A82 Pulpit Rock Improvement Environmental Impact Assessment: Environmental Statement September 2010

ISBN 978 1 906006 95 2

This section is also available in pdf format (57k)

Contents

1. INTRODUCTION
2. SCHEME DESCRIPTION
3. CONSULTATION
4. ASSESSMENT METHODOLOGY
5. POLICIES AND PLANS
6. LANDSCAPE AND VISUAL EFFECTS
7. LAND-USE
8. CULTURAL HERITAGE
9. ECOLOGY AND NATURE CONSERVATION
10. PEDESTRIANS, CYCLISTS, EQUESTRIANS AND COMMUNITY EFFECTS
11. ROAD DRAINAGE AND THE WATER ENVIRONMENT
12. DISRUPTION DUE TO CONSTRUCTION
13. CUMULATIVE IMPACT ASSESSMENT
14. ENVIRONMENTAL IMPACT TABLES
15. SCHEDULE OF ENVIRONMENTAL COMMITMENTS

16. APPENDICES

1. APPENDIX 1 – CONSULTATION RESPONSES
a. Statutory Consultation Responses
b. Non-Statutory Consultation Responses
c. Local Businesses and Residences Consultation Responses

2. APPENDIX 2 – VIADUCT STRUCTURE DESIGN STATEMENT

3. APPENDIX 3 – SITES AND MONUMENTS GAZETTEER

4. APPENDIX 4 - ECOLOGICAL APPENDICES
a. NVC and Bryophyte Survey
b. Macrophyte Survey Notes
c. European Protected Species Surveys
d. Otter Habitat Assessment Report
e. Fish Survey Report (June 2009)
f. Fish Survey Report (January 2010)

5. APPENDIX 5 – A82 FULL CLOSURE – ASSESSMENT REPORT

6. APPENDIX 6 – WATER ASSESSMENT – COPIES OF METHODS A, C AND D ASSESSMENTS

List of Figures

Figure 1.1 Location Plan
Figure 2.1 Environmental Constraints
Figure 2.2 The Scheme
Figure 6.1 Landscape Character Types
Figure 6.2 Viewpoint Locations
Figure 6.3 Viewpoints – Landscape Character (4 Sheets)
Figure 6.4 Photomontages (4 Sheets)
Figure 6.5 Visual Analysis
Figure 6.6 Scheme Landscape Design
Figure 6.7 Landscape Sections (3 Sheets)
Figure 7.1 Existing Land-use
Figure 8.1 Cultural Heritage Assets
Figure 9.1 Phase 1 Habitat Survey
Figure 9.2 Ecological Features
Figure 10.1 Community Facilities
Figure 11.1 Water Resources Study Area
Figure 11.2 Existing Drainage Conditions
Figure 11.3 Drainage Proposals
Figure 13.1 Cumulative Assessment Schemes

Glossary and Abbreviations

This table provides a glossary of the main terms and an explanation of the key abbreviations used in this Environmental Statement.

Environmental Assessment Process

Baseline

The current environmental conditions against which potential impacts/effects are identified.

Baseline Study / Survey

The process of research and fieldwork by which the current baseline conditions are established.

Construction

Any activities, which take place during the construction phase, including temporary land take.

Effect

The result of an impact on a particular resource or receptor.

Environmental Impact Assessment (EIA)

A process for identifying and evaluating the likely effect of a proposed development on the environment. EIA normally forms part of the consent procedure.

Environmental Statement

A document or series of documents which reports the findings of the EIA

Impact

A physical or measurable change to the environment attributable to the Scheme.

Infrastructure

The facilities, services and businesses in a defined area.

Magnitude of effect

The actual change taking place to the environment, for example, the extent of land take or predicted change in noise levels.

Operation

Any activities forming part of or associated with the operation of the Scheme.

Permanent Land take

The permanent occupation of land by Scheme infrastructure, including physical features such as buildings.

Receptor

A component of the natural, created or built environment such as a human being, water, air, a building or a plant that is affected by an impact

Resources

Physical or qualitative features of the environment which are capable of identification and evaluation, and which are often the subject of some form of protective planning designation.

Scope

The extent of coverage of EIA.

Significance of impact

The product of an impact’s magnitude and the sensitivity, importance or value of the relevant receptor or resource

Sources of Effect

The Scheme activities or components, which give rise to environmental effects, as defined below.

Types of Effect

Cumulative Effect

An effect resulting from the accumulation of a number of effects. A cumulative effect may result from:

The combination of different effects at a particular location;

The recurrence of effects of the same type at different locations;

The interaction of different effects over time or

The interaction between the Scheme and other projects.

Direct Effect

An effect arising from an impact attributable to a project component or activity.

Environmental Effect

Identification of the possible range and location of potential impact, the words impact and effect have been used interchangeably

Indirect Effect

An effect arising from additional development works which are as a result of the Scheme.

Non-significant Effect

An effect, which is unlikely to have an influence on the decision-making process.

Permanent Effect

An effect, which is irreversible or likely to persist for the foreseeable life of the Scheme.

Residual Effect

An effect, which is likely to remain after the application of mitigation measures.

Secondary Effect

An effect, which may arise as a consequence of a primary effect, particularly between different environmental topics (e.g. reduced amenity of a community facility due to noise and disturbance).

Significant Effect

An effect, which, in isolation or in combination with other effects, is likely – in the opinion of the EA team – to have an influence on the decision-making process.

Temporary Effect

An effect which is of limited duration, due to either the cessation of the impact giving rise to it or the ability of the environment to accommodate or recover from it.

Unavoidable Effect

An effect which is an inevitable consequence of the Scheme and which cannot be removed or rendered insignificant by mitigation.

Mitigation

Measures adopted to reduce, ameliorate or avoid significant effects.

Engineering Terms

Construction Compound

A defined area (usually fenced off) where construction activity takes place

Permanent Land take

A requirement for land that will be needed as part of the operation phase of the Scheme

Temporary Land take

A requirement for land that will be needed during the construction phase of the Scheme only, and can be returned to other use afterwards

The following is an explanation of some of the abbreviations used in this Environmental Statement:

DMRB

Design Manual for Roads and Bridges

SEPA

Scottish Environment Protection Agency

SNH

Scottish Natural Heritage

WOSAS

West of Scotland Archaeological Service

LLFT

Loch Lomond Fisheries Trust

LLTNPA

Loch Lomond and the Trossachs National Park Authority

SAC

Special Area of Conservation

SPA

Special Protection Area

SSSI

Site of Special Scientific Interest

NSA

National Scenic Area

RoD

Record of Determination

BAP

Biodiversity Action Plan

HGV’s

Heavy Goods Vehicles

SPP

Scottish Planning Policy Statement

CAR

Controlled Activities Regulations

IEEM

Institute of Ecology and Environmental Management

IEMA

Institute of Environmental Management and Assessment

WCA

Wildlife and Countryside Act

Disclaimer

This document has been prepared in accordance with the scope of Scott Wilson's appointment with its client and is subject to the terms of that appointment.  It is addressed to and for the sole and confidential use and reliance of Scott Wilson's client.  Scott Wilson accepts no liability for any use of this document other than by its client and only for the purposes for which it was prepared and provided.  No person other than the client may copy (in whole or in part) use or rely on the contents of this document, without the prior written permission of the Company Secretary of Scott Wilson Ltd.  Any advice, opinions, or recommendations within this document should be read and relied upon only in the context of the document as a whole.  The contents of this document do not provide legal or tax advice or opinion.


Published Date 23 Sep 2010 Type Projects