APPENDIX C – TRUNK ROAD NETWORK PROCEDURES – ERSKINE BRIDGE
APPENDIX C – TRUNK ROAD NETWORK PROCEDURES – ERSKINE BRIDGE
INTRODUCTION
Purpose
Erskine Bridge is an exposed structure and it is essential that traffic control is applied during high winds to ensure that vulnerable vehicles are not exposed and blown over or blown into the path of other vehicles. This equally applies to pedestrians and cyclists potentially using the relevant pathways on it.
This plan identifies the specific wind monitoring and operational procedures to be adopted in response to predicted and actual high winds in the proximity of the Bridge.
HIGH WINDS
Taking cognisance of wind forecasting and warning information from the Meteorological Office and monitoring ‘live’ speeds provided by the wind data facility on the Erskine Bridge, graduated operational responses will be implemented to allow the majority of drivers continued use of the Bridge, until the final phase. These are as follows:
Stage 1 A ‘Warning’ phase implemented for wind gusts in the 35 to 44 mph range;
Stage 2 Procedures intended to advise of
‘segregation’ arrangements during
45 mph cross and 60 mph head/tail wind gusts, in order to
divert
high-sided vehicles; and
Stage 3 Full closure of Erskine Bridge for wind gusts of 70 mph and above, irrespective of wind direction.
WIND MONITORING
Wind Forecast
Erskine Bridge is the subject of site-specific wind forecast/wind warning information provided by the Meteorological Office, as follows:
(a) Daily 5-day Forecast
This forecast is issued at approximately 0600 hrs each day and permits the Operating Company (OC) to plan and prepare for possible restrictions or closures. It is graduated and reflects rising wind speeds:
- Green (G): maximum gust speeds 30 mph and below;
- Amber (A): maximum gust speeds 31 to 44 mph;
- Red (R): maximum gust speeds 45 to 59 mph; and
- Black (B): maximum gust speeds 60 mph and over.
(b) Detailed Daily 24-hour Forecast
This forecast is also issued at approximately 0600 hrs daily and runs from 0700 hrs that morning to 0700 hrs the following morning.
(c) ‘Wind (Gale) Warning’ or ‘Wind (Storm) Warning’
Issued, if during the next 6 hours the maximum gust is forecast to exceed 45 mph or 60 mph respectively.
Live Wind Data
In addition, an ultrasonic wind anemometer is installed immediately above the centre bridge deck of Erskine Bridge and provides ‘live’ data and associated forecast information from the Met Office, on a web-based, large screen display within the OC Operational Control Room (OCR).
RESPONSIBILITIES
(a) Strathclyde Police
The police are empowered in terms of the Road Traffic Regulation Act 1984, Section 67(1) to close or instruct closure of a road in extraordinary circumstances, in order to mitigate potential danger. Consequently, in situations which raise concerns for safety, and with increasing wind velocities at the Erskine Bridge being within the recognised parameters, the Duty Engineer’s findings must immediately be intimated to Strathclyde Police for the police to decide and confirm approval for the implementation of ‘segregation’ or ‘full closure’ arrangements.
(b) Duty Engineer (24/7)
The OC Duty Engineer (D/E) will ensure that all wind related information for the Erskine Bridge is appropriately monitored and evaluated and, where appropriate, will instruct OCR staff to consult with the police, with a view to implementing procedures for either Stage 2 – ‘Segregation’ or Stage 3 – ‘Full Closure’. The D/E will be responsible for liaising with the Met Office to confirm forecasts and projections.
(c) The Operational Control Room (OCR)
The OCR will undertake continuous monitoring of wind data from
the ‘live’ information feed on the web site, fully
supporting the D/E in the wind
management arrangements for Erskine Bridge and liaising with
Strathclyde Police. They will coordinate with Traffic Scotland in
the implementation of each of the relevant stages.
(d) Duty Officer
In close liaison with the OCR, the OC Duty Officer (D/O) will be responsible for deploying all traffic management (TM) resources necessary to fulfil requirements to assist police in implementing the agreed stages’ response and updating staff with the relevant progress of TM operations.
(e) Traffic Scotland
Traffic Scotland will maintain close liaison with the OCR throughout the incident and will:
- Implement the pre-arranged variable message signs (VMS) Plan to reflect the parameters of the particular Stage notified;
- Undertake a cursory CCTV sweep of the visible bridge deck area for a ‘Full Closure’, in order to confirm an absence of vehicles to the OCR, after all TM operations have been completed;
- Updating information on both Traffic Scotland and Freight Scotland web sites; and
- At the completion of the incident, cancel associated VMS Plans only when a complete removal of all physical traffic management has been effected and when notified by the OCR.
MOBILISATION PROCEDURES
Stage / Wind Gust Speed |
Actions |
---|---|
Stage 1 Wind gusts over |
‘Warning’ Phase
|
Stage 2 Cross wind gusts of 45 mph or Head/Tail wind gusts of 60 mph
|
‘Segregation’ Phase
|
Stage 3 Cross wind gusts and Head/Tail Wind gusts of 70 mph |
‘Full Closure’ Phase
Note: The temporary drop-down signs currently utilised at Stage 2 must be left open until reduced wind speeds allow them to be closed safely. |
Wind gusts of |
Structural Examination Where velocities of 80 mph or greater have been experienced, Erskine Bridge must be subjected to a structural survey as soon as reasonably practicable. |
Traffic Management – Stage 2 (‘Segregation’)
Temporary drop-down signs intimating, ‘Erskine Bridge Closed to High Sided Vehicles’ are pre-positioned at the following locations and will be deployed in support of the primary VMS signs:
- M8 (E) – On approach to the off-slip to M898;
- M8 (W) – On approach to the off-slip to M898;
- A82 (N) – On approach to the off-slip to A898
(Prior to advanced direction
signs (ADS) at Auchentoshan Distillery); - A82 (S) – On approach to the off-slip to A898;
- B815 (E) at Erskine – On approach to the roundabout giving access to the A898 northbound; and
- A726 (W) at Erskine – Between the spectacle roundabouts, prior to the access slip to the A898 northbound.
Traffic Management – Stage 3 (‘Full Closure’)
The following actions to be undertaken by TM and ISU Crews to assist police in implementing the agreed response:
- Closure of the northbound M898 at its access point from the M8 westbound;
- Closure of the M898 from its merge point between the east and
west bound
off-slips from the M8, to the A726/B815 Bishopton/Erskine off-slip. This will physically compel all traffic to leave via the latter road; - Closure of the A726/B815 northbound on-slip from the ‘Spectacle’ Roundabout onto the bridge; and
- Closure of the A82 westbound and eastbound on-slips onto the A898.
RE-OPENING PROCEDURES
A decision to re-open Erskine Bridge from either a Stage 2 (‘Segregation’) or a Stage 3 (‘Full Closure’), will be taken by the police on the advice of the D/E, who will have previously ascertained the following:
- Whether the forecast wind gust speeds are expected to remain below the relevant speed and the wind direction is not expected to change adversely or blow from a more critical direction;
- When reviewing a Stage 2 (‘Segregation’)
scenario, it is important that
removal is not undertaken where it is anticipated that it will possibly require a re-imposition a relatively short time later; and - Similarly, as a Stage 3 (‘Full Closure’) may require more than 1 hour to re-open and perhaps 1½ to 2 hrs to close again, re-opening should not be considered where there is potential of further closure within a few hours.
Sequence of Arrangements for Re-opening
The following Table lists the sequential removal of the relevant stages, listing associated procedures and responsibilities:
Stage / Wind Gust Speed |
Actions |
---|---|
Reduction from Stage 3 Cross wind gusts and Head/Tail Wind gusts now reduced to less than 70 mph |
Removal of ‘Full Closure’
|
Reduction from Stage 2 Cross wind gusts now less than |
Removal of ‘Segregation Arrangements’
|
Reduction from Stage 1 Winds speed gusts now below 35 mph |
Removal of ‘Warning’ Signs
|