5 Design Implications and Sustainability

5 Design Implications and Sustainability

5.1 Introduction

This section summarises the key design ideas and innovations that have been generated by the team during the design stage in order to improve the sustainability of the various structures and earthworks used in the FRC scheme. It addresses these under the headings of:

  • Main Crossing; and
  • Road Connections (roads, earthworks and land-based structures).

Each are summarised in tabular form and include the design idea, its sustainability benefits and how it is to been taken forward within the project. Ideas that are now standard best practice are left out of these tables but included in Appendix 7. This latter provides an overall summary of the various ideas and innovations and indicates where these generate different benefits within the overall ‘sustainability mix’.

In addressing the sustainability objectives, targets and indicators as reviewed in Section 4, there have been a number of sustainability design ideas and innovations brought forward. These have either been incorporated into the Stage 3 design or will be considered at the tender design stage.

5.2 Main Crossing

Table 15: Key Design Ideas and Innovations for the Main Crossing

Design Proposal

Sustainability Objectives contributed to*

Outcome and State of Progress

Wind shielding on Main Crossing will improve reliability

To design, build and operate a reliable crossing (1)

Taken forward through Stage 3 Design / Employer’s Requirements

Both carriageways on the Main Crossing will have widened hard shoulders

To design, build and operate a reliable crossing (1)

Taken forward through Stage 3 Design / Employer’s Requirements

Dedicated public transport corridor helps public transport services run more reliably

To design, build and operate a reliable crossing (1)

To contribute to the improvement of cross-Forth access to economic opportunities (2)

To contribute towards the development of cross-Forth public transport opportunities (3)

To improve local accessibility and reduce community severance (7)

To contribute to the promotion of healthy lifestyle opportunities and social inclusion (9)

To minimise carbon emissions once the scheme is opened to traffic (13)

Taken forward through Stage 3 Design / Employer’s Requirements

Intelligent Transport Systems (ITS) will help to regulate the flow of traffic

To design, build and operate a reliable crossing (1)

To provide a safe design for both vehicle travellers and non-motorised users (10)

To minimise carbon emissions once the scheme is open to traffic (13)

Taken forward through Stage 3 Design / Employer’s Requirements

Specification of carriageway surfacing to the cable-stayed bridge to reduce the frequency at which resurfacing is required

To design, build and operate a reliable crossing (1)

To adopt sustainable resource management in design and construction (5)

To reduce, reuse and recycle materials and products where practicable (11)

Options considered at Stage 3 Design. Contractor to choose most practicable option.

Energy-efficient ITS and lighting systems

To minimise carbon emissions once the scheme is opened to traffic (13)

To be considered at Tender Design Stage

Sustainable sourcing of steel

To adopt sustainable resource management in design and construction (5)

To reduce, reuse and recycle materials and products where practicable (11)

To minimise embodied energy and carbon associated with the construction of the scheme (12)

To be considered at Tender Design Stage

* Sustainability Objective no. in brackets

5.3 Road Connections

5.3.1 Roads and Earthworks

Table 16: Key Design Ideas and Innovations for Roads and Earthworks

Design Proposal

Sustainability Objectives contributed to*

Outcome and State of Progress

Hard shoulder provision on the scheme. The proposed scheme will incorporate hard shoulders on the majority of the scheme

To design, build and operate a reliable crossing (1)

To contribute to the improvement of cross-Forth access to economic opportunities (2)

To provide a safe design for both vehicle travellers and non-motorised users (10)

Taken forward through Stage 3 Design / Employer’s Requirements

New and improved car/bus interchanges to facilitate use of public transport

To design, build and operate a reliable crossing (1)

To contribute to the improvement of cross-Forth access to economic opportunities (2)

To contribute towards the development of cross-Forth public transport opportunities (3)

To improve local accessibility and reduce community severance (7)

To contribute to the promotion of healthy lifestyle opportunities and social inclusion (9)

To minimise carbon emissions once the scheme is open to traffic (13)

Taken forward through Stage 3 Design / Employer’s Requirements

Provision for non-motorised users (NMU paths and crossings at Queensferry Junction and Ferrytoll Junction)

To improve local accessibility (7)

To contribute to the promotion of healthy lifestyle opportunities and social inclusion (9)

Taken forward through Stage 3 Design / Employer’s Requirements

Ensuring the scheme accommodates the needs of disabled people (DDA 2005)

To contribute to the improvement of cross-Forth access to economic opportunities (2)

To provide a scheme that accommodates the needs of disabled people (8)

Taken forward through Stage 3 Design / Employer’s Requirements

Optimisation of cut and fill balance to minimise the need to import, or export, fill from site

To adopt sustainable resource management in design and construction (5)

To reduce, reuse and recycle materials and products where practicable (11)

To minimise embodied energy and carbon associated with key materials and their transport to site (12)

Taken forward through Stage 3 Design / Employer’s Requirements

Pass majority of runoff through SUDS

To protect water quality, geomorphology and maximise the use of sustainable drainage systems for environmental and hydrological benefit (17)

Taken forward through Stage 3 Design / Employer’s Requirements

Limit number of watercourse crossing and re-alignments by making use of existing infrastructure

To protect water quality, geomorphology and maximise the use of sustainable drainage systems for environmental and hydrological benefit (17)

Taken forward through Stage 3 Design / Employer’s Requirements

Sourcing timber products from certified sustainable sources (e.g. FSC)

To adopt sustainable resource management in design and construction (5)

To reduce, reuse and recycle materials and products where practicable (11)

To minimise embodied energy and carbon associated with key materials and their transport to site (12)

To protect and enhance the natural heritage including local biodiversity (14)

To be considered at Tender Design Stage

Use of recycled materials in highway design (including, recycled aggregate, kerbs, plastic pipes)

To adopt sustainable resource management in design and construction (5)

To reduce, reuse and recycle materials and products where practicable (11)

To minimise embodied energy and carbon associated with key materials and their transport to site (12)

To protect and enhance the natural heritage including local biodiversity (14)

To be considered at Tender Design Stage

* Sustainability Objective no. in brackets

5.3.2 Land-based Structures

Table 17: Key Design Ideas and Innovations for Land-Based Structures

Design Proposal

Sustainability Objectives contributed to*

Outcome and State of Progress

Retain and re-use existing structures where possible

To reduce, reuse and recycle materials and products where practicable (11)

To provide a safe design for both vehicle travellers and non-motorised users (10)

To minimise embodied energy and carbon associated with key materials and their transport to site (12)

To reduce noise and air emissions (16)

Taken forward to Stage 3 Design and to be utilised at:

M9 Junction 1A

Overton Road Bridge

Newmains Road Bridge

Existing Ferrytoll railway bridges

 

To accept non-toxic products for concrete impregnation

To adopt sustainable resource management in design and construction (5)

To protect and enhance the natural heritage including local biodiversity (14)

To protect water quality, geomorphology and maximise the use of sustainable drainage systems for environmental and hydrological benefit (17)

This is not a mandatory contract requirement. The Contractor could consider this design proposal for the detailed design.

 

Lightweight fills for abutments / wingwalls etc

To adopt sustainable resource management in design and construction (5)

To reduce, reuse and recycle materials and products where practicable (11)

To minimise embodied energy and carbon associated with key materials and their transport to site (12)

This could not be included at Stage 3 design. The Contractor could consider this design proposal for the detailed design.

 

Stainless steel reinforcement in areas of high exposure (piers / parapet edge beams) to reduce future maintenance

To adopt sustainable resource management in design and construction (5)

To reduce, reuse and recycle materials and products where practicable (11)

This could not be included at Stage 3 design. The Contractor could consider this design proposal for the detailed design.

 

Greater use of voided concrete construction to reduce materials (Cobiaxdeck, voided abutments)

To adopt sustainable resource management in design and construction (5)

To reduce, reuse and recycle materials and products where practicable (11)

To minimise embodied energy and carbon associated with key materials and their transport to site (12)

This could not be included at Stage 3 design. The Contractor could consider this design proposal for the detailed design.

 

Precast Technologies – Precast foundations, columns crossheads, beams and deck

To adopt sustainable resource management in design and construction (5)

To reduce, reuse and recycle materials and products where practicable (11)

To minimise embodied energy and carbon associated with key materials and their transport to site (12)

This could not be included at Stage 3 design. The Contractor could consider this design proposal for the detailed design.

 

Compressive membrane action to reduce reinforcement in deck slabs

To adopt sustainable resource management in design and construction (5)

To reduce, reuse and recycle materials and products where practicable (11)

To minimise embodied energy and carbon associated with key materials and their transport to site (12)

This could not be included at Stage 3 design. The Contractor could consider this design proposal for the detailed design.

 

Use of non-chemical de-icing or non-salt de-icing products

To adopt sustainable resource management in design and construction (5)

To protect and enhance the natural heritage including local biodiversity (14)

To protect water quality, geomorphology and ecology (17)

This is not a mandatory contract requirement. The maintaining authority could consider this proposal.

 

Flexi-arch for culverts and/or pipeline structures

To adopt sustainable resource management in design and construction (5)

To provide a safe design for both vehicle travellers and non-motorised users (10)

Not taken forward on major utility structures due to cover requirements from crown of structure. Flexi arch was not applied to a new culvert (Swine Burn) due to flood water flow conditions and also the need to form a low flow channel through the culvert.

 

Self compacting concrete

To minimise embodied energy and carbon associated with key materials and their transport to site (12)

Not to be taken forward

Over widening bridges for future lane provision

To contribute towards the development of cross-Forth public transport opportunities (3)

Incorporated for A8000 overbridge and for hard shoulders on the main crossing, in both cases to facilitate future public transport opportunities.

T-headed reinforcement – Reduce anchorage length of rebar (Departure required)

To adopt sustainable resource management in design and construction (5)

To reduce, reuse and recycle materials and products where practicable (11)

To minimise embodied energy and carbon associated with key materials and their transport to site (12)

Not covered by current British Standards or included in future Eurocodes. Design has not been implemented on highway bridges and therefore no evidence of its structural performance.

 

Lightweight concrete to reduce loading and member sizes

To adopt sustainable resource management in design and construction (5)

To reduce, reuse and recycle materials and products where practicable (11)

To minimise embodied energy and carbon associated with key materials and their transport to site (12)

The Client has specific concrete mix requirements to achieve the necessary strength as well as provide durable concrete structures and lightweight concrete would not comply.

 

Intelligent monitoring for structures

To provide a safe design for both vehicle travellers and non-motorised users (10)

Not taken forward due to cost and uncertainty of effectiveness. Current bridge maintenance regime is considered sufficient for monitoring the condition of structures.

* Sustainability Objective no. in brackets

5.4 Moving Forward to Construction

A number of the ideas and innovations that relate to the sustainability objectives with an ‘environmental’ focus have been generated during the EIA process and feature as identified mitigation measures. These will be contract requirements.

Other design ideas and innovations have already been incorporated into the Stage 3 design particularly those that have been identified as ‘best practice’.

A key output from the carbon footprinting work has been the development of a carbon calculator and baseline footprint for the Stage 3 design. This will be made available to the successful contractor who will be expected to deliver ‘no worse’ and preferably an improvement on the baseline carbon footprint.

The targets and requirements set out in the Sustainable Resource Management Framework and its associated Materials Plan will be included in the Contract.

It is intended that the ethos of sustainability will be a requirement of the Contract and the tenderers and the successful Contractor will be expected to join with the FRC team and work as a team to delivery sustainable benefit of the project.