Draft Orders and Environmental Impact Assessment Report - A9/A96 Inshes to Smithton

Transport Scotland published draft Orders and an Environmental Impact Assessment Report (EIAR) for the proposed scheme on 13 September 2019 for formal comment. The Statutory Consultation Period closes on Friday 25 October 2019. Representations to the draft Orders, including Objections, can be made in writing to the following address:

Director of Major Projects
A9/A96 Inshes to Smithton
Transport Scotland
Buchanan House
58 Port Dundas Road
Glasgow
G4 0HF

Or by email to a9a96-inshes-smithton@transport.gov.scot


Draft Orders



Environmental Impact Assessment Report







Published Date 13 Sep 2019 Type Projects Mode of transport