridge is significantly less stiff than for a bridge with a single main span due to the lack of longitudinal restraint to the top of the central tower.

At the concept design stage a plane-frame analysis model of a bridge incorporating a typical tower and typical box girder deck was established to illustrate this effect and serve as a means for a parametric study of ways in which the central tower can be stabilised.

D.2 Static Behaviour

9 lanes of traffic are applied to the bridge. The deflection of the single main span bridge is within the expected range and validates the model. The deflection of the double main span bridge is over twice that of the single main span bridge. A significant horizontal deflection of the central tower is observed. Although the serviceability deflection criteria have not yet been established, the running of trams or LRT on the bridge would generally require a reasonably stiff structure.

δ = 2,200 mm

δ = 2,200 mm

δ =4,565 mm

δ =4,565 mm

The flexural moment due to live load at the base of tower is also increased approximately threefold.

Moment at base of tower = 355 MNm

Moment at base of tower = 355 MNm

Moment at base of tower = 1090 MNm (central) and 495 MNm (flanking)

Moment at base of tower = 1090 MNm (central) and 495 MNm (flanking)

 

D.3 Dynamic Behaviour

The reduction in vertical stiffness is associated with a reduction in the vertical frequency of vibration. This has potential implications for aerodynamic behaviour since a more flexible structure is more susceptible to aerodynamic instability.

f = 0.29 Hz

f = 0.29 Hz

f = 0.16 Hz

f = 0.16 Hz

D.4 Potential Means to Stabilise the Central Tower

The problem of a double main span cable stay bridge is well recognised and the proposal made during the FRCS study was to adopt very rigid pyramid type towers with large foundations in order to provide a central tower which is stiff in its own right.

Bridge elevation proposed by FRCS Report 4 Appendix C

Bridge elevation proposed by FRCS Report 4 Appendix C

Such a tower type has been successfully adopted on Rion-Antirion bridge with 560 m spans as illustrated below. However, the resulting structure is visually imposing which is unlikely to be appropriate for this site where particular attention must be paid to not over-dominate the existing bridges. The foundation costs may also be increased.

Rion Antirion Bridge (2004), Greece

Bridge elevation proposed by FRCS Report 4 Appendix C

Another example of using a triangulated tower to stabilise a multi-span cable stay system is the Maracaibo Bridge with 235 m spans.

Maracaibo Bridge (1962), Venezuela

Maracaibo Bridge (1962), Venezuela

An alternative means has been previously adopted on the Ting Kau Bridge with 448 m and 475 m main spans. Stabilising cables were used which tied the central tower back to the deck/tower junction of the flanking towers. The solution is not particularly aesthetically pleasing due to the visual onfusion between the cable fans and the tie back cables with their pronounced visible sag.

Ting Kau Bridge (1998), Hong Kong

Ting Kau Bridge (1998), Hong Kong

There are likely to be some technical difficulties with extending this solution to a 650m main span. The stay cables required would be approximately 20% longer than the longest stay cables ever produced in the world. The visible sag would be significantly increased with the longer stay cables and the effectiveness of the system would be reduced as the stiffness of long cables is greatly reduced due to their sag. The tensions in the stabilising cables would be increased and may be difficult to equilibrate through the deck. It is therefore not recommended.

The Millau Viaduct provides a very elegant example of a multi-span cable stay bridge where the central towers have been stabilised by a combination of stiffness in the deck and tower. The towers are also slightly triangulated with a longitudinal dimension of 15.5 m at deck level which gives reasonable proportions. The deck is 4.2 m deep spanning 342 m, a span to depth ratio of 80 which would correspond to a structural depth of 8.1 m for a 650 m span. Additionally, the deck has a moment connection to the towers which further increases its flexural stiffness.

Millau Viaduct (2004), France

Millau Viaduct (2004), France

One final solution to be considered is to extend the stay cable fans so that they cross in the centre of each of the main spans. Although this solution has not been adopted on any major cable stay bridges to date it has been proposed as a viable solution by Professor Niels Gimsing in Cable Supported Bridges:Concept and Design which also refers to previous studies carried out by others. Parametric studies to investigate this alternative were carried out at the concept design stage to validate it as a practical and efficient means to stabilise the tower.

Two alternatives are recommended for further consideration and have been investigated in detail to confirm their structural viability for this project.

Functional Cross Section

Central Tower Stability

Three Corridor

Achieved by crossing cables in the centre of the main spans

Double Level Deck

Use the combined deck and tower stiffness to achieve sufficient static and dynamic global stiffness.