Appendix 6: Energy and Carbon Report Contents 1 Introduction 2 Methodology 3 Initial Carbon Footprint Assessment 4 Embodied Energy and Carbon at Stage 3 Design 5 Carbon Emissions Associated with Earthworks 6 Options to Reduce Embodied Energy and Carbon 7 Carbon Emissions Associated with Transport of Materials 8 The Shadow Price of Carbon 9 Conclusions Annex A Energy and Carbon Values Annex B Embodied Energy and Carbon Calculations   Footnotes

Appendix 6: Energy and Carbon Report

This section is also available in pdf format (532k)

Contents

1 Introduction
1.1 Purpose
1.2 Background
1.3 Operational Carbon
1.3.1 Impact of Potential Cable Replacement Works
1.3.2 Scheme Features to Reduce CO2 emissions
1.4 CEEQUAL
1.5 Scheme Description

2 Methodology
2.1 Introduction
2.2 Highways Agency Carbon Accounting Tool
2.2.1 Emissions Calculation Approach
2.2.2 Key Data Sources
2.3 Inventory of Carbon and Energy
2.3.1 Selection Criteria
2.3.2 Transport
2.3.3 Recycling Methodology
2.3.4 Advisory Notes

3 Initial Carbon Footprint Assessment
3.1 Purpose
3.2 Limitations
3.3 Methodology and Scope
3.4 Presentation of Results
3.4.1 Data Gathering and Key Assumptions
3.4.2 Results
3.4.3 Sourcing Scenarios

4 Embodied Energy and Carbon at Stage 3 Design
4.1 Introduction
4.2 Road Connections
4.2.1 Roads Network
4.2.2 Land-Based Structures
4.3 Main Crossing
4.3.1 Substructure
4.3.2 Superstructure
4.4 Combination of Options for Main Crossing Superstructure
4.5 Embodied Energy and Carbon Summary

5 Carbon Emissions Associated with Earthworks
5.1 Maximising the Cut and Fill Balance
5.2 Export of Unacceptable Earthwork Material

6 Options to Reduce Embodied Energy and Carbon
6.1 Use of Recycled Aggregate
6.2 Using Recycled Steel

7 Carbon Emissions Associated with Transport of Materials
7.1 Introduction
7.2 Illustrative Sourcing Scenarios

8 The Shadow Price of Carbon
8.1 Introduction
8.2 Methodology
8.3 Illustrative Example
8.4 Monetising Carbon

9 Conclusions
9.1 Background and Purpose
9.2 Approach
9.3 Results of Embodied Energy and Carbon Assessment
9.4 Potential Options to Reduce Energy and Carbon
9.5 Operational Carbon
9.6 Next Stages

Annex A Energy and Carbon Values

Annex B Embodied Energy and Carbon Calculations

 

1 Introduction

1.1 Purpose

The purpose of this report is to provide information summarising:

  • how the issue of energy and carbon is addressed using sustainability management tools;
  • energy and carbon accounting;
  • the estimated energy and carbon footprint of the Stage 3 design; and
  • how the energy and carbon footprint will be monitored going forward against the above baseline.

1.2 Background

A key principle of the Sustainable Development Policy for the project (refer to Appendix 1) is to:

‘Seek to minimise the carbon footprint of the crossing and associated network connections by consideration of the impact of its design, procurement, construction, maintenance, operation and decommissioning’

A Sustainability Appraisal Framework has been established to underpin this policy and has been used at key stages (e.g. Stage 2 Options, Stage 3 Design). The Sustainability Appraisal Framework includes two objectives (together with associated targets and indicators) that focus on carbon, these are:

Table 1: Energy and carbon related sustainability objectives, targets, and indicators

Sustainability Objectives

Target

Indicators

12. To minimise embodied energy and carbon associated with the construction of the scheme

1. Seek to minimise the embodied energy and carbon associated with key materials and their transport to site

Estimated embodied energy and carbon

 

 

Actual embodied energy and carbon in materials, transportation and waste

 

2. Minimise energy use and all carbon emissions during construction

Predicted energy requirement and CO2 emissions

 

 

Actual energy used and CO2 emissions

13. To minimise carbon emissions once the bridge is opened to traffic

1. Seek to reduce CO2 emissions from vehicles crossing the Forth at Queensferry compared with existing FRB

Predicted CO2 emissions

 

2. Minimise the energy requirements of the new bridge (once it is open to traffic) to the minimum necessary for safe operation

Predicted energy requirements

 

 

Actual energy requirements

 

3. Maximise % of required energy for the bridge (once opened to traffic) acquired from renewable sources

Predicted energy sources

 

 

Actual energy sources

This report provides information which can be used to measure progress against objective 12, embodied energy and carbon associated with construction of the scheme.

1.3 Operational Carbon

The regional air quality assessment reported in Chapter 15 of the ES uses a standard approach to address the difference between the air quality that would be likely with the proposed scheme (the ‘Do-Something’ scenario) and without the proposed scheme (the ‘Do-Minimum’ scenario) for both the anticipated year of opening (2017) and the design year 15 years after opening (2032). The future Do-Minimum scenario assumes that the Forth Road Bridge is still in operation.

The regional assessment in the ES presents total CO2 emissions for the road network covered in the TMfS:05a (Traffic Model for Scotland) for 2005, 2017 Do-Minimum and 2017 Do-Something scenarios as well as total distance travelled in each scenario and emissions per kilometre travelled. Using standard methodology, there is a calculated increase of 14,952 tonnes per year of CO2 emissions between the Do-Minimum and Do-Something scenarios in 2017, which is consistent with the predicted increase in vehicle kilometres travelled along the traffic links selected for the regional air quality assessment.

This assessment of CO2 emissions is based on traffic flows from the strategic traffic model, TMfS:05A. This approach uses established Department for Transport formulae (DMRB emission factors) to calculate CO2 emissions based on model output speeds and volumes. This approach forecasts modest increases in CO2 emissions, associated with the introduction of the proposed scheme.

The use of the strategic traffic model has the advantage of wide network coverage, so all of the network effects of the proposed scheme will be encompassed by the assessment. The methodology used to calculate emissions is consistent with many other road projects assessed in Scotland in recent years and it is recognised as the current best practice. However, the CO2 calculations are based on average speeds and this approach is not capable of assessing the local impact of stop-start traffic conditions. In addition, it does not address the negative impact of the major maintenance and recabling work that would be likely to be required in the absence of a replacement crossing.

Transport Scotland recognised that a refinement to the standard methodology was required to address this matter. A new Passenger car and Heavy-duty Emission Model (PHEM) based emissions calculation module has been developed. This can be used with microsimulation models such as S-Paramics (referred to generically as Paramics). The emissions evaluation using Paramics with PHEM relationships is a technique being developed on behalf of Transport Scotland, but not yet fully approved for use in scheme appraisal. The information obtained from this evaluation tool has been used to supplement the strategic calculations which are based on the Department for Transport formulae. The PHEM based results are intended to provide a more informed view of the likely locally generated impact of the proposed scheme.

The PHEM model output is a series of emission factors, based on vehicle type, vehicle speed, vehicle loading and vehicle acceleration. This method calculates the rate of emission for each vehicle at each simulated timestep. The use of PHEM emissions relationships with the Paramics model offers the ability to take into account emissions from stop-start motoring, which is not fully reflected within the global evaluation within the air quality model which is based on traffic information from the Transport Model for Scotland (TMfS). The local PHEM based assessment therefore examines the localised effect of stop start motoring conditions on the congested approaches to the Forth Road Bridge and the localised benefits to be derived from relieving these conditions. It is recognised that this local assessment does not quantify wider impacts outwith the Paramics model area.

Traffic conditions in peak periods within the vicinity of the Forth Road Bridge are frequently congested. The established and standard methodology for calculating CO2 emissions, (based on the Department for Transport formulae), relies on average traffic speed as the basis for calculation. In comparison to the Do-Minimum, the proposed scheme will result in smoother traffic flows and improved journey time reliability. The average speed calculated on the network, using the Department for Transport method, in the vicinity of the scheme in the Do-Minimum scenario, reflects a range of emissions conditions from traffic which is variously accelerating, braking, idling and cruising, rather than travelling steadily at that average speed. One of the features of the Managed Crossing Scheme is that traffic will be controlled to improve flow conditions and hence, reduce emission rates, compared with the current conditions.

Tests were undertaken using the Paramics / PHEM module to compare Do-Something traffic emissions with Do-Minimum emissions in the AM and PM modelled periods for 2017 forecasts. The scheme design in conjunction with ITS operation will result in improved fuel efficiency and lower emissions per kilometre. However, the Do-Something scheme involves additional travel distance for cross Forth traffic and additional traffic demand which result in increased CO2 emissions.

In this Do-Something scenario, the additional CO2 emissions for the AM period are forecast to be 3.7 tonnes in the AM period and 14.7 tonnes in the PM period. These forecasts relate to AM and PM periods during average week day traffic. The proposed scheme involves some additional travel distance to cross the Forth and attracts more traffic to this part of the network. As a result of these two factors, the travel distance in terms of vehicle kilometres is expected to increase in the Do-Something scheme, compared with the Do-Minimum comparator.

Results of the test are presented in Tables 2 and 3.

Table 2: Total CO2 Emissions within the Paramics Network in 2017 (tonnes)

Pollutant

Emissions 2017 Do-Minimum

Emissions 2017 Do-Something

Difference 2017DM/2017 Do-Something

% Change (local area) 2017 Do-Something versus 2017 Do-Minimum

CO2 (Tonnes) AM

253.1

256.8

3.7

1.5%

CO2 (Tonnes) PM

268.4

283.1

14.7

5.5%

Table 3: Total vehicle Kilometres within the Paramics Network in 2017 

 

Vehicle Kilometres 2017 Do-Minimum

Vehicle Kilometres 2017 Do-Something

Difference 2017DM/2017 Do-Something

% Change (local area) 2017 Do-Something versus 2017 Do-Minimum

AM

932,669

995,484

62,815

6.7%

PM

1,129,048

1,191,004

61,956

5.5%

If the fuel efficiency of the network operation were to remain constant, the rate of CO2 per kilometre would also be expected to remain constant. Total vehicle kilometres is the measure of total distance travelled by all vehicles in the model network. If the Do-Something model were to operate with the same level of fuel efficiency as the Do-Minimum, then we would expect the proportionate change in emissions to be similar to the increase in vehicle kilometres.

When we compare the increases in CO2 in Table 2 with the increases in vehicle kilometres in Table 3, we can see that the percentage increase in CO2 in the PM peak is similar to the percentage increase in travel in the PM peak. However, in the AM peak the percentage increase in CO2 is significantly lower than the increase in travel distance and hence, less than might otherwise be expected. The test indicates that during the congested morning peak period, the forecast increase in CO2 emissions from the additional traffic and distance travelled is reduced by the improved scheme design and operation of ITS, which reduces congestion.

There is less congestion relief forecast in the evening peak and therefore a smaller reduction in the predicted increase in CO2 emissions during this period.

1.3.1 Impact of Potential Cable Replacement Works

The proposed scheme will reduce or avoid the need for cable replacement and other maintenance works that are likely to be necessary to retain the Forth Road Bridge in use in the absence of a replacement crossing. These works on the Forth Road Bridge, extending over an anticipated eight year period, would have a significant impact on traffic congestion and routing and hence emissions that the air quality assessment reported. Avoiding the need for cable replacement, and the lengthy period of congested conditions associated with that work, would mean that total CO2 emissions during the congested peak periods for the proposed scheme are likely to be reduced.

Paramics / PHEM tests were undertaken to test the impact of main cable replacement works on the Forth Road Bridge which are anticipated to require contraflow restrictions on the existing bridge for 268 weeks over 8 years between 2012 and 2019 inclusive. The traffic conditions which will prevail for much of the time if the cable replacement is undertaken will be very different from the normal Do-Minimum conditions. Stop-start traffic will occur for longer periods in more locations under this scenario. Even allowing for a significantly reduced level of demand, the reduced capacity available on the Forth Road Bridge means that the average delay to vehicles will increase by around 40 minutes per journey, compared with normal un-restricted travel.

In order to provide a comparison of the local impacts of the cable replacement works on CO2 emissions, similar equivalent tests were undertaken by applying the same demand to the unrestricted base network. The demand applied to both networks equates to 70% of base (2008) levels of demand. Interpeak emissions have not yet been assessed. The peak period tests also do not take account of the effects of the likely increased vehicle kms and increased congestion on competing crossings and approach routes caused by diverting traffic.

The assessed annual emissions are summarised in Table 4 below and are presented as negative numbers as they represent an impact which could be avoided by building the proposed scheme.

Table 4: Indicative Cable Replacement Impact

Modelled Period

Modelled CO2(e) difference (Tonnes)

Annualisation Factor*

CO2(e) difference per annum (Tonnes)

AM (4 hours)

-20.5

167.5

-3,434

PM(4 hours)

-12.9

167.5

-2,161

Total

-33.4

-5,595

* Annualisation Factor assumes 5 weekdays and 33.5 weeks per year.

The results in Table 4 indicate that the MCR works are likely to result in an increase in CO2 emissions owing to an increase in congestion during the works. If the proposed scheme were implemented then this increase in emissions from the MCR works would potentially be avoided. Therefore an indication of the annual net impact of the proposed scheme on CO2 emissions can be calculated by taking the standard assessment forecast increase in emissions owing to the proposed scheme and then subtracting the predicted local area increase in emissions that would be expected during the period of the cable replacement works.

The graph below (Figure 1) indicates the cumulative effect of the forecast changes in CO2 emissions using this approach. As can be seen in this illustration, up to 2016, there is a net decrease in CO2 emissions, this continues until 2019 at a lower rate as the increase in CO2 from the proposed scheme cancels much of the reduction. After 2019 the cable replacement would be complete and hence the CO2 emissions from the proposed scheme would now be higher than the Do-Minimum. However, there is a cumulative net saving in CO2 emissions until 2025. Therefore the predicted increase in CO2 emissions is delayed until 2025 by the implementation of the proposed scheme. It should be noted that the MCR impacts are derived from identical traffic demand in both the MCR modelling and the comparator Do-Minimum modelling. Therefore, only the impact of network changes are taken into account. The Managed Crossing Scheme impact, indicated in Chapter 15 (Air Quality) of the ES and presented in the graph, includes both the effect of network changes and the effect of additional traffic demand in the Do-Something scenario.

Figure 1: Indicative cumulative change in CO2(e)

Figure 1: Indicative cumulative change in CO2(e)

The data in Figure 1 illustrate that emissions during the congested peak periods for the proposed scheme are likely to be less than the Do-Minimum (including cable replacement) over the period 2012 to 2025. This assessment excludes the additional benefits that may result from avoiding delays and increased emissions within the interpeak periods due to cable replacement works. Further work will investigate these impacts.

1.3.2 Scheme Features to Reduce CO2 emissions

In terms of impacts from vehicles using the crossing, the FRC scheme includes a number of features aimed at reducing CO2 emissions. These include:

  • use of Intelligent Transport Systems to improve network efficiency and decrease congestion;
  • infrastructure to facilitate modal shift, particularly through the provision of a dedicated public transport corridor on the FRB and associated public transport public transport lanes and public transport links; and
  • encouraging and facilitating active modes of transport (e.g. cycling) by minimising impacts on paths and cycle routes and improving these where feasible.

1.4 CEEQUAL

The Civil Engineering Environmental Quality and Awards Scheme (CEEQUAL) is an assessment and awards scheme for improving sustainability in civil engineering projects being promoted by the Institution of Civil Engineers and others. Its objective is to encourage the attainment of environmental excellence in civil engineering projects, and thus deliver improved environmental and social performance in project specification, design and construction.

The Forth Replacement Crossing is pursuing accreditation with CEEQUAL. The issue of energy and carbon forms component of the overall assessment.

1.5 Scheme Description

The FRC is a major infrastructure project comprising a new cable-stayed bridge across the Firth of Forth with associated new road connections and improved road infrastructure to the north and south. A description of the project is provided in Section 1.1.2 of the Sustainability Appraisal and Carbon Management Report. Additional detail can be found in the DMRB Stage 3 Scheme Assessment Report (Jacobs Arup 2009a) and Chapter 4 of the ES (Jacobs Arup 2009b).

2 Methodology

2.1 Introduction

The Sustainable Development Policy sets out the key sustainability principles and objectives which form a core thread throughout all the activities of the project team and stages in the project life cycle. Reducing the environmental impacts of the scheme, including lowering the carbon footprint, is integral to this policy.

An energy and carbon assessment has been established for the scheme, and this will be used as a tool for several purposes:

  • for comparing scheme options;
  • for driving innovation within the scheme design;
  • for use in reviewing tender proposals from potential contractors; and
  • for monitoring and measuring efficiencies.

2.2 Highways Agency Carbon Accounting Tool

The Highways Agency (HA) Carbon Accounting Tool (HA 2008; HA 2009) has been developed with reference to existing carbon accounting methodologies and information from the Environment Agency, Department of Environment, Food and Rural Affairs (DEFRA) and the International Organization for Standardization, and has drawn upon recognised best practice. The overall scope of the Accounting Tool is to cover all operations and activities over which HA has control, defined in terms of financial or contractual commitments for which HA is ultimately responsible. This includes responsibility for the greenhouse gas emissions produced by its supply chain when they are undertaking business on behalf of the Agency.

As such, the model can be used to capture emissions from power consumption, fuel usage, resources consumed and discarded, and the embodied energy elements associated with extraction, manufacture, production, installation, and transportation of all elements utilised on behalf of the Agency. The HA Carbon Accounting Tool (HA 2008; HA 2009) can be used to create a carbon footprint for all aspects of the FRC construction project as well as for the ongoing maintenance operations required.

2.2.1 Emissions Calculation Approach

Emissions are calculated by applying documented emission factors that convert a measure of activity from an emissions source into a volume of greenhouse gases (GHG) emissions. Emissions are reported as CO2 (rather than CO2e or carbon equivalent as per DEFRA guidance, refer to section 7). An example calculation is included below:

Measure of activity X Emissions Factor = Emission Estimate

100 tonnes of steel X 1.77 tCO2/t = 177 tCO2

Where tCO2 = tonnes of CO2

2.2.2 Key Data Sources

Identified below are the key published data sources referred to within the HA Carbon Accounting Tool (HA 2008; HA 2009) to provide the majority of emission factors.

  • Guidelines to DEFRA’s GHG Conversion Factors for Company Reporting – Annexes, (DEFRA 2007a).
  • Inventory of Carbon and Energy (University of Bath 2007).
  • Carbon Calculator for Construction Activities (Environment Agency 2007).

Assumptions and uncertainties are an inherent part of the carbon footprinting process as is the recognition that there are limitations in the data available. Future developments and clarifications will help to refine the assessment as the project progresses.

2.3 Inventory of Carbon and Energy

The Inventory of Carbon and Energy (ICE) Version 1.6a is the University of Bath’s embodied energy and embodied carbon database, and is a freely available summary of the larger ICE-Database (University of Bath 2008). It provides an inventory of embodied energy and carbon coefficients for building materials. The data has been collected from secondary sources in the public domain (journal articles, books, conference papers, etc). The report is structured into 34 main material groups (i.e. aggregates, metals etc) with a material profile created for each main material.

The Inventory of Carbon and Energy report provide the following explanatory note, defining the term ‘embodied energy’:

"The embodied energy (carbon) of a building material can be taken as the total primary energy consumed (carbon released) over its life cycle. This would normally include (at least) extraction, manufacturing and transportation. Ideally the boundaries would be set from the extraction of raw materials (including fuels) until the end of the products lifetime (including energy from manufacture, transport, energy to manufacture capital equipment, heating and lighting of factory, maintenance, disposal…etc), known as ‘Cradle-to-Gate’, which includes all energy (in primary form) until the product leaves the factory gate. The final boundary condition is ‘Cradle-to-Site’, which includes all of the energy consumed until the product has reached the point of use (i.e. building site)."

Boundary conditions for each material are specified within the material profiles. Cradle-to-Gate is the boundary condition most commonly specified in the report. Users are encouraged to consider the impacts of transportation for their specific case. In a few cases Cradle-to-Grave has been specified due to the original data resources.

The Inventory of Carbon and Energy contains both embodied energy and carbon data1, but the embodied energy coefficients carry a higher accuracy. One of the main reasons for this is that the majority of the collected data was for embodied energy, not embodied carbon. Many of the embodied carbon coefficients within ICE were estimated by the authors based on the typical fuel mix in the relevant UK industries. There are, however, uncertainties associated with this method of determining embodied carbon as a result of different fuel mixes and technologies (i.e. electricity generation). For example, two factories could manufacture the same product, resulting in the same embodied energy per kilogram of product produced, but the total carbon emitted by both could vary widely dependent upon the mix of fuels consumed by the factory.

Even with the most reliable data, embodied energy and carbon analysis carries a natural level of uncertainty. The ICE database has proved to be robust when compared with other similar inventories.

2.3.1 Selection Criteria

The embodied energy and carbon coefficients selected for the ICE database were representative of typical construction materials employed in the British market. In the case of metals, the values for primary and recycled materials were first estimated, and then a recycling rate (and recycled content) was assumed for the metals typically used in the marketplace. This enabled an approximate value for embodied energy in industrial components to be determined.

2.3.2 Transport

Boundary conditions within the Inventory of Carbon and Energy are selected as cradle-to-gate. Transport from factory gate to construction site is not therefore included. Emissions associated with transport must be calculated separately. Section 7 considers emissions associated with transport of materials to site. The Sustainable Resource Framework also addresses material sourcing and sets targets to source materials locally where possible.

2.3.3 Recycling Methodology

The Inventory of Carbon and Energy recycling methodology is known as the recycled content approach. However, the metal industries endorse a methodology known as the substitution method. Each method is fundamentally different. The recycled content approach is a method that credits recycling, whereas the substitution method credits recyclability.

The Inventory of Carbon and Energy considers the recycled content approach most suitable for the construction industry. The substitution method may run the risk of under accounting for the full impacts of primary metal production.

2.3.4 Advisory Notes

  • Functional units: It is inappropriate to compare materials solely on a kilogram basis. A comparative study should consider the quantity of materials required to provide a set function. It is only then that two materials can be compared for a set purpose.
  • Lifetime: Ideally the functional unit should consider the lifetime and durability of the product.
  • Waste: The quantity of waste generated from the production of materials must be considered. This should include analysis of what happens to the wasted materials, whether they are re-used, recycled or disposed of to landfill.
  • Maintenance: The maintenance requirements and the impact this has on energy and material consumption needs to be considered.

3 Initial Carbon Footprint Assessment

3.1 Purpose

During DMRB Stage 2, a carbon footprinting exercise was carried out to provide a high-level comparison of the carbon emissions associated with two scheme alternatives for the proposed Forth Replacement Crossing as defined in the Scheme Definition Report (Jacobs Arup 2009g).

A brief overview of the characteristics of the two schemes is provided in Table 5 below:

Table 5: Characteristics of the two scheme alternatives

Replacement Bridge Scheme (FS2)

Managed Crossing Scheme (MG2)

  • Extensive new road network and associated earthworks
  • Three-corridor main crossing (orthotropic cable-stayed bridge with twin concrete box girder approach viaducts) with separate provision for public transport
  • No refurbishment of existing Forth Road Bridge (FRB)
  • Less extensive road network and associated earthworks
  • Two-corridor main crossing (orthotropic cable-stayed bridge with twin concrete box girder approach viaducts) with no separate provision for public transport
  • Refurbishment of FRB to allow use by public transport

3.2 Limitations

The components of the scheme alternatives that were included in the carbon assessment were limited to those that could be reasonably estimated at that stage of the project. Included in this early assessment were estimates of the types and amounts of construction materials to be used in the new road network, main crossing and refurbishment of the Forth Road Bridge (for MG2 only). However, it was not possible at Stage 2 to include:

  • accurate estimates of the likely energy required for other aspects of the construction such as the use of plant and equipment or the removal of waste from site; and
  • emissions associated with the operation of the Forth Replacement Crossing i.e. vehicle usage and bridge maintenance.

3.3 Methodology and Scope

The carbon footprint assessment was based on the information contained in the Highways Agency (HA) Carbon Accounting Tool for Major Projects (HA 2009). The HA model is described in Section 2.2 above.

The carbon footprint assessment for the two scheme alternatives was initially limited to the construction materials to be used in the schemes.

At Stage 3, the scope of the assessment was widened to include other aspects such as energy use, transportation of materials, waste generation. This assessment is presented from Section 4 onwards.

3.4 Presentation of Results

3.4.1 Data Gathering and Key Assumptions

(a) Road Network

(i) Option FS2

Pavement = 487,000 m2 of new construction and 148,000 m2 of overlay/inlay

Earthworks cut = 1,159,000 m3 and fill = 2,700,000 m3

(ii) Option MG2

Pavement = 254,000 m2 of new construction and 254,000 m2 of overlay/inlay

Earthworks cut = 628,000 m3 and fill = 340,000 m3.

(b) Main Crossing

(i) Option FS2

Three-corridor main crossing (orthotropic cable-stayed bridge with twin concrete box girder approach viaducts) with separate provision for public transport.

(ii) Option MG2

Two-corridor main crossing (orthotropic cable-stayed bridge with twin concrete box girder approach viaducts) with no separate provision for public transport.

(c) Future Refurbishment of existing Forth Road Bridge

Option MG2 only:

  • Ready mix concrete: high strength = 588 tonnes
  • Steel: general = 1,595 tonnes
  • Asphalt = 388 tonnes

3.4.2 Results

A summary of the results of the initial carbon footprinting exercise is provided in Table 6 and Figure 2 below:

Table 6: Summary carbon footprinting results comparing two scheme alternatives

Component

 

 

Embodied Carbon (tCO2)

FS2

MG2

tonnes CO2

Proportion of Scheme Carbon Footprint

Tonnes CO2

Proportion of Scheme Carbon Footprint

Road Network (main materials i.e. asphalt & aggregate to be used in construction of new pavement and overlay/inlay of existing pavement)

8,575

3%

5,029

3%

Earthworks associated with Road Network

62,873

25%

11,750

8%

Main Crossing (Orthotropic Cable-Stayed Bridge & Twin Concrete Box Girder Approach Viaducts)

180,947

72%

130,312

87%

Refurbishment of Existing FRB (main materials i.e. steel concrete & asphalt) to be used in refurbishment

0

0%

3,028

2%

TOTAL

252,395

 

150,119

 

Figure 2: Summary carbon footprinting results comparing two scheme alternatives

Figure 2: Summary carbon footprinting results comparing two scheme alternatives

Based on this analysis, it was calculated that Option FS2 would result in approximately 68% (102,000 tonnes) more embodied carbon than Option MG2:

  • for both options the Main Crossing represents the greatest proportion of the embodied carbon. The embodied carbon associated with the Main Crossing for FS2 is approximately 39% (52,000 tonnes) more than for MG2;
  • FS2 would entail more earthworks than for MG2 and this is reflected in the difference (approximately 51,000 tonnes) in embodied carbon for this component; and
  • the future refurbishment of the FRB (Option MG2) represents a very small proportion of embodied carbon (approximately 2%).

3.4.3 Sourcing Scenarios

Table 7 provides an illustration of how the different materials that would be used in the two FRC scheme alternatives contribute to their respective carbon footprint:

Table 7: Breakdown of carbon footprint by material type

Component

Proportion of Carbon Footprint

FS2 – Replacement Bridge Scheme

MG2 – Managed Crossing Scheme

Steel

48%

65%

Soil requiring import/export (earthworks)

30%

8%

Concrete

16%

22%

Asphalt

3%

1%

Quarried aggregate

2%

1%

Polymer membrane

1%

1%

From the above it can be seen that steel and concrete contribute the majority of the embodied carbon associated with construction materials to be used in either scheme, and that the earthworks, especially those associated with FS2, are also a major contributor. As such it is considered that the greatest potential "savings" in terms of the carbon emissions associated with the construction materials to be used in the project, irrespective of which scheme alternative is selected, will be made by concentrating on these key areas i.e. seeking out alternative materials or crossing designs that would use these key materials more efficiently.

In addition, some simple calculations have been carried out using the available data in order to illustrate how different sourcing scenarios would affect the carbon footprint of the crossing. For example, it has been calculated that:

  • sourcing all the steel locally rather than from further afield, could represent a carbon "saving" of over 6,000 CO2 on the transportation of that steel to site (approximately 2.6% of the overall footprint for FS2); and
  • using 100% recycled aggregate rather than using 100% freshly quarried aggregate could represent a savings of nearly 2,000 tonnes CO2 (approximately 0.75% of the overall footprint of FS2).

4 Embodied Energy and Carbon at Stage 3 Design

4.1 Introduction

Building on the high-level carbon footprinting exercise carried out at the initial design stage, a more detailed analysis was carried out as the design developed. This assessed the embodied energy and carbon associated with key materials and components to be used in the scheme. The analysis is based on energy and carbon coefficients extracted from the Inventory of Carbon and Energy database (University of Bath 2008) and the HA Carbon Accounting Tool (HA 2008; HA 2009). Annex A provides an inventory of energy and carbon coefficients used in the assessment.

The energy and carbon assessment divides the scheme into its main component parts, as shown in Figure 3. Material quantities were provided by each of the relevant design teams. This assessment is based on Stage 3 Design.

Figure 3: Main Component of the FRC scheme

Figure 3: Main Component of the FRC scheme

4.2 Road Connections

4.2.1 Roads Network

Table 8 presents a summary of embodied energy and carbon associated with materials to be used in the road network. These calculations are based on estimated material quantities and the application of appropriate energy and carbon values to give total embodied energy and carbon (details of energy and carbon factors are provided in Annex A).

Material quantities are based on Stage 3 Design. This assessment includes the use of asphalt material, quarried aggregates and the import of suitable fill material. Filter materials in drains (consisting of plastic pipes of varying diameters and filter stone) have not been included as material quantities are not available at this stage.

The energy and carbon assessment for the road network has been broken down into a number of components: the pavement; overlay; sub-base; capping, and fill material. The pavement and overlay consist of asphalt material, while the sub-base and capping is made up of aggregate material. Imported fill material consists of general aggregate material.

The total embodied energy associated with these materials is 342,794 GJ and the total embodied carbon is 8,701 tCO2. As shown in Table 8 the pavement accounts for approximately 67% of total embodied energy. The import of fill material makes up around 20%, the overlay around 8%, while the sub-base and capping account for 2% and 3% of the total respectively. Similarly, as shown in Figure 4, in terms of embodied carbon the pavement accounts for 46% of the total, the import of fill material 40%, the overlay 6%, and the sub-base and capping make up 3% and 6% respectively.

Table 8: Summary of the estimated embodied energy and carbon for road network

Component

Category

Material

Energy

Carbon

GJ

tCO2

Pavement

Quarry Sourced Material

General Asphalt

230,752

3,994

Overlay

General Asphalt

27,381

474

Sub-base

General Aggregate

5,221

261

Capping

General Aggregate

10,441

2,993

Import of fill

General Aggregate

69,000

3,450

Total

342,794

8,701

Figure 4: Percentage of embodied energy by component for road network

Figure 4: Percentage of embodied energy by component for road network

Figure 5: Percentage of embodied carbon by component for road network

Figure 5: Percentage of embodied carbon by component for road network

4.2.2 Land-Based Structures

Table 9 below gives a summary of embodied energy and carbon associated with materials to be used in the land-based structures. As before, the energy and carbon assessment is based on estimated material quantities and the application of appropriate energy and carbon values to give total embodied energy and carbon.

The assessment includes key materials associated with construction (i.e. concrete, steel, imported fill). Material quantities are based on Stage 3 Design.

The total embodied energy associated with materials to be used in the land-based structures is 536,890 GJ, and the total embodied carbon is 47,768 tCO2. As shown in Figure 6, steel accounts for approximately 70% of the total embodied energy, while concrete and imported fill make up around 25% and 5% respectively. In terms of embodied carbon, as shown in Figure 7, steel accounts for 54% of the total, while concrete and imported fill make up around 43% and 3% respectively.

Table 9: Summary of the estimated embodied energy and carbon for land-based structures

Category

Material

Energy

Carbon

GJ

tCO2

Concrete

Concrete: high strength

133,957

20,142

Precast concrete

1,754

189

Metals

Steel: bar & rod

193,036

13,418

Steel: section

179,883

12,606

Quarry Sourced Materials

General aggregate: Imported Fill

28,260

1,413

Total

536,890

47,768

Figure 6: Percentage of embodied energy in land-based structures by material type

Figure 6: Percentage of embodied energy in land-based structures by material type

Figure 7: Percentage of embodied carbon in land-based structures by material type

Figure 7: Percentage of embodied carbon in land-based structures by material type

4.3 Main Crossing

4.3.1 Substructure

Table 10 below gives a summary of embodied energy and carbon associated with materials to be used in the substructure of the Main Crossing. The energy and carbon assessment is based on estimated material quantities and the application of appropriate energy and carbon values to give total embodied energy and carbon.

The assessment includes key materials associated with construction (i.e. cement, steel, aggregate, sand, stone, and concrete). Material quantities are based on Stage 3 Design.

The total embodied energy associated with materials to be used in the substructure is 742,986 GJ, and the total embodied carbon is 56,448 tCO2. As shown in Figure 8 steel accounts for approximately 81% of the total embodied energy. Cement and concrete contribute around 7% each, while aggregate material, stone and sand account for the remaining 5%. As shown in Figure 9 steel accounts for around 72% of total embodied carbon, while cement makes up 14% and concrete 10%. Stone, sand, and aggregate material account for the remaining 4%.

Table 10: Summary of the estimated embodied energy and carbon for the substructure

Category

Material

Energy

Carbon

GJ

tCO2

Cements

Cement: general - 50% blast furnace slag

52,260

7,813

Metals

Steel: general2

397,410

25,791

Sheet piling: heavy use

208,986

15,160

Quarry Sourced Materials

Quarried aggregate

3,726

298

Recycled aggregate

582

34

Sand

2,264

113

Stone: general

27,060

1,515

Concrete

General Road and Pavement

39,614

4,057

High Strength

11,084

1,667

Total

742,986

56,448

Figure 8: Percentage of embodied energy in substructure by material type

Figure 8: Percentage of embodied energy in substructure by material type

Figure 9: Percentage of embodied carbon in substructure by material type

Figure 9: Percentage of embodied carbon in substructure by material type

Table 11 shows the labelling scheme for each element of the Main Crossing substructure. Table 12 shows embodied energy and carbon associated with each element of the substructure. SNTBP accounts for approximately 43% of total embodied energy, while ASC (Piled) and STP account for 28% and 10% respectively.

Table 11: Labelling of elements associated with the substructure

SNTBP

South and north tower bases

ASLPr

Approach span piers, S3 to S8 and N3

STP

South tower piles

ASMPr

Approach span piers, S1, S2, N1 and N2

NTP

North tower piles

ACS (Piled)

S1, S2, S3, S4, N1 pile caps and piles

CTB

Central tower base

ACS (Pad)

S5 to S8 and N2, pads

Table 12: Estimated embodied energy and carbon associated with each component of substructure

Structure

Embodied Energy GJ

Percentage of Total

Embodied Carbon (tCO2)

Percentage of Total

SNTBP

320,019

43%

23,701

42%

STP

76,074

10%

5,962

11%

NTP

61,815

8%

4,864

9%

CTB

33,585

5%

3,807

7%

ASC (Piled)

208,318

28%

14,408

25%

ASC (Pad)

16,557

2%

1,363

2%

ASMPr

11,151

2%

978

2%

ASLPr

15,467

2%

1,364

2%

Total

742,986

100%

56,448

100%

4.3.2 Superstructure

(a) Cable-Stayed Bridge Options

Table 13 and Table 14 present a summary of embodied energy and carbon associated with materials to be used in each of the options for the cable-stayed bridge. These calculations are based on estimated material quantities and the application of appropriate energy and carbon values to calculate total embodied energy and carbon. Details of energy and carbon factors are provided in Annex A.

The assessment includes key materials associated with construction (i.e. steel, concrete, asphalt, etc). Material quantities are based on Stage 3 Design.

The total embodied energy associated with materials to be used in the cable-stayed bridge - orthotropic is 1,257,089 GJ, and the total embodied carbon is 98,491 tCO2. As shown in Figure 10, steel accounts for approximately 92% of the total embodied energy, while concrete accounts for about 6% of the total. As shown in Figure 11 steel accounts for approximately 89% of the total embodied carbon, while concrete accounts for about 11%.

In comparison, the total embodied energy associated with materials to be used in the cable-stayed bridge - composite is 1,215,501 GJ, and the total embodied carbon is 100,044 tCO2. As shown in Figure 12 steel accounts for approximately 85% of the total embodied energy, while concrete accounts for about 12% of the total. As shown in Figure 13, steel accounts for approximately 78% of the total embodied carbon, while concrete accounts for about 21%.

Table 13: Estimated embodied energy and carbon for cable-stayed bridge - Orthotropic

Cable-Stayed Bridge - Single Deck Box Girder - Orthotropic

Category

Material

Energy

Carbon

GJ

tCO2

Metals

Steel: general (UK typical)

839,641

60,908

Steel: general (primary)

1,723

134

Steel: bar & rod (UK Typical)

115,915

8,058

Steel: bar & rod (Primary)

2,184

161

Steel: wire

133,956

10,530

Stainless steel

65,545

7,109

Misc

Paint

5,465

286

Quarry Sourced Materials

Asphalt

19,752

342

Concrete

Concrete (high strength)

72,908

10,962

Concrete (general road and pavement)

0

0

Total

1,257,089

98,491

Figure 10: Percentage of embodied energy in cable-stayed bridge by material type – orthotropic

Figure 10: Percentage of embodied energy in cable-stayed bridge by material type – orthotropic

Figure 11: Percentage of embodied carbon in cable-stayed bridge by material type – orthotropic

Figure 11: Percentage of embodied carbon in cable-stayed bridge by material type – orthotropic

Table 14: Estimated embodied energy and carbon for cable-stayed bridge - composite

Cable-Stayed Bridge - Single Deck Box Girder - Composite

Category

Material

Energy

Carbon

GJ

tCO2

Metals

Steel: general (UK typical)

571,607

41,465

Steel: general (primary)

1,757

137

Steel: bar & rod (UK Typical)

204,844

14,239

Steel: bar & rod (Primary)

2,184

161

Steel: wire

193,572

15,217

Stainless steel

65,545

7,109

Misc

Paint

3,953

207

Quarry Sourced Materials

Asphalt

32,224

558

Concrete

Concrete (high strength)

138,327

20,799

Concrete (general road and pavement)

1,488

152

Total

1,215,501

100,044

Figure 12: Percentage of embodied energy in cable-stayed bridge by material type - composite

Figure 12: Percentage of embodied energy in cable-stayed bridge by material type - composite

Figure 13: Percentage of embodied carbon in cable-stayed bridge by material type – composite

Figure 13: Percentage of embodied carbon in cable-stayed bridge by material type – composite

(b) Approach Viaduct Options

Table 15 and Table 16 present a summary of embodied energy and carbon associated with materials to be used in each of the options for the approach viaducts. As before, these calculations are based on estimated material quantities and the application of appropriate energy and carbon values to give total embodied energy and carbon.

The assessment includes key materials associated with construction (i.e. steel, concrete, asphalt, etc). Material quantities are based on Stage 3 Design.

The total embodied energy associated with materials to be used in the approach viaduct- composite is 249,815 GJ, and the total embodied carbon is 20,666 tCO2. As shown in Figure 14 steel accounts for approximately 83% of the total embodied energy, while concrete accounts for about 14% of the total. As shown in Figure 15 steel accounts for approximately 73% of the total embodied carbon, while concrete accounts for about 26%.

In comparison, the total embodied energy associated with materials to be used in the approach viaduct - concrete is 219,265 GJ, and the total embodied carbon is 20,588 tCO2. As shown in Figure 16 steel accounts for approximately 68% of the total embodied energy, while concrete accounts for about 28% of the total. As shown in Figure 17 steel accounts for approximately 54% of the total embodied carbon, while concrete accounts for about 45%.

Table 15: Estimated embodied energy and carbon for approach viaduct - composite

Approach Bridge - Twin Composite Box Girder

Category

Material

Energy

Carbon

GJ

tCO2

Metals

Steel: general (UK Typical

134,479

9,755

Steel: general (UK Primary)

1,271

99

Steel: bar & rod

57,807

4,018

Steel: wire

0

0

Stainless steel

12,315

1,336

Misc

Paint

699

37

Quarry Sourced Materials

Asphalt

8,046

139

Concrete

Concrete (high strength)

34,979

5,259

Concrete (general road and pavement)

218

22

Total

249,815

20,666

Figure 14: Percentage of embodied energy in approach viaduct by material type - composite

Figure 14: Percentage of embodied energy in approach viaduct by material type - composite

Figure 15: Percentage of embodied carbon in approach viaduct by material type – composite

Figure 15: Percentage of embodied carbon in approach viaduct by material type – composite

Table 16: Estimated embodied energy and carbon for approach viaduct - concrete

Approach Bridge - Twin Concrete Box Girder

Category

Material

Energy

Carbon

GJ

tCO2

Metals

Steel: general (UK Typical

27,650

2,006

Steel: general (UK Primary)

1,359

106

Steel: bar & rod

85,482

5,942

Steel: wire

23,030

1,810

Stainless steel

12,315

1,336

Quarry Sourced Materials

Asphalt

8,046

139

Concrete

Concrete (high strength)

61,164

9,197

Concrete (general road and pavement)

218

22

Total

219,265

20,558

Figure 16: Percentage of embodied energy in approach viaduct by material type - concrete

Figure 16: Percentage of embodied energy in approach viaduct by material type - concrete

Figure 17: Percentage of embodied carbon in approach viaduct by material type - concrete

Figure 17: Percentage of embodied carbon in approach viaduct by material type - concrete

4.4 Combination of Options for Main Crossing Superstructure

Table 17 and Table 18 present a summary of embodied energy and carbon associated with potential options for the Main Crossing superstructure. In terms of embodied energy, option 1 is highest with a total embodied energy of 1,506,904 GJ. Option 4 would have the lowest embodied energy, 1,434,766 GJ. The difference between highest and lowest is 72,138 GJ, or approximately 5%.

In terms of embodied carbon, option 2 is highest with a total embodied carbon of 120,710 tCO2. Option 3 would have the lowest embodied carbon, 119,049 tCO2. The difference between highest and lowest is 1,661 tCO2, or approximately 1.4% which is considered to be minimal.

Table 17: Summary of estimated embodied energy associated with combination of options for the main crossing superstructure

Cable-Stayed Bridge

Orthotropic

Composite

Embodied Energy (GJ)

Approach Viaduct

Composite

Option 1) 1,506,904

Option 2) 1,465,316

Concrete

Option 3) 1,476,353

Option 4) 1,434,766

Table 18: Summary of estimated embodied carbon associated with combination of options for the main crossing superstructure

Cable-Stayed Bridge

Orthotropic

Composite

Embodied Carbon (tCO2)

Approach Viaduct

Composite

Option 1) 119,157

Option 2) 120,710

Concrete

Option 3) 119,049

Option 4) 120,602

4.5 Embodied Energy and Carbon Summary

Table 19 provides a summary of total embodied energy and carbon for each component of the scheme. In the case where Option 1 is chosen for the Main Crossing superstructure, the total embodied energy for the scheme would be 3,129,574 GJ and the total embodied carbon would be 232,074 tCO2.

The Main Crossing superstructure (cable-stayed bridge and approach viaduct) makes up the greatest proportion of total embodied energy and carbon. In the case where Option 1 above is chosen, the main crossing superstructure would account for approximately 48% of the overall embodied energy of the scheme. Under this scenario, the main crossing substructure would account for around 24% of total embodied energy, while land-based structures and the road network would make up 17% and 11% respectively.

Figure 18 provides a summary of total embodied energy for each component of the scheme, with Option 1 selected for the superstructure. Similarly, Figure 18 provides a summary of total embodied carbon for each component of the scheme.

Table 19: Summary of the estimated total embodied energy and carbon for each component of the scheme

Component

Energy

Carbon

GJ

tCO2

Road Network

342,794

8,701

Land-Based Structures

536,890

47,768

Main Crossing Substructure

742,986

56,448

Main Crossing Superstructure

Option 1

1,506,904

119,157

Option 2

1,465,316

120,710

Option 3

1,476,353

119,049

Option 4

1,434,766

120,602

Figure 18: Summary of the estimated total embodied energy and for each component of the scheme (under option 1 for main crossing)

Figure 18: Summary of the estimated total embodied energy and for each component of the scheme (under option 1 for main crossing)

Figure 19: Summary of the estimated total embodied carbon and for each component of the scheme (under option 1 for main crossing superstructure)

Figure 19: Summary of the estimated total embodied carbon and for each component of the scheme (under option 1 for main crossing superstructure)

Table 20 and Table 21 below give a summary of embodied energy and carbon broken down by material type for each component of the scheme. In the case where Option 1 is chosen for the main crossing superstructure, steel accounts for approximately 75% of total embodied energy. Quarry sourced materials (aggregates, stone, asphalt, etc) make up around 14% of total embodied energy, while cement and concrete account for around 11% and paint accounts for less than 1% of the total.

In terms of carbon, again assuming Option 1 is chosen, steel accounts for approximately 73% of total embodied carbon. Quarry sourced materials make up around 5% of total embodied carbon, while cement and concrete account for around 22% and paint accounts for less than 1% of the total.

Table 20: Summary of the estimated embodied energy by material type for each component of the scheme

Category

Material Type

Embodied Energy (GJ)

Road Network

Structures

Substructure

Main Crossing

Option 1

Option 2

Option 3

Option 4

Cement

Cement: general - 50% blast furnace slag

 

 

52,260

 

 

 

 

Metals

Steel: general (UK typical)

 

 

397,410

974,120

706,086

867,291

599,257

Steel: general (primary)

 

 

 

2,993

3,027

3,082

3,116

Steel: bar & rod (UK Typical)

 

193,036

 

173,722

262,651

201,397

290,326

Steel: bar & rod (Primary)

 

 

 

2,184

2,184

2,184

2,184

Steel: section

 

179,883

 

 

 

 

 

Steel: wire

 

 

 

133,956

193,572

156,986

216,602

Steel: stainless

 

 

 

77,860

77,860

77,860

77,860

Sheet piling: heavy use

 

 

208,986

 

 

 

 

Misc

Paint (Average)

 

 

 

6,165

4,652

5,465

3,953

Quarry Sourced Materials

Quarried aggregate

 

 

3,726

 

 

 

 

Recycled aggregate

 

 

582

 

 

 

 

General aggregate

84,662

28,260

 

 

 

 

 

Asphalt

258,132

 

 

27,798

40,271

27,798

40,271

Sand

 

 

2,264

 

 

 

 

Stone: general

 

 

27,060

 

 

 

 

Concrete

General Road and Pavement

 

 

39,614

218

1,706

218

1,706

High Strength

 

133,957

11,084

107,888

173,307

134,072

199,491

Prefabricated Concrete

 

1,754

 

 

 

 

 

Total

342,794

536,890

742,986

1,506,904

1,465,316

1,476,353

1,434,766

Table 21: Summary of the estimated embodied carbon by material type for each component of the scheme

Category

Material Type

Embodied Carbon (tCO2)

Road Network

Structures

Substructure

Main Crossing

Option 1

Option 2

Option 3

Option 4

Cement

Cement: general - 50% blast furnace slag

 

 

7,813

 

 

 

 

Metals

Steel: general (UK typical)

 

 

25,791

70,664

51,220

62,914

43,471

Steel: general (primary)

 

 

 

233

236

240

243

Steel: bar & rod (UK Typical)

 

13,418

 

12,076

18,257

14,000

20,181

Steel: bar & rod (Primary)

 

 

 

161

161

161

161

Steel: section

 

12,606

 

 

 

 

 

Steel: wire

 

 

 

10,530

15,217

12,341

17,027

Steel: stainless

 

 

 

8,445

8,445

8,445

8,445

Sheet piling: heavy use

 

 

15,160

 

 

 

 

Misc

Paint (Average)

 

 

 

323

244

286

207

Quarry Sourced Materials

Quarried aggregate

 

 

298

 

 

 

 

Recycled aggregate

 

 

34

 

 

 

 

General aggregate

4,233

1,413

 

 

 

 

 

Asphalt

4,468

 

 

481

697

481

697

Sand

 

 

113

 

 

 

 

Stone: general

 

 

1,515

 

 

 

 

Concrete

General Road and Pavement

 

 

4,057

22

175

22

175

High Strength

 

20,142

1,667

16,222

26,058

20,159

29,995

Prefabricated Concrete

 

189

 

 

 

 

 

Total

8,701

47,768

56,448

119,157

120,710

119,049

120,602

5 Carbon Emissions Associated with Earthworks

5.1 Maximising the Cut and Fill Balance

An earthworks strategy has been developed for the proposed scheme that reviews the earthworks material available on site, potential sources of imported material, the earthworks balance, options available for improving the earthworks balance and the impact that the proposed construction programme will have on the earthworks balance. Attention has been paid to earthworks geometry, such as flat slopes to allow lower grade material to be used in fill or steepened slopes with reinforcement, soil nails or reinforced embankments, in an attempt to reduce cut and fill quantities and to minimise the need to import or export fill to and from the site.

The earthworks strategy has allowed the development of the Stage 3 design and will be further developed to aid the final design within the constraints of the EIA and ES, minimising both the volume of imported material required and the surplus destined for disposal.

The import of fill material has been taken account within the carbon footprint calculations presented in Section 4.2 above, where earthworks fill materials have been referred to as ‘general aggregate’. The emission factor for general aggregate was selected as the most appropriate in view of the nature of the earthworks materials likely to be handled.

Notwithstanding the efficiency gains that will be generated by the cut and fill balance, it is estimated that there will be a certain quantity of material that will be unusable and will therefore need to be disposed of and the implications of this to the carbon footprint is covered in Section 5.2 below.

5.2 Export of Unacceptable Earthwork Material

Table 22 provides estimated quantities of earthwork materials to be exported from site. These quantities are based on Stage 3 Design. In total, it is estimated that 115,000m3 of material would be removed from site (refer to Chapter 4 of the ES). Note that this does not include potential material exported for land-based structures.

Table 22: Estimated quantities of earthwork materials to be removed from site (Stage 3 Design)

 

M9 Junction 1a

Queensferry Junction

Ferrytoll Junction

Estimated Export (m3)

20,000

55,000

40,000

N.B. These quantities do not include potential export of material for structures

Table 24 provides an estimate of the carbon emissions associated with the removal of this waste material from site. It is estimated that the waste is transported on average 35km from site (refer to Table 23).

The emissions factor for transport is taken from the HA Accounting Tool (HA 2008; HA 2009). The calculations indicate that the removal of waste earthwork materials from site results in the emission of an estimated 2,555 tCO2.

Table 23: Potential material disposal (landfill) sites and estimated distance

Name

Estimated Distance (km)

Binn Farm Landfill

39.9

Avondale Landfill

21.1

Avondale Hazardous Landfill

21.1

West Carron Landfill

31.0

Lochhead Landfill Site

13.7

Oatslie Sandpit Landfill

31.7

Levenseat Landfill

37.5

Greengairs Landfill

56.6

Greenoakhill Landfill

56.5

Average

35.0

Table 24: Carbon emissions associated with the removal of waste earthworks material from site

Category

Material

Mass (tonnes)

Average waste removal distance (km)

Road Transport (tCO2/t.km)

Carbon (tCO2)

Waste removal

Inert waste

230,000*

35.0

0.0003174

2,555

* Assumed 2.0 tonnes per m3

6 Options to Reduce Embodied Energy and Carbon

6.1 Use of Recycled Aggregate

As well as maximising the earthworks cut and fill balance which can make a positive contribution to reducing the carbon footprint of the scheme, there may be further potential for reducing embodied energy and carbon associated with the road network by using recycled aggregate from other local sources, where this is appropriate, instead of quarried aggregate.

Table 25: Comparison of carbon values for recycled and quarried aggregate

Type of Material

Embodied Carbon Value (tCO2/t)

Recycled Aggregate

0.00369

Quarried Aggregate

0.00800

Table 25 above compares embodied carbon values for recycled and quarried aggregate. These values are taken directly from the Highways Agency Carbon Accounting Tool (HA 2008; HA 2009). Based on these values, it is estimated that the carbon intensity of recycled aggregate is 54% lower compared to quarried material.

Transport is likely to be significant for aggregates and the proximity of material sources and method of transport to site could have a greater overall influence on energy and carbon.

There is likely to be a large volume of material generated on site from rock cuts and from quarrying the existing roads that could be processed and re-used on site for capping, sub-base and a percentage of road-base. An earthworks strategy has been developed for the proposed scheme which reviews the earthworks material available on site, potential sources of imported material, the earthworks balance, and options available for improving the earthworks balance. The earthworks strategy will aid the final design and help to minimise both the volume of imported material required and the surplus destined for disposal.

As reported in Section 4.13.2 of the Sustainability Appraisal and Carbon Management Report, earthworks materials will be sourced locally where appropriate with the aim of reducing haulage distance for imported fill and for exported material.

6.2 Using Recycled Steel

Table 26 shows embodied energy and carbon values associated with steel materials from different sources. Values are given for steel from primary sources, secondary sources, and for the market average.

The embodied energy and carbon of steel from secondary sources is approximately 75% lower than that from primary sources (on a tonne for tonne basis). This shows that there may be significant savings to be made (in terms of a reduction in embodied energy and carbon) by using an increased proportion of recycled steel in the project where this is appropriate, as steel accounts for a major proportion of the overall embodied energy and carbon. However, other sustainability factors should also be considered, such as durability and the life span of products, maintenance requirements, performance, and ability to re-use materials after decommissioning.

Table 26: Comparing embodied energy and carbon values for steel

Material

Embodied Energy (MJ/kg)

Embodied Carbon Kg CO2/Kg

UK Typical

Primary

Secondary

UK Typical

Primary

Secondary

General Steel

24.4

35.3

9.5

1.77

2.75

0.43

Bar and Rod

24.6

36.4

8.8

1.71

2.68

0.42

7 Carbon Emissions Associated with Transport of Materials

7.1 Introduction

This section examines emissions of carbon associated with the transport of materials to site. Emissions from transport will depend on: a) the quantity of material to be transported; b) where the material is sourced from (i.e. distance to site); and c) the predominant mode of transport used.

Table 27 provides carbon emissions values associated with different modes of transport. These values are taken from DEFRA’s published GHG conversion factors (DEFRA 2009b) and are expressed in terms of kg CO2e (carbon equivalent) emitted in order to transport one tonne of material a distance of one kilometre. Please note that all DEFRA guidance uses the unit CO2e (carbon equivalent), rather than just CO2 as used in the HA model above (refer to Section 2.2).

Table 27: Carbon emission values associated with transport of materials to site (DEFRA 2009b)

Mode of Transport

Carbon Emissions (kg CO2e/tonne.km)

Articulated HGV (UK average)

0.0860

Rail Freight

0.0319

Shipping (Large bulk carrier)

0.0071

7.2 Illustrative Sourcing Scenarios

For the purposes of this illustrative exercise the following four sourcing scenarios for steel are considered:

Option 1) All steel sourced a distance of 400 km from site and transported by rail to site

Option 2) All steel sourced a distance of 400 km (approximate distance Edinburgh to Sheffield) from site and transported by road to site

Option 3) All steel sourced from Rotterdam, the Netherlands, (approximately 730km3) and transported by sea to site

Option 4) All steel sourced from China (approximately 17,000 km4) and transported by sea to site

The results are summarised below in Table 28. These calculations are for emissions associated with transport only. Emissions associated with embodied carbon (i.e. carbon produced during extraction, processing and manufacture) are not shown in Table 28 (as estimated in Section 4 above, total embodied carbon associated steel is approximately 170,000 tCO2).

Table 28: Carbon emissions associated with the different sourcing options

Material

Total Mass of Steel Material (tonnes)

Carbon Emissions associated with Transport (tCO2e)

Option 1

Option 2

Option 3

Option 4

Steel

90,000

1,148

3,096

466

10,863

Of the three options, Option 3 would result in the lowest amount of CO2e being emitted, while Option 4 would result in the highest. Option 4 is over 23 times more carbon polluting than Option 3. Choosing option 3 over option 4 would result in a carbon ‘saving’ of 10,397 tCO2e.

Please note, material quantities are provisional only at this stage and are based on currently available estimates provided by the Design Team. Material quantities will also vary depending on the type of design selected for the Main Crossing. For this exercise, material quantities were based on the selection of the orthotropic option for the cable-stayed bridge and the composite option for the approach viaduct.

Carbon emissions associated with the transport of steel materials to site are relatively low compared to the embodied carbon content in steel (estimated to be between 1% to 5%). Steel has a high embodied energy and carbon content and accounts for a major proportion of the overall ‘footprint’ of the scheme.

8 The Shadow Price of Carbon

8.1 Introduction

In 2007 DEFRA published revised guidance on how to value greenhouse gas emissions in government appraisals (DEFRA 2007b). This is for use in all policy and project appraisals across government with significant effects on carbon emissions. The guidance adopts the concept of the Shadow Price of Carbon (SPC) as the basis for incorporating carbon emissions in cost-benefit analysis and impact assessments.

The shadow price of carbon (SPC) is used to value the expected increase or decrease in emissions of greenhouse gas emissions resulting from a proposed policy. Put simply, the SPC reflects the damage costs of climate change caused by each additional tonne of greenhouse gas emitted – converted into carbon dioxide equivalent (CO2e) for ease of comparison. The value of the shadow price of carbon used in this report is based on DEFRA guidance of 2007. It should however be noted that since undertaking this exploratory work a recent update on carbon valuation has been produced by the Department of Energy and Climate Change (DECC) - Carbon Valuation in UK Policy Appraisal: A Revised Approach Climate Change Economics, Department of Energy and Climate Change July 2009 (DECC 2009). Future work on carbon valuation will reflect the changes introduced in this revised approach.

The SPC is different from the previously used social cost of carbon (SCC) in that it takes more account of uncertainty and is based on a stabilisation trajectory. Including the benefits of lower CO2e emissions from a policy designed to reduce them (or a policy with a different objective that also reduced CO2e as a co-benefit) in the policy’s appraisal would make the policy relatively more attractive - either in comparison to alternatives with worse CO2e impacts, or by increasing the scale of the benefits relative to costs. Accounting for such environmental benefits aids ‘green’ policy-making.

Similarly, valuing the additional CO2e emitted by a policy would add to its overall costs and make it a relatively less attractive option than one with lower additional CO2e emissions (or indeed CO2e savings). It is possible that including the monetised value of a policy that increases CO2e emissions may even switch the balance of costs and benefits so that the costs outweighed the benefits.

8.2 Methodology

DEFRA has produced guidance on how to value greenhouse gas emissions in government appraisal. This guidance is outlined below in four steps:

Step 1: Quantify the impact of greenhouse gas emissions, giving the figures in tonnes of carbon dioxide equivalent

Set out the exact quantity of carbon dioxide – or CO2 equivalent – the policy is expected to save/emit each year in a spreadsheet. This should be a net change from an assumed baseline rate of emissions. The assumed baseline are emissions in the absence of the policy.

Step 2: Calculate the correct schedule of the Shadow Price of Carbon to use and set it alongside the quantities of greenhouse gas saved

  • The value of the Shadow Price of Carbon (SPC) is dependent upon the year the carbon is abated/emitted.
  • In the year 2000, in year 2000 prices the SPC is set to £19 per tonne CO2e.
  • The SPC rises over time for two reasons:
  • to account for observed (and assumed) inflation; and
  • increasing by 2 per cent per year to account for rising damage costs from higher greenhouse gas concentrations.
  • Do not use the same value of the SPC for each year. Use the tables below to find the SPC for each year of your policy, i.e. a SPC schedule. Alternatively, use the tables to find the SPC in the start year of the policy, then add 2% per year to it.

Table 29: SPC from 2007 to 2050 (in 2009 prices) (adapted from DEFRA 2007b)

Year

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

SPC in 2009 prices and with 2% pa increases (£)

26.5

27.1

27.6

28.2

28.7

29.3

29.9

30.5

31.1

31.7

32.3

33.0

 

2019

2020

2021

2022

2023

2024

2025

2026

2027

2028

2029

2030

2031

2032

2033

2034

33.6

34.3

35.0

35.7

36.4

37.1

37.9

38.6

39.4

40.2

41.0

41.8

42.7

43.5

44.4

45.3

 

2035

2036

2037

2038

2039

2040

2041

2042

2043

2044

2045

2046

2047

2048

2049

2050

46.2

47.1

48.1

49.0

50.0

51.0

52.0

53.1

54.1

55.2

56.3

57.4

58.6

59.8

60.9

62.2

  • All values of the SPC listed in Table 29 are in 2009 prices. These values have been adjusted from DEFRA’s guidance on greenhouse gas pricing (DEFRA 2007b). For policies appraised in other years or using another year’s price level (which may be appropriate if other costs and benefits are in a different year’s price level), the SPC must be adjusted.

Step 3: Multiply each year’s quantity of greenhouse gas emissions abated/emitted (expressed in CO2e) by that year’s Shadow Price of Carbon

  • The spreadsheet should already have each year of the policy’s greenhouse gas emissions (expressed in CO2e), and a SPC schedule. Multiply these year by year.

Step 4: Use the monetised greenhouse gas values in your cost-benefit analysis

  • Continue appraising the policy according to Green Book guidance. This includes showing the Net Present Value (NPV) of the carbon impacts in isolation and as part of the overall NPV. It also includes performing sensitivity analysis around the carbon impacts in the same way undertaken for other costs and benefits.
  • During sensitivity analysis look out for whether a ±5% change in the SPC would turn a NPV positive policy into NPV negative, or visa versa, or where a higher or lower SPC would change the ranking of different policy options. If this is the case, it should be made clear in the appraisal, and borne in mind in the recommendation.
  • Make all assumptions clear in the analysis and Impact Assessment. The policy appraisal must at least state the quantity of greenhouse gases and the value of these (i.e. quantity multiplied by the SPC).

General guidance on greenhouse gas policy appraisal can be found on the DEFRA website. This includes papers on the SPC, which give more detail on the rationale for using SPC and the theoretical background.

8.3 Illustrative Example

The following exercise provides an illustrative example of how the shadow price of carbon could be accounted for during project appraisal. Two scenarios are presented:

  • ‘Scenario 1’ where the option for the main crossing includes an orthotropic steel deck and steel is sourced from Rotterdam (730 km) and transported to site by sea; and
  • ‘Scenario 2’ where the option for the main crossing includes a composite deck and steel is sourced from China (17,000 km) and transported to site by sea.

Table 30: Comparison of embodied carbon associated with four different options for the Main Crossing and approach viaduct

Cable-Stayed Bridge

Orthotropic

Composite

Embodied Carbon (tCO2)

Approach Viaduct

Composite

119,157

120,710

Concrete

119,049

120,602

Table 31: Comparison between the ‘Best Case’ and ‘Worst Case’ scenarios for carbon emissions

Scenario 1 (tCO2)

Scenario 2 (tCO2)

Embodied Carbon

119,049

120,710

Transport of Steel

466

10,863

Total

119,515

131,573

Based on the above analysis, opting for Scenario 1 over Scenario 2 would result in a carbon ‘saving’ of:

  • 131,573 – 119,515 = 12,058 tCO2e

8.4 Monetising Carbon

Best practice guidance adopts the concept of the Shadow Price of Carbon (SPC) as the basis for incorporating carbon emissions in cost-benefit analysis and impact assessments. The SPC reflects the damage costs of climate change caused by each additional tonne of greenhouse gas emitted – converted into carbon dioxide equivalent (CO2e) for ease of comparison. This allows efficiency in design leading to a reduction in embodied carbon to be monetised at a current value.

9 Conclusions

9.1 Background and Purpose

The Forth Replacement Crossing Sustainable Development Policy (refer to Appendix 1) sets out the key sustainability principles and objectives which form a core thread throughout all the activities of the project team and stages in the project life cycle. Reducing the environmental impacts of the scheme, including lowering the carbon footprint, is integral to this policy.

9.2 Approach

This energy and carbon assessment is based on information contained in the Highways Agency Carbon Accounting Tool (HA 2008; HA 2009). Other key sources of data include the Inventory of Carbon and Energy produced by the University of Bath (University of Bath 2008) and DEFRA’s GHG conversion factors (DEFRA 2008). Estimated quantities of construction materials to be used in the scheme were provided by the relevant project design teams. The impact of scheme in terms of carbon emissions associated with vehicles using the crossing is discussed within the Chapter 15 (Air Quality) of the ES.

9.3 Results of Embodied Energy and Carbon Assessment

During the early stages of the project design an initial high-level carbon footprinting exercise was carried out to provide a high-level comparison of the carbon emissions associated with two scheme alternatives for the proposed Forth Replacement Crossing.

Based on this early analysis, it was calculated that Option FS2 (involving extensive new road network, three-corridor main crossing with separate provision for public transport) would result in approximately 68% (102,000 tonnes) more embodied carbon than Option MG2 (less extensive road network, two-corridor main crossing, and refurbishment of the FRB to allow use by public transport). This assessment also indicated that steel and concrete were responsible for the majority of the embodied carbon associated with materials to be used in the scheme.

Building on the high-level carbon footprinting exercise carried out at the initial design stage, a more detailed analysis was carried out based on Stage 3 Design which assessed the embodied energy and carbon associated with key materials.

The findings from this assessment indicate that, in the case where Option 1 (orthotropic cable-stayed bridge and composite approach viaduct) is chosen for the Main Crossing superstructure, the total embodied energy for the scheme would be 3,129,574 GJ and the total embodied carbon would be 232,074 tCO2.

The Main Crossing superstructure (cable-stayed bridge and approach viaduct) makes up the greatest proportion of total embodied energy and carbon. In the case where Option 1 is chosen, the Main Crossing superstructure would account for approximately 48% of the overall embodied energy of the scheme. Under this scenario, the Main Crossing substructure would account for around 24% of total embodied energy, while land-based structures and the road network would make up 17% and 11% respectively.

In terms of which materials make the greatest contributions to overall embodied energy, steel accounts for approximately 75%, quarry source materials (aggregates, stone, asphalt, etc) make up around 14%, while cement and concrete account for around 11% and paint accounts for less than 1% of the total.

9.4 Potential Options to Reduce Energy and Carbon

A number of options are being considered which are aimed at reducing embodied energy and carbon. Some of these include:

  • using recycled aggregate rather than quarried aggregate;
  • use of other recycled materials such as kerbs, plastic pipes, etc;
  • using an increased proportion of recycled steel;
  • implementation of a sustainable resource management framework;
  • optimisation of cut and fill balance to minimise the need to import, or export, fill from site;
  • use of pre-cast technologies; and
  • various other design measures to achieve an efficient and economical design, thereby minimising material use.

An initial investigation of the carbon emissions associated with the transport of materials to site was also undertaken as part of this assessment. Various illustrative sourcing scenarios for steel materials were assessed, including: sourcing from within the UK and transporting by rail or road; shipping from Rotterdam to Rosyth; or shipping from China. The results of this exercise indicate that sourcing materials close to site and transporting them by the most sustainable means available could achieve significant carbon savings.

9.5 Operational Carbon

In terms of emissions of greenhouse gases such as CO2 associated with the operation of the scheme, the ES assessment (Chapter 15: Air Quality) predicted a 14,952 tonne increase in CO2 emissions in 2017 with the proposed scheme due to more vehicle kilometres being travelled. The scheme will increase the length of the majority of cross-Forth journeys by about 1km because the new crossing is slightly further west than the Forth Road Bridge.

Further assessment was carried out to more fully capture the localised effect of "stop-start" motoring conditions on the congested approaches to the Forth Road Bridge and the localised benefits to be derived from relieving these conditions. The assessment involved modelling a local network in the vicinity of the Forth Replacement Crossing using an alternative approach that better takes into account the emissions from such "stop-start" traffic conditions. Initial findings indicate that during the congested morning peak period, increased CO2 emissions from the additional distance travelled may be mitigated by reduced congestion that the proposed scheme will deliver relative to the situation without the scheme. There is less congestion relief in the evening peak and therefore the mitigating effect referred to above is less evident during this period.

In terms of impacts from vehicles using the crossing, the FRC scheme includes a number of features aimed at reducing CO2 emissions. Briefly, these include:

  • use of Intelligent Transport Systems to improve network efficiency and decrease congestion;
  • promoting modal shift, particularly through the provision of a public transport corridor on the FRB; and
  • encouraging and facilitating active modes of transport (e.g. cycling) by minimising impacts on paths and cycle routes and improving these where feasible.

9.6 Next Stages

The energy and carbon assessment will form a ‘baseline’ against which future progress can be monitored. The Contractor will be expected to calculate embodied energy and carbon based on its design and this should not exceed, and should preferably improve on the baseline condition.

Annex A Energy and Carbon Values

Category

Material Type

Conversion

Energy (GJ/t)

Carbon (tCO2/t)

Comments

Cements

 

 

General

1.5 tonnes/m3

4.6

0.83

 

Cement: general - 25% blast furnace slag

1.86 tonnes/m3

3.81

0.64

 

Cement: general - 50% blast furnace slag

1.86 tonnes/m3

3.01

0.45

 

 

Category

Material Type

Conversion

Energy (GJ/t)

Carbon (tCO2/t)

Comments

UK Typical

Primary

Secondary

UK Typical

Primary

Secondary

Metals

Steel: general

8.0 tonnes/m3

24.4

35.3

9.5

1.77

2.75

0.43

Estimated from UK's consumption of types of steel, and worldwide recycled content 42.7%

Steel: bar & rod

7.9 tonnes/m3

24.6

36.4

8.8

1.71

2.68

0.42

 

Steel: section

8.0 tonnes/m3

25.4

36.8

10

1.78

2.78

0.44

 

Steel: wire

8.0 tonnes/m3

-

36.00

-

2.83

-

-

 

Steel: stainless

8.0 tonnes/m3

56.7

-

-

6.15

-

-

 

Sheet piling: heavy use

0.9 tonnes/m2

24.4

35.3

9.5

1.77

 

 

Category

Material Type

Conversion

Energy (GJ/t)

Carbon (tCO2/t)

Comments

Misc

Paint (Average)

1.2 kg/litre

68

3.56

Large variations in data, especially for carbon emissions

 

Category

Material Type

Conversion

Energy (GJ/t)

Carbon (tCO2/t)

Comments

Quarry Sourced Materials

Quarried aggregate

2.0 tonnes/m3

0.10

0.008

Recycled aggregate

2.0 tonnes/m3

0.10

0.00369

General aggregate

2.0 tonnes/m3

0.10

0.005

ICE database

General Asphalt

1.7 tonnes/m3

2.60

0.045

Sand

1.85 tonnes/m3

0.10

0.005

Soil

1.7 tonnes/m3

0.45

0.023

Stone: general

2.0 tonnes/m3

1.00

0.056

Wide data range

 

Category

Material Type

Conversion

Energy

Carbon

Comments

GJ/t

tCO2/t

Concrete

General Road and Pavement

-

1.24

0.127

 

High Strength

-

1.39

0.209

 

Prefabricated Concrete

-

2.00

0.215

 

Notes:

Above values entered from Highways Agency Model and ICE Database on 17/7/09

The HA Model and ICE Database contain a comprehensive range of embodied energy and carbon values for construction materials

Annex B Embodied Energy and Carbon Calculations

Road and Earthworks

Energy and Carbon Calculations for the Road Network and Earthworks

Component

Category

Material specification

Mass (tonnes)

Energy & Carbon values

Energy

Carbon

GJ/t

tCO2/t

GJ

tCO2

Pavement

Quarry Sourced Material

General Asphalt

88,751

2.60

0.045

230,752

3,994

Overlay

General Asphalt

10,531

2.60

0.045

27,381

474

Sub-base

General aggregate

52,206

0.100

0.005

5,221

261

Capping

General aggregate

104,413

0.10

0.005

10,441

522

Import of fill

General aggregate

690,000

0.10

0.01

69,000

3,450

Total

342,794

8,701

Land-Based Structures

Summary of Energy and Carbon Calculations for Land-Based Structures

Structure

Mass (tonnes)

Energy & Carbon values

Energy

Carbon

Category

Material

GJ/t

tCO2/t

GJ

tCO2

Concrete

Concrete: high strength

96,372

1.39

0.209

133,957

20,142

Precast concrete

877

2.00

0.215

1,754

189

 

Structure

Mass (tonnes)

Estimated Recycled Proportion (%)

Embodied Energy (GJ/t)

Embodied Carbon (tCO2/t)

Energy

Carbon

Category

Material

UK Typical

Secondary

UK Typical

Secondary

GJ

tCO2

Metals

Steel: bar & rod

7,847

0

24.6

8.8

1.71

0.42

193,036

13,418

Steel: section

7,082

0

25.4

10

1.78

0.44

179,883

12,606

 

Structure

Mass (tonnes)

Energy & Carbon values

Energy

Carbon

Category

Material

GJ/t

tCO2/t

GJ

tCO2

Quarry Sourced Materials

General aggregate: Imported Fill

282600

0.100

0.005

28,260

1,413

Total

536,890

47,768

Embodied Energy Calculations for Land-Based Structures

Structure

Ferrytoll

Queensferry Junction

FT01/02

FT03

FT05

FT07E

FT10E

FT11

FT12

ESQ02

ESQ03

ESQ04

ESQ05

ESQ06

ESQ07

ESQ09E

Category

Material

Embodied Energy GJ

Concrete

Concrete: high strength

66,484

4,537

3,319

10,258

177

6,946

6,345

3,536

2,819

3,586

4,837

2,102

7,256

40

Precast concrete

0

0

476

0

0

0

0

0

0

0

0

0

0

252

Metals

Steel: bar & rod

98,154

6,691

5,338

4,772

221

12,398

11,341

4,994

3,764

5,166

7,134

3,100

10,701

320

Steel: section

147,244

6,985

0

0

0

0

0

6,858

3,556

7,620

0

0

0

0

Quarry Sourced Materials

General aggregate: Imported Fill

12,963

1,220

790

106

0

3,578

2,725

480

411

244

1,292

592

1,574

0

 

Structure

M9 Junction 1A

TOTAL

M901

M903

M904

M905E

M907E

M908E

Category

Material

Embodied Energy GJ

Concrete

Concrete: high strength

3,210

967

2,572

293

303

4,370

133,957

Precast concrete

0

200

0

0

0

826

1,754

Metals

Steel: bar & rod

5,043

1,525

4,723

394

467

6,790

193,036

Steel: section

7,620

0

0

0

0

0

179,883

Quarry Sourced Materials

General aggregate: Imported Fill

334

540

486

144

42

738

28,260

Total (GJ)

536,890

Information on Land-Based Structures

Structure

Comments

Ferrytoll

FT01/FT02

Mainline Viaduct

FT03

Ferrytoll Junction North - New Underbridge

FT05

Railway bridge

FT06E

Structure Demolished

FT07E

Widening of Structure

FT08E

No Works required under Stage 3

FT09E

No Works required under Stage 3

FT10E

Minor works

FT11

Proposed Retaining Wall

FT12

Retaining Wall Gyratory Interchange South Bound

Queensferry Junction

ESQ02

Queensferry Junction North

ESQ03

Queensferry Junction South

ESQ04

New Overbridge

ESQ05

Pipe Protection System

ESQ06

Pipe Protection System

ESQ07

Pipe Protection System

ESQ08E

Structure Demolished

ESQ09E

Minor Parapet Works

M9 Junction

M901

New Overbridge

M903

New Underbridge

M904

New Swine Burn Culvert

M905E

Minor works

M906E

Structure Retained

M907E

Culvert Extension

M908E

Reconstruction of Western Section

Information on Main Crossing Substrutures:

SNTBP

South and north tower bases

ASLPr

Approach span piers, S3 to S8 and N3

STP

South tower piles

ASMPr

Approach span piers, S1, S2, N1 and N2

NTP

North tower piles

ACS (Piled)

S1 to S4, N1 pile caps and piles

CTB

Central tower base

ACS (Pad)

S5 to S8 and N2, pads

Embodied Carbon Calculations for Land-Based Structures

Structure

Ferrytoll

Queensferry Junction

FT01/02

FT03

FT05

FT07E

FT10E

FT11

FT12

ESQ02

ESQ03

ESQ04

ESQ05

ESQ06

ESQ07

ESQ09E

Category

Material

Embodied Carbon (tCO2)

Concrete

Concrete: high strength

9,996

682

499

1,542

27

1,044

954

532

424

539

727

316

1,091

6

Precast concrete

0

0

51

0

0

0

0

0

0

0

0

0

0

27

Metals

Steel: bar & rod

6,823

465

371

332

15

862

788

347

262

359

496

215

744

22

Steel: section

10,319

490

0

0

0

0

0

481

249

534

0

0

0

0

Quarry Sourced Materials

General aggregate: Imported Fill

648

61

40

5

0

179

136

24

21

12

65

30

79

0

 

Structure

M9 Junction 1A

TOTAL

M901

M903

M904

M905E

M907E

M908E

Category

Material

Embodied Carbon (tCO2)

Concrete

Concrete: high strength

483

145

387

44

46

657

20,142

Precast concrete

0

22

0

0

0

89

189

Metals

Steel: bar & rod

351

106

328

27

32

472

13,418

Steel: section

534

0

0

0

0

0

12,606

Quarry Sourced Materials

General aggregate: Imported Fill

17

27

24

7

2

37

1,413

Total (tCO2)

47,768

Summary of Embodied Energy and Carbon Associated with Land-Based Structures

Structure

Embodied Energy GJ

Percentage of Total

Embodied Carbon tCO2

Percentage of Total

FT01/FT02

324,845

61%

27,786

58%

FT03

19,433

4%

1,698

4%

FT05

9,924

2%

961

2%

FT07E

15,137

3%

1,879

4%

FT10E

398

0%

42

0%

FT11

22,922

4%

2,085

4%

FT12

20,411

4%

1,879

4%

ESQ02

15,868

3%

1,383

3%

ESQ03

10,550

2%

955

2%

ESQ04

16,616

3%

1,445

3%

ESQ05

13,263

2%

1,288

3%

ESQ06

5,793

1%

561

1%

ESQ07

19,531

4%

1,914

4%

ESQ09E

612

0%

55

0%

M901

16,207

3%

1,384

3%

M903

3,233

1%

300

1%

M904

7,781

1%

739

2%

M905E

831

0%

79

0%

M907E

812

0%

80

0%

M908E

12,724

2%

1,255

3%

Total

536,890

100%

47,768

100%

Main Crossing Substructure

Energy and Carbon Calculations for the Main Crossing Substructure

Structure

Mass (tonnes)

Energy & Carbon values

Energy

Carbon

Category

Material

GJ/t

tCO2/t

GJ

tCO2

Cements

Cement: general - 50% blast furnace slag

17,362

3.01

0.45

52,260

7,813

Structure

Mass (tonnes)

Estimated Recycled Proportion (%)

Embodied Energy (GJ/t)

Embodied Carbon (tCO2/t)

Energy

Carbon

Category

Material

UK Typical

Secondary

UK Typical

Secondary

GJ

tCO2

Metals

Steel: general

23,446

50

24.4

9.5

1.77

0.43

397,410

25,791

Sheet piling: heavy use

8,565

0

24.4

1.77

0

208,986

15,160

Structure

Mass (tonnes)

Estimated Recycled Proportion (%)

Embodied Energy (GJ/t)

Embodied Carbon (tCO2/t)

Energy

Carbon

Category

Material

UK Typical

Secondary

UK Typical

Secondary

GJ

tCO2

Quarry Sourced Materials

Quarried aggregate

37,259

-

0.1

0.008

3,726

298

Recycled aggregate

5,822

50

-

0.1

-

0.00369

582

34

Sand

22,643

-

0.1

0.005

2,264

113

Stone: general

27,060

-

1.0

0.056

27,060

1,515

Structure

Mass (tonnes)

Energy & Carbon values

Energy

Carbon

Category

Material

GJ/t

tCO2/t

GJ

tCO2

Concrete

General Road and Pavement

31,947

1.24

0.127

39,614

4,057

High Strength

7,974

1.39

0.21

11,084

1,667

Total

742,986

56,448

Embodied Energy Calculations for the Main Crossing Substructure

Structure

Estimated Recycled Proportion (%)

SNTP

STP

NTP

CTB

ASC (Piled)

ASC (Pad)

ASMPr

ASLPr

Total

Category

Material

Embodied Energy (GJ)

Cements

Cement: general - 50% blast furnace slag

-

26,334

0

0

5,860

9,081

3,763

2,989

4,232

52,260

Metals

Steel: general

50

199,298

14,967

12,831

11,577

131,905

8,645

7,661

10,526

397,410

Sheet piling: heavy use

-

91,256

42,432

32,989

0

42,310

0

0

0

208,986

Quarry Sourced Materials

Quarried aggregate

-

1,675

0

0

0

948

378

300

425

3,726

Recycled aggregate

50

462

0

0

120

0

0

0

0

582

Sand

-

994

0

0

0

535

252

200

283

2,264

Stone: general

-

0

0

0

0

23,540

3,520

0

0

27,060

Concrete

General Road and Pavement

-

0

18,676

15,995

4,944

0

0

0

0

39,614

High Strength

-

0

0

0

11,084

0

0

0

0

11,084

Total (GJ)

742,986

Embodied Carbon Calculations Substructure

Structure

Estimated Recycled Proportion (%)

SNTP

STP

NTP

CTB

ASC (Piled)

ASC (Pad)

ASMPr

ASLPr

Total

Category

Material

Embodied Carbon (tCO2)

Cements

Cement: general - 50% blast furnace slag

-

3,937

0

0

876

1,358

563

447

633

7,813

Metals

Steel: general

50

12,934

971

833

751

8,560

561

497

683

25,791

Sheet piling: heavy use

-

6,620

3,078

2,393

0

3,069

0

0

0

15,160

Quarry Sourced Materials

Quarried aggregate

-

134

0

0

0

76

30

24

34

298

Recycled aggregate

50

27

0

0

7

0

0

0

0

34

Sand

-

50

0

0

0

27

13

10

14

113

Stone: general

-

0

0

0

0

1,318

197

0

0

1,515

Concrete

General Road and Pavement

-

0

1,913

1,638

506

0

0

0

0

4,057

High Strength

-

0

0

0

1,667

0

0

0

0

1,667

Total (tCO2)

56,448

Main Crossing Superstructure

Energy and Carbon Calculations for Main Crossing Superstructure Options Summary

Cable Stay Bridge - Single Deck Box Girder - Orthotropic

Category

Material

Mass (tonnes)

Energy and Carbon Values

Energy

Carbon

GJ/t

GJ

GJ

tCO2

Metals

Steel: general (UK typical)

34,412

24.40

1.77

839,641

60,908

Steel: general (primary)

49

35.30

2.75

1,723

134

Steel: bar & rod (UK Typical)

4,712

24.60

1.71

115,915

8,058

Steel: bar & rod (Primary)

60

36.40

2.68

2,184

161

Steel: wire

3,721

36.00

2.83

133,956

10,530

Stainless steel

1,156

56.70

6.15

65,545

7,109

Misc

Paint: 100um thickness

48

68

3.56

3,288

172

Paint: 300um thickness

32

68

3.56

2,177

114

Quarry Sourced Materials

25mm Asphalt

227

2.60

0.045

589

10

70mm Asphalt

5,011

2.60

0.045

13,030

226

125mm Asphalt

2,359

2.60

0.045

6,133

106

Concrete

Concrete (high strength)

52,452

1.39

0.209

72,908

10,962

Concrete (general road and pavement)

0

1.24

0.127

0

0

 

 

 

 

Total

1,257,089

98,491

 

Cable Stay Bridge - Single Deck Box Girder - Orthotropic

Material

Embodied Energy (GJ)

Percentage of Total

Embodied Carbon (tCO2)

Percentage of Total

Steel: general (UK typical)

839,641

67%

60,908

62%

Steel: general (primary)

1,723

0%

134

0%

Steel: bar & rod (UK Typical)

115,915

8,058

Steel: bar & rod (Primary)

2,184

0%

161

0%

Steel: wire

133,956

10,530

Stainless steel

65,545

5%

7,109

7%

Paint

5,465

0%

286

0%

Asphalt

19,752

2%

342

0%

Concrete (high strength)

72,908

6%

10,962

11%

Concrete (general road and pavement)

0

0%

0

0%

Total

1,257,089

100%

98,491

100%

Cable Stay Bridge - Single Deck Box Girder - Composite

Category

Material

Steel: general (UK typical)

Mass (tonnes)

Energy and Carbon values

Energy

Carbon

GJ/t

tCO2/t

GJ

tCO2

Metals

23,427

24.40

1.77

571,607

41,465

Steel: general (primary)

50

35.30

2.75

1,757

137

Steel: bar & rod (UK Typical)

8,327

24.60

1.71

204,844

14,239

Steel: bar & rod (Primary)

60

36.40

2.68

2,184

161

Steel: wire

5,377

36.00

2.83

193,572

15,217

Stainless steel

1,156

56.70

6.15

65,545

7,109

Category

Material

Mass (tonnes)

Energy and Carbon values

Energy

Carbon

GJ/t

tCO2/t

GJ

tCO2

Misc

Paint: 100um thickness

26

68

3.56

1,776

93

Paint: 300um thickness

32

68

3.56

2,177

114

Category

Material

Mass (tonnes)

Energy and Carbon values

Energy

Carbon

GJ/t

tCO2/t

GJ

tCO2

Quarry Sourced Materials

25mm Asphalt

1,086

2.60

0.045

2,824

49

70mm Asphalt

0

2.60

0.045

0

0

125mm Asphalt

11,308

2.60

0.045

29,400

509

Category

Material

Mass (tonnes)

Energy and Carbon values

Energy

Carbon

GJ/t

tCO2/t

GJ

tCO2

Concrete

Concrete (high strength)

99,516

1.39

0.209

138,327

20,799

Concrete (general road and pavement)

1,200

1.24

0.127

1,488

152

Total

1,215,501

100,044

 

Cable Stay Bridge - Single Deck Box Girder - Composite

Material

Embodied Energy (GJ)

Percentage of Total

Embodied Carbon (tCO2)

Percentage of Total

Steel: general (UK typical)

571,607

47%

41,465

41%

Steel: general (primary)

1,757

0%

137

0%

Steel: bar & rod (UK Typical)

204,844

17%

14,239

14%

Steel: bar & rod (Primary)

2,184

0%

161

0%

Steel: wire

193,572

16%

15,217

15%

Stainless steel

65,545

5%

7,109

7%

Paint

3,953

0%

207

0%

Asphalt

32,224

3%

558

1%

Concrete (high strength)

138,327

11%

20,799

21%

Concrete (general road and pavement)

1,488

0%

152

0%

Total

1,215,501

100%

100,044

100%

Energy and Carbon Calculations for Approach Bridge Options

Approach Bridge - Twin Composite Box Girder

Category

Material

Mass (tonnes)

Energy and Carbon Values

Energy

Carbon

GJ/t

GJ

GJ

tCO2

Metals

Steel: general (UK typical)

5,511

24.40

1.77

134,479

9,755

Steel: general (primary)

36

35.30

2.75

1,271

99

Steel: bar & rod

2,350

24.60

1.71

57,807

4,018

Steel: wire

0

36.00

2.83

0

0

Stainless steel

217

56.70

6.15

12,315

1,336

Misc

Paint: 100um thickness

3

68

3.56

200

10

Paint: 300um thickness

7

68

3.56

499

26

Quarry Sourced Materials

25mm Asphalt

164

2.60

0.045

426

7

70mm Asphalt

0

2.60

0.045

0

0

125mm Asphalt

2,931

2.60

0.045

7,620

132

Concrete

Concrete (high strength)

25,165

1.39

0.209

34,979

5,259

Concrete (general road and pavement)

176

1.24

0.127

218

22

 

 

 

 

Total

249,815

20,666

 

Approach Bridge - Twin Composite Box Girder

Category

Material

Mass (tonnes)

Energy and Carbon Values

Energy

Carbon

GJ/t

GJ

GJ

tCO2

Metals

Steel: general (UK typical)

1,133

24.40

1.77

27,650

2,006

Steel: general (primary)

39

35.30

2.75

1,359

106

Steel: bar & rod

3,475

24.60

1.71

85,482

5,942

Steel: wire

640

36.00

2.83

23,030

1,810

Stainless steel

217

56.70

6.15

12,315

1,336

Misc

Paint: 100um thickness

0

68

3.56

0

0

Paint: 300um thickness

0

68

3.56

0

0

Quarry Sourced Materials

25mm Asphalt

164

2.60

0.045

426

7

70mm Asphalt

0

2.60

0.045

0

0

125mm Asphalt

2,931

2.60

0.045

7,620

132

Concrete

Concrete (high strength)

44,003

1.39

0.209

61,164

9,197

Concrete (general road and pavement)

176

1.24

0.127

218

22

 

 

 

 

Total

219,265

20,558

 

Approach Bridge - Twin Concrete Box Girder

Material

Embodied Energy (GJ)

Percentage of Total

Embodied Carbon (tCO2)

Percentage of Total

Steel: general (UK Typical

27,650

13%

2,006

10%

Steel: general (UK Primary)

1,359

1%

106

1%

Steel: bar & rod

85,482

39%

5,942

29%

Steel: wire

23,030

11%

1,810

9%

Stainless steel

12,315

6%

1,336

6%

Paint

0

0%

0

0%

Asphalt

8,046

4%

139

1%

Concrete (high strength)

61,164

28%

9,197

45%

Concrete (general road and pavement)

218

0%

22

0%

Total

219,265

100%

20,558

100%

 

 

Cable Stay Bridge

Orthotropic

Composite

Embodied Energy (GJ)

Approach Viaduct

Composite

1,506,904

1,465,316

Concrete

1,476,353

1,434,766

Combination of Options for Main Crossing

Cable Stay Bridge

Orthotropic

Composite

Embodied Energy (GJ)

Approach Viaduct

Composite

119,157

120,710

Concrete

119,049

120,602

 

Footnotes

1. 1 The carbon coefficients contained within the ICE database are generally consistent with those in the Highways Agency Carbon Accounting Tool. Where there are discrepancies these are noted in the calculation tables.

2. " http://www.distances.comal " material comes from secondary (i.e. recycled) sources.

3. http://www.distances.com

4. http://www.portworld.com