34 Progress Updates

Filter by:

A9 Dualling: Luncarty to Pass of Birnam - Construction update - Autumn 2021

23 Feb 2022

Progress made in the construction of the A9 Dualling: Luncarty to Pass of Birnam project.

A9 Dualling: Luncarty to Pass of Birnam - Construction update - Summer 2021

12 Nov 2021

Progress made in the construction of the A9 Dualling: Luncarty to Pass of Birnam project.

A9 Dualling: Luncarty to Pass of Birnam - Construction update - Spring 2021

30 Jul 2021

Progress made in the construction of the A9 Dualling: Luncarty to Pass of Birnam project.

Bridging the gap for the Maybole Bypass

29 Jul 2021

A significant milestone with the completion of the beam installation for the third, and final, bridge on the project

A9 Dualling: Luncarty to Pass of Birnam - Construction update - Winter 2020/21

27 May 2021

Progress made in the construction of the A9 Dualling: Luncarty to Pass of Birnam project.

A9 Dualling: Luncarty to Pass of Birnam - Construction update - Autumn 2020

11 Jan 2021

Road surfacing works progressed at pace along the mainline A9 with significant progress noticeable at various locations throughout the site.

A9 Dualling: Luncarty to Pass of Birnam - Construction update - Summer 2020

19 Nov 2020

By early June 2020, our contractor was able to proceed with planning and pre-start preparations on site, following the Scottish Government’s up-date to the construction sector guidance.

Construction site planning and pre-start preparations commence

8 Jun 2020

The Scottish Government has updated its construction sector guidance to move to Phase 1 of its route map for moving out of lockdown, allowing the construction industry to proceed with planning and pre-start preparations.

A9 Dualling: Luncarty to Pass of Birnam - Construction update - Spring 2020

1 Jun 2020

Following the Scottish Government announcement at the end of March, our contractor Balfour Beatty implemented a managed shutdown of the site, in line with the Government guidelines including physical distancing.

A9 Dualling: Luncarty to Pass of Birnam - Construction update - Winter 2019/20

1 Mar 2020

Despite adverse weather creating challenging working conditions in February, bridge beam lifting operations at Gelly overbridge were successfully completed during two overnight closures of the A9 on 18 and 19 February

Page 1 of 4