BEAR Scotland has been commissioned by Transport Scotland to demolish the existing M80 7-8 G90 gantry on the northbound (NB) carriageway, relocate the existing M80 7-8 G20 gantry, as well as remove and install new signage and vehicle restraint systems (VRS) over a length of 0.7km (Approx. 1.1ha).
The construction activities for the works are as follows:
- Installation of traffic management (TM) on M80 NB including temporary vehicle barriers (various phases, locations and arrangements).
- Establish site compound, welfare facilities etc. (various phases, locations and arrangements).
- Remove existing VRS at works locations.
- Excavate and pile for new foundations at locations of new gantry, one foundation in NB verge and one foundation in central verge.
- Cast reinforced concrete for new foundations at location of new gantry.
- Install a new post mounted sign upstream of existing location of M80 7-8 G20, in NB verge.
- Remove existing gantry steel superstructure from M80 7-8 G20 and installing it on the new foundations at location of the new gantry.
- Touch up paint on gantry steelwork.
- Dismantle existing M80 7-8 G90 gantry including demolition of foundations down to 1m below ground level.
- Demolish foundations of gantry M80 7-8 G20 down to 1m below ground level.
- Install new VRS at existing and new gantry/sign locations.
- Apply road markings on M80 between Junctions 7 and 8.
- Remove all TM.
The works are currently programmed to be completed within 2026/2027 financial year, with works expected to begin on the 13th of April 2026. Works are programmed to be completed over two to three months as a combination of day and night-works (07:00 - 16:30 and 19:30 – 06:00). Multiple phases of TM will be required for the duration of the works, these include:
- NB hard shoulder closure, potentially with narrow running lanes and a partial closure of Lane 1 to allow all works to be undertaken in the NB verge at various locations.
- NB Lane 3 closure with hard shoulder running, potentially with narrow running lanes. A partial Lane 2 closure, along with a Lane 3 southbound (SB) closure with hard shoulder running to allow all works to be undertaken in the central reserve.
- Full overnight closures of the M80 in both directions during lifting out and in of the M80 7-8 G20 superstructure and for demolition of M80 7-8 G90 gantry.
Location
The scheme lies on the M80 NB carriageway at Dennyloanhead, within Falkirk Council and is predominantly bordered by both arable land and small sections of woodland.