Annex B - AtkinsRealis WSP Joint Venture Presentation Slides
Slide 1 - Meeting details
A83 Rest and Be Thankful
Task Force No.32
9 September 2026
Ritchie Clift (AWJV)
Slide 2 - LTS Ground Investigation
LTS – Ground Investigation
Emerging Outcomes
· Depth to bedrock established – variable, deeper / shallower than Stage 3 assumptions
· Bedrock strength equal to greater than Stage 3 assumptions
· High groundwater levels at the southern extent of the scheme and within the Rest and Be Thankful car park
The results of the ground Investigations are available on the British Geological Society (BGS) website.
· In line with industry practice, Ground Model currently being concluded to inform Specimen Design in line with the now established ground parameters, including:
o Catch-pit
o Culverts
o Debris Flow Shelter foundations
o Rock cut opposite car park
o Watercourse cascade structures
Slide 3 - Ongoing work
Ongoing work
Medium Term Solution
· MTS two-way options appraisal – awaiting decision.
· Objection resolution and Public Local Inquiry (PLI) if necessary
· Specimen Design
· Contract preparation
Long Term Solution
· Objection resolution and PLI if necessary
· Rock Anchor Trial (currently on site)
· Conclude ground model
· Specimen Design
· Contract preparation