Annex A - BEAR Scotland RaBT Presentation Slides

Slide 1 - Meeting details

Slide 1 - Meeting details, as described in the following text

A83 Taskforce

Meeting No. 32

Microsoft Teams

9 September 2026

Eddie Ross

Scheme Delivery Manager

BEAR Scotland Ltd

Slide 2 - Presentation Overview

Slide 2 - Presentation Overview, as described in the following text

A83 Taskforce No. 32

Presentation Overview

 

Part 1: Rest and Be Thankful

·       Hillside conditions

·       Debris barrier repair project

·       Works planned in next period

 

Part 2: Wider A83 works programme

·       Works completed since last meeting

·       Works planned in next period

 

Slide 3 - Part 1: Rest and be Thankful

Slide 3 - Part 1: Rest and be Thankful, as described in the following text

A83 Taskforce

Part 1: Rest and Be Thankful

 

Hillside Conditions

·       Daily monitoring has continued through the period.

·       Weather has predominantly been dry throughout the Spring / Summer.

·       Hillside conditions have been relatively stable with no issues impacting the trunk road.

·       No use of the Old Military Road in the period.

·       Maintenance work was paused and temporary traffic signals removed over summer at the request of the Taskforce.

Slide 4 - Catch Fence Emptying and Repairs

Slide 4 - Catch Fence Empyting and Repairs

A83 Taskforce

Catch Fence Emptying and Repairs

Slide contains a photograph of a recently repaired catch fence along the A83.

Slide 5 - Catch Fence Emptying and Repairs

Slide 5 - Catch Fence and Emptying Repairs

A83 Taskforce

Catch Fence Emptying and Repairs

Slide contains a photograph of a recently repaired catch fence along the A83.

Slide 6 -Further BEAR works

Slide 6 - Further BEAR works

A83 Taskforce

Further BEAR works

  • Stockproof Fence being installed on the slope above the trunk road to protect young trees.
  • Maintenance in debris pits and channels.
  • 3a and 3b lower slope scour works.
  • Westbound drainage improvements.

Further barrier repairs. 

Slide 7 - Further BEAR works

Slide 7 - Further BEAR works

Traffic Management

  • Traffic management only in place to facilitate essential works.
  • Works undertaken during daytime for safety and efficiency reasons.
  • During wetter seasons queuing under key channels is not advisable meaning that the coned off area is longer.
  • Works will be paused at Christmas / New Year.
  • Works will be paused during the busier summer period.

Slide 8 - Lower Slope Scour

Slide 8 - Lower Slope Scour

A83 Taskforce

Lower Slope Scour

Slide contains a photograph of scouring next to a culvert below the A83.

 

Slide 9 - Lower Slope Scour 

Slide 9 Lower Slope Scour

Slide 10 - Thank you and any questions

Slide 10 - thank you and any questions

A83 Taskforce

Thank You & Any Questions