Previous Open Actions
Action 28.7) In relation to the drainage works and open culvert at the Rest and Be Thankful, Drainage works complete. Action closed.
Action 30.3) Transport Scotland to engage with HIE and Argyll and Bute Council to facilitate an economic impact forum.
Action 31.4) BEAR Scotland to provide an update on the timescales for the work at the Erines pinch point.
Part 1: Rest and Be Thankful
No actions taken
Part 2: A83 Operation and Road Maintenance
Action 32.1) Transport Scotland and BEAR Scotland to confirm timescales for any decision or improvements at Erines pinch point
Action 32.2) BEAR Scotland to investigate potential resurfacing works at the bridge at Loch Shira.
Action 32.3) IW to liaise with stakeholder to progress cattle underpass.