3. Recommendations for Further Assessment 3.1 Recommendation 3.2 Southern Route Corridor Options 3.3 Northern Route Corridor Options

3. Recommendations for Further Assessment

3.1 Recommendation

The rationale described in the previous chapter and the resultant recommendations were presented to Transport Scotland at a workshop on 5 March 2008. Transport Scotland accepted all of the recommendations at the conclusion of the workshop.

Following the initial assessment stage, the corridor options noted below were therefore taken forward for further consideration at the next stage of assessment.

3.2 Southern Route Corridor Options

  • South Corridor Option 1.
  • South Corridor Option 2.
  • South Corridor Option 3.
  • Combination of South Corridor Options 1 and 2 (known as South Corridor Option 4A moving forward).

3.3 Northern Route Corridor Options

  • North Corridor Option 1.
  • North Corridor Option 2.
  • North Corridor Option 3.